HomeMy Public PortalAbout2012-29 Approving change order to the agreement with Eastman Aggregate EnterprisesRESOLUTION NO. 2012-29
A CAPITAL PROJECT AUTHORIZING RESOLUTION OF
THE VILLAGE COUNCIL OF THE VILLAGE OF KEY
BISCAYNE, FLORIDA, APPROVING A CHANGE ORDER TO
THE AGREEMENT BETWEEN THE VILLAGE AND
EASTMAN AGGREGATE ENTERPRISES, LLC FOR THE
BEACH RENOURISHMENT PROJECT; PROVIDING FOR
AUTHORIZATION; AND PROVIDING FOR AN EFFECTIVE
DATE.
WHEREAS,on April 24, 2012, the Village of Key Biscayne (the "Village") entered into an
Agreement with Eastman Aggregate Enterprises, LLC for the construction of the Village's Beach
Renourishment Project (the "Project"); and
WHEREAS, the Village's Engineer for the Project, Coastal Systems International, Inc., has
recently advised the Village that a change order consisting of an additional 9,500 tons of fill costing
$244,000, as further described in Exhibit "A," is necessary to complete the Project (the "Change
Order"); and
WHEREAS, the Village Council desires to approve the Change Order in order to complete
the Project and authorize the Village Manager to execute the same; and
WHEREAS, the Village Council finds that this Resolution is in the best interest and welfare
of the residents of the Village.
NOW, THEREFORE, BE IT RESOLVED BY THE VILLAGE COUNCIL OF THE
VILLAGE OF KEY BISCAYNE, FLORIDA, AS FOLLOWS:
Section 1. Recitals Adopted. Each of the above stated recitals are hereby adopted,
confirmed and incorporated herein
Section 2. Change Order Approved. The Village Council hereby approves the Change
Order attached as Exhibit "A."
Section 3, Village Manager Authorized. The Village Manager is hereby authorized
to execute the Change Order attached a:, Exnibit "A."
Section 4. Effective Date. This Resolution shall be effective imrnediately upon
adoption.
PASSED AND ADOPTED this 3rd day of July, 2012.
ATTFST:
MAY I R FRANKLIN H. APLAN
CONCEIITA ALV AREZ, MMC, VILLAGE CLE
APPROVED AS 7'O FORM AND LEGAL SI FFFICI
2
EXHIBIT "A"
Project: Village of Key Biscayne Beach Renourishment
Construction Cost Summary - Initial Values and Change Order
June 28, 2012
Initial Design: 31,000 cubic yards (46,500 tons
Item #
Description
Cost
Unit Cost
(per ton)
Notes
1
Mobilization/ Demobilization
$140,072.00
$3.01
Does not apply to
Change Order
2
Beach Fill
$1,187,145.00
$25.53
3
Geotechnical Testing
$6,804.00
$0.15
4
Beach Tilling
$16,125.00
$0.35
5
Turbidity Monitoring
$28,165.00
$0.61
6
Vibration Control and
Monitoring
$66,112.00
$1.42
7
Tolls
$24,918.75
$11.25
Unit Cost is per truck
hauling 21 tons
8
Performance Bond
$22,040.13
$0.47
9
* Owner Contingency 5%
g y
$78,493.78
$1.69
Does not apply to
Change Order
Total Unit Price per ton for Change Order
(excluding tolls, contingency & mobilization/demobilization):
Modified Design: 37,500 cubic yards (56,250 tons)
Additional Material : 6,500 cubic yards (9,750 tons)
Change Order Request
$28.52
Item
Description
Quantity
Unit Cost
TOTAL
1
Beach Fill (tons)
9750
$28.52
$278,070.00
2
Tolls (loads)
443
$11.25
$4,983.75
3
*Seaweed Removal (days)
6
$2,500.00
$15,000.00
Total Construction Change Order
Additional Consulting Fees (See enclosed Coastal Systems Proposal)
$298,053.75
1y41 i il' al Io-l�i r iii lv' � � I lilll9'i ldxliil N'I"� P N
� y'��, I d� lyil !�' ,,yIG'91I411 �
�, Illil{i lii {�14ik yyo-q,' . fifV 91,,l Vr{ ,
tl l'i yy„�i Snl w,i3"'y' ��rl, 1 S
�4lE� `EeP :�w 'I `r `°1r.
I mi �>t� "l`,1 "Q141141y4&~,pl({�t1 y �I��N I,d'
1' °. `.t .4�� .0 i s , `x lr,'�" �$
4i l ll lir '� ��u '
�'1ill'igd �P.1 x
'f
Mt.. ,
iti � �N
i��•, .'[:
V"111py r
VN,Npy1YYo- 3ky°` gi'},u
IV'�N"'P V'iil 1"
I,I; ; � ,�^
Xi14;
� �,�54, g`
IVI IV
61
rt!1 I , l d 'i
1 VI' Ip� � �I�I�I � g1� h61�
u, ., �, �,,
�
tv`rs P o -P1
j§ e M
I,T `y
d ' � � Sn `'I
' t r
�' �y o-4' 4 "�
Y'f' € .,,
,}€,} ( ! .
.P v
lsyPy iFl ���i�l �o I�l
,,. l
s z
li i� 1p,
. 4
, i
ii
I; i
wi
',I"�h•'"
Part 4 Permit Modifications
a.
b.
Permit Modifications
6
18
46
33
46
12
$ 19,710 $ 24,845
Seaweed Processing
2
7 5
26
3
$ 5,135
Grand Total
Grand Total After Contingency is Applied
* The remaining balance of the Owner Contingency is $63,493.78.
