RE: BOW Meeting 7.29.21
Approval of Change Order#30 Contract R-37463
Dear Board of Public Works and Safety Members:
The Department of Infrastructure & Development is requesting approval of Change Order#30 to
Contract R-37463, in an amount not to exceed $173,590.76, with Indiana Department of
Transportation. This is the final change order for cost adjustment for claim resolution.