HomeMy Public PortalAboutWeek of 1123 Work PlanAnticioated Work —Week of November 23. 2020
No work planned on Thursday, November 26 and Friday, November 27, except as noted
• Annual catch basin cleaning (BMC Corporation); BMC will be working on Friday, November 27
• Line Painting (K5 Corporation)
o NIGHT WORK, dates TBD: Arsenal Park, Arlington Street, Maplewood Street, School Street,
Waverley Ave. and various other locations
• Common Street (Onyx Corporation)
o Install remaining street lights on Common Street
• Road Program (Onyx Corporation)
o Install guardrail on Bellevue Road
o Top course paving: Monday on Frank Street, Louise Street and Downey Street; Tuesday on
Bellevue Road and Kimball Road
o Loam and seed Frank Street and Louise Street
o Various cleanup/punch list work on all streets
• Sewer System Rehabilitation (Commonwealth Construction)
o Continue work on School Street near #181-183 and #185-187 pending delivery of additional
structure
• Sewer System Rehabilitation (Umbro & Sons Construction)
o Sewer line replacement on Gill Road at Sycamore Street
o Clean and inspect sewer lines (Inland Waters) on California Street, California Park and
Chandler Street
• Water Service Repairs (Commonwealth Construction)
o Begin water service replacements on Alden Road and Sheldon Road
• National Grid
Utility companies are responsible for notifying residents prior to conducting work, but planned work
is listed below:
o Continue gas service relays on Forest Street
o Continue gas service relays on Duff Street
Note: All work is weather -dependent and subject to change.