HomeMy Public PortalAboutBromfield Street Look-ahead 0708212021 Water Main Replacement Program
Bromfield Street
Contractor: A.D Paolini LLC
Three week look -ahead:
Week of 7/12
• Setting up erosion control (1.S Days)
• Setting up bypass (2.S Days)
• Flushing and chlorinating Bypass.
Week of 7/19
Testing Bypass (1 Day)
Test Pits if possible (2 Days)
Finishing Bypass setup dependent on test results (2 Days)
Week of 7/26
• Schedule first Tie-in and begin trunkline
ALL WORK TENTATIVE AND SUBJECT TO CHANGE