HomeMy Public PortalAboutWeek of 1206 Work PlanAnticipated Work —Week of December 6. 2021
• Fall 2021 Complete Streets Work (Lorusso Corporation)
o Continue pedestrian crossing improvements at Casey Park
• 2020 Sanitary Sewer Investigations (Umbra Construction)
o Inland Waters will perform warranty inspections in the work area
• 2021 Sanitary Sewer Investigations (National Water Main)
o Contractor will be cleaning and inspecting various sewer lines (7:00 AM — 4:00 PM) within the Protect 2,
Project 3 and 4 work areas. No interruption of water or sewer service is anticipated, however there may
be temporary road closures and/or parking restrictions
• Sanitary Sewer Rehabilitations Contract 21-01S (National Water Main)
o Contractor will continue cleaning and inspection of various sewer and drain mains within the project
area
• Survey crews will be performing surveys of Highland Ave., Morse Street and Fifth Avenue. Note that street
surveys may include also include survey within 25-feet of the street layout.
• Test pits are scheduled on Boylston Street (Fairfield Street to Porter Street), Chester Street, and Locke Street
• National Grid Gas Work
Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed
below:
o Continue gas main replacement on Lovell Road
o Continue gas main replacement on Winter Street
o Continue gas main replacement on Pine Street and Nash Street
o Continue replacement of sidewalk panels damaged during gas main installation
• Eversource
Utility companies are responsible for notifying residents prior to conducting work, but planned work is listed
below:
o Continue conduit installation on Forest Street (Main Street to Linear Park)
Note: All work is weather -dependent and subject to change.