HomeMy Public PortalAboutWeek of 1026 Work PlanAnticioated Work —Week of October 26. 2020
• Annual catch basin cleaning (BMC Corporation)
• Water Main Flushing Program Week 6
o Evening work, 7 PM to midnight
http://www.watertowndpw.org/DocumentCenter/View/1093/Flushing-Week-of-10-
26?bidld=
• Annual Town -wide water main leak detection survey (Liston Utility Services)
o Work is complete
• Line Painting (K5 Corporation)
o NIGHT WORK, dates TBD: Arsenal Park, Arlington Street, Maplewood Street, School Street,
Waverley Ave. and various other locations
• Common Street (Onyx Corporation)
o Street light installation pending Eversource connections
o Install resin crosswalks on Columbia Street and Common Street at Spring Street (Saturday,
October 24)
o Complete any remaining line painting/crosswalk installations
• Road Program (Onyx Corporation)
o Continue curb and sidewalk installation on Downey Street
o Continue curb and sidewalk installation on Frank Street and Louise Street
o Site cleanup/winter preparation on Nichols Ave.
o Strip asphalt on Wheeler Lane and begin grading and compaction
• Complete Streets Project (Onyx Corporation)
o No work planned
• Sewer System Rehabilitation (Commonwealth Construction)
o Install drain manhole on School Street near #181-183 and #185-187
• Sewer System Rehabilitation (Umbro & Sons Construction)
o Sewer repairs at various locations on Bailey Road and near #10 Stoneleigh Circle
o Clean and inspect sewer lines on Mt. Auburn Street between Otis Street and Stearns Road,
Russell Ave., Garfield Street, Marcia Road, Amherst Road and various surrounding streets
• Water Service Repairs (Commonwealth Construction)
o Begin water service replacements on Waverley Ave. between Belmont Street and Orchard
Street
• National Grid
Utility companies are responsible for notifying residents prior to conducting work, but planned work
is listed below:
o Continue gas main relays on Forest Street
o Continue gas service installations on Grandview Ave.
o Resume gas service installations on Duff Street
Note: All work is weather -dependent and subject to change.