HomeMy Public PortalAboutWeek of 1221 Work PlanAnticioated Work —Week of December 21. 2020
• Annual catch basin cleaning (BMC Corporation) on hold
• Common Street (Onyx Corporation)
o Work complete for the season
• Road Program (Onyx Corporation)
o Work complete for the season
o Wheeler Lane top course, Nichols Ave. curb and sidewalk construction to resume in spring
o Remaining punch list work to be completed in the spring
• Sewer System Rehabilitation (Commonwealth Construction)
o Final trench paving rescheduled for spring
• Sewer System Rehabilitation (Umbro & Sons Construction)
o Sewer repairs on Bailey Road between #86 and #90 Bailey Road, anticipate two days work
o No work planned week of December 28, 2020
• National Grid
Utility companies are responsible for notifying residents prior to conducting work, but planned work
is listed below:
o Continue gas service relays on Whites Ave.
o Continue gas service relays on Duff Street
o Continue gas main replacement on Taylor Street
o No work Wednesday, December 23; work resumes Monday, January 4, 2021
Note: All work is weather -dependent and subject to change.