Loading...
HomeMy Public PortalAboutChange Order No. 9 to Contract No. 175-2019 - Kokosing Industrial - Miscellaneous Repairs RICHMOND SANITARY DISTRICT 2380 Liberty Avenue,Richmond,IN 47374 CHANGE ORDER#9 Change Order Date: February 22,2022 Owner: Richmond Sanitary District Contract No.: 175-2019 Contractor: Kokosing Industrial, Inc. Contract Date: November 25,2019 Project: Wm.E. Ross WWTP Phase I.Improvements Project Project No.: 13451. SRF Project No.: WW19018901 The Contract Documents are modified as follows upon execution of this Change Order and Approval by SRF: Item# Description Qty Change Unit Cost/Unit Total Increase/(Decrease) 44 Repair Sleeve on ALP at 6B 1 LS $ 4,162.00 $ 4,162.00 45 Raise FRP Baffle Wall 6"in 2A&3A 1 LS $ 5,500.00 $ 5,500.00. 46 Infrared Diagnostics Survey 1 LS $ 7,500.00 $ 7,500.00 48 Replace 24"Check Valve at IPB(Labor&Misc Parts Only) 1 LS $ 4,638.00 $ 4,638.00 49 Reimbursement for Grating on Aeration Effluent Channel 1 LS $ (3,031.60) $ (3,031.60) 50 Deletion of Submersible Pump Splice Boxes 1 LS $ (1,857.00) $ (1,857.00) NET CHANGE $ 16,911.40 Page 1 of 2 .. RICHMOND SANITARY DISTRICT 2380 Liberty Avenue,Richmond,IN 47374 CHANGE ORDER#9 Change Order Date: February 22,2022 Owner: Richmond Sanitary District Contract No.: 175-2019 Contractor. Kokosing Industrial,Inc. Contract Date: November 25,2019 Project Wm.E.Ross WWTP Phase I Improvements Project Project No.: 13451 SRF Project No.: WW19018901 CHANGE IN CONTRACT PRICE Original Contract Price: $13,875,000.00 Net change from Previous Change Orders: $824,853.44 Contract price prior to this Change Order: $14,699,853.44 Net increase/(decrease)of this Change Order: $ 16,911.40 Contract price with all approved Change Orders: $14,716,764.84 Percentage of increase/(decrease)with Change Orders: 6.07% CHANGE IN CONTRACT COMPLETION TIME Original Completion Time(days): (578 Substantial,639 Final) Net change from Previous Change Orders: (144 Substantial,143 Final) Completion time prior to this Change Order: (722 Substantial,782 Final) Net increase/decrease of this Change Order: (0 Substantial,30 Final) Completetion time with all approved Change Orders: (722 Substantial,812 Final) This Change Order is for complete and final settlement of all direct and indirect costs,impact costs and time extensions incurred at any time resulting from the performance of the changed work or associated claims. This Change Order is Subject to Final Approval by Funding Agency(SRF). Recommended by: j 02/16/2022 Richmond Sanitary District Engineer Date Accepted by: Owner: Richmond Sanitary District Board President Signature Date Contractor: 2 ii io in Kokosing Industrial,Inc. Author' d Signature Date Page 2 of 2