Loading...
HomeMy Public PortalAboutBromfield Street Look-ahead 0708212021 Water Main Replacement Program Bromfield Street Contractor: A.D Paolini LLC Three week look -ahead: Week of 7/12 • Setting up erosion control (1.S Days) • Setting up bypass (2.S Days) • Flushing and chlorinating Bypass. Week of 7/19 Testing Bypass (1 Day) Test Pits if possible (2 Days) Finishing Bypass setup dependent on test results (2 Days) Week of 7/26 • Schedule first Tie-in and begin trunkline ALL WORK TENTATIVE AND SUBJECT TO CHANGE