$322,898.75
$244,404.97
C0AS1.11.
St STEMS
1 114\,)11)1,1
COASTAL SYSTEMS INTERNATIONAL, INC.
464 South Dixie Highway • Coral Gables, Florida 33146
Tel: 305-661-3655 • Fax: 305-661-1914
www.coastalsystemsint.com
June 22, 2012
Mr. John Gilbert, Village Manager
VILLAGE OF KEY BISCAYNE
88 West McIntyre Street
Key Biscayne, Florida 33149
135040.02-A5
RE: PERMIT MODIFICATION REQUESTS FOR THE VILLAGE OF KEY BISCAYNE BEACH
RENOURISHMENT PROJECT, VILLAGE OF KEY BISCAYNE, MIAMI-DADE COUNTY,
FLORIDA
Dear Mr. Gilbert:
Pursuant to our recent discussions, this is to submit a Proposal Addendum to the Village of Key
Biscayne (Village) for consulting services related to modifying the permits issued by the Miami -
Dade County Permitting, Environment and Regulatory Affairs Department (PERA), Florida
Department of Environmental Protection (DEP), and U.S. Army Corps of Engineers (Corps)
authorizing the Key Biscayne Beach Renourishment Project (Project).
Pre -construction beach profile surveys and pre -construction biological resource assessments
were conducted in late May 2012, as required by environmental regulatory permits, pursuant to
Parts 15(b) and 17(a)(i) of our Contract with the Village. This surveying must be conducted
immediately prior to commencement of construction to document the current physical and
biological beach and resource conditions. Additionally, the Project permits require the seagrass
survey to be conducted during the seagrass growing season, which is from June 1 through
September 30. The Project was redesigned under Part 14 of our Contract with the Village to
account for changes in the elevation of the beach due to continued erosion since the time of
application and natural fluctuations in the limits of the seagrass beds just offshore of the Village.
Based upon an engineering analysis of the information obtained during the preconstruction
physical and biological surveys and the redesign of the beach within the permitted construction
templates, Coastal Systems recommends placement of additional sand to provide minimal storm
protection to the Village and to take advantage of the current contractor mobilization. Prior to
placement of the additional recommended fill volume, modifications to the environmental
permits are required. This scope of services includes preparation and processing of permit
modification requests to PERA, DEP, and the Corps by Coastal Systems.
The following work task describes the scope of work to be performed by Coastal Systems to
prepare and process environmental permit modifications for the Village:
Coastal, Environmental, Civil Eneineerinz and Manaeement
135040.02-A5
Mr. John Gilbert
June 22, 2012
Page 2
PART 4 — PERMIT MODIFICATION REQUEST AND PROCESSING
a. Permit Modification Request and Processing: Coastal Systems will prepare and process
permit modification requests to PERA, DEP, and the Corps seeking expedited authorization
of the proposed Project revisions. An exhibit will be prepared in support of the requests
depicting the permitted and proposed construction toe of fill (CTOF), the 2010 and 2012
surveyed seagrass limits, the permitted and proposed equilibrium toe of fill (ETOF) based
upon the DEAN Method, and the permitted ETOF based upon the Profile Translation Method
overlaid on current aerial photography of the Project site. The Modification Requests will
seek authorization for the placement of an additional 6,500 cubic yards of fill material within
the redesigned beach fill template. Coastal Systems will coordinate with agency staff to
facilitate an expedited review of the modification requests, including preparation of
responses to agency Requests for Additional Information (RAI), to ensure no lapse in
contractor production rates. The Village will provide the agencies with required permit
modification fees (amounts to be determined).
b. Wrack Line Processing: Excessive amounts of seaweed have been deposited along the
shoreline of the Project, and Coastal Systems has been coordinating with Village staff, the
Village beach maintenance contractor, the construction contractor, and the environmental
agency compliance staff. The remainder of the permitting budget was allocated to these
services from the PERA processing budget under the previous contract to begin the permit
modification process to place the excess seaweed in selected areas of the dune. Additional
budget is required to address the compliance issues to collect and place the seaweed in the
Crandon Park area, and to address the unauthorized placement of seaweed in selected areas of
the dunes.
GENERAL
These services will be provided as an Addendum to Coastal Systems' agreement with the Village
dated August 1, 2006. This Addendum is subject to the original agreement terms and conditions
and is valid to be executed for sixty (60) days. Fees and expenses will be invoiced each month in
accordance with our existing agreement with the Village.
Coastal, Environmental, Civil Engineering and Management
135040.02-A5
Mr. John Gilbert
June 22, 2012
Page 3
Please return an executed copy of this Addendum or a Notice to Proceed, which will serve as our
authorization to proceed with the scope of services herein. We look forward to continuing to
work with the Village through the implementation of this beach renourishment project. Should
you have any questions or require additional information, please do not hesitate to contact Ms.
Penny Cutt at 561-478-1004 ext. 311 or pcutti coastalsystemsint.com or me at 305-669-8650 or
tlankenship@coastalsystemsint.com.
Sincerely,
COASTAL SYSTEMS INTERNATIONAL, INC.
Timothy K. Blankenship, P.E.
Director
DATE:
SIGNED:
PRINT:
VILLAGE OF KEY BISCAYNE
Name
TKB:PC:mr
Enclosures
Title
File, TKB, CJB, LMS, PC, DM, Contract Book, Accounting
F \Protect\135040 02\Proposals \(12-06-21) PRO J filbert A-5 Permit Modification docx
Coastal. Environmental, Civil Engineering and Management