HomeMy Public PortalAboutWeek of 1018 Work PlanAnticipated Work —Week of October 18, 2021
• 2020 Road Program & Common Street (Onyx Corporation)
o Punch list work (all work areas)
• 2021 Road Program (Lorusso Corporation)
o Punch list work (all work areas)
• Waverley Ave. Road Reconstruction (Lorusso Corporation)
o Punch list work
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Protect 2,
Project 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may
be temporary road closures and/or parking restrictions
• Water Service Replacement Program (Paolini LLC)
o Continue water service replacements at #204 Acton Street, #8, #12, #16-18, #24-26, #45-47 Oakland
Street; #23-25, #27-29 Morton Street; and #17-19 Howard Street
• Bromfield Street Water Main Replacement (Paolini LLC)
o Temporarily pave trenches and cleanup site
• Pavement Preservation —Mill & Overlay (Lorusso Corporation)
o Line painting as needed: Whites Ave. (Main St. to Hudson St.), Hudson St., Bancroft St. (Westminster
Ave. to Waverley Ave.), Homer St., Evans St. (#70 Evans St. to #113 Evans St.), Emerson Rd. (Main St. to
#34 Emerson Rd.), Whitman Rd. (Main St. to Town line), Stuart St.
• Sidewalk Rehabilitation (Century Paving)
o Continue sidewalk repairs on Bailey Road
o Depending on work progress, begin sidewalk repairs at 181-183 School Street, and Stoneleigh Road,
between Oakley Road and Stoneleigh Circle
• Line Painting (K5 Corporation)
o NIGHT WORK —line painting, town -wide
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed
below:
o Continue gas main replacement on Cottage Street
o Continue gas main replacement on Lovell Road
o Continue gas main replacement on George Street and Wilson Ave.
o Continue replacement of sidewalk panels damaged during gas main installation
o Begin permanent trench repairs on Poplar Street, Riverside Street, and Ladd Street
Note: All work is weather -dependent and subject to change.