CAPITAL IMPROVEMENT PROGRAM
Introduction
The Capital Improvement Program is a multiyear workplan designed to facilitate policy decisions based on a citywide capital needs !.
assessment and corresponding fiscal analysis.One of the primary goals is to maximize the effective use of available financial
resources that are required to properly maintain and enhance certain publicly owned property.
This includes infrastructural systems,general government buildings,park lands and other appurtenant facilities. The intended
purpose of this document is to provide the City Council with a mechanism for selecting capital improvements,establishing workplan
priorities and determining funding sources.
Elements
A description of the various funding sources is contained in the first section of the report.This information is followed by a revenue
summary and an expenditure detail.The final element is comprised of a comprehensive project inventory.
Projects are listed categorically by program.The project detail also includes a brief explanation of the work to be performed,total
estimated cost and recommended funding sources.
Priorities
For FY 1995-1996,the Council Subcommittee established five priority categories.The categories are:
1. Essential-These are projects with direct public safety or high risk liability implications such as, installation of curb and gutters
where there are none or which badly need replacement,intersections without street lights, replacement or repair of sidewalks
with more than 1.5 inches of elevation from tree roots,etc.
2. Necessary-This category could best be described as,"It does not have public safety implications and is not mandated but
really does need to be done".These are projects such as re-roofing the multipurpose building and the La Rosa maintenance
facility or replacement of an HVAC system.
3. Mandated-These are ADA projects.
4. Routine-These are preventive maintenance projects such as painting,cape and slurry,and carpeting.They are scheduled on
a fixed interval but subject to annual review.
S. Discretionary-These are optional projects. Examples are the field lights at Oak Avenue School,upgrading parking lot lights,
installation of reflectors on streets,construction of additional bathrooms at Live Oak Park,and the pavilion. ',.
Summary
The Capital Improvement Program is revised annually to reflect various changes in the workplan,such as the status of incompleted
projects(carry-overs),priority adjustments,funding revisions and the addition of new items.A deliberate effort has been made to
minimize the use of General Funds wherever possible.The predetermined format of this report is not intended to preclude the City
Council from making any program adjustments.The workplan is subject to change and structured to be utilized by the City Council
as a functional management plan.
245
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
I
CAPITAL IMPROVEMENT PROGRAM
FUNDING SOURCE DESCRIPTION
General Fund
The General Fund is the primary source of revenue available to the City.General Funds are derived from state subventions generated
by sales and use taxes and interest accrued on City investments.General Funds are unrestricted and may be used for any purpose
by the local jurisdiction.
Proposition C Fund
Proposition C is the 1/2 cent sales tax for transit that was approved by the voters in November 1990.Collection of the tax began in
April 1991.The proceeds of the 1/2 cent sales tax are to be used to improve transit service and operations, reduce traffic congestion,
improve air quality,efficiently operate and improve the condition of the streets and freeways utilized by public transit,and reduce
foreign fuel dependence.
Gas Tax Fund
Proposition 111 and State Constitutional Amendment 1 of 1990 provided for an increase in the state gasoline tax.A portion of the
additional revenue collected is reallocated to counties and cities for street and highway programs.These revenues were restricted
and required the City to expend General Funds for street and highway improvements in an amount no less than the average
"maintenance of effort"(actual costs)established during FY 1987-1988, FY 1988-1989 and FY 1989-1990. The maintenance of effort
requirement was suspended for FY 1992-1993 through FY 2001-2002. The requirement was suspended permanently during
FY 1996-1997.
SB821 Fund
The allocation of funds to cities provides for construction of pedestrian or bicycle facilities, provided a plan has been developed
for improvements.These funds are also allowed to be used for ADA required curb cuts.
Sewer Reconstruction
This fund accounts for special fees collected to be used for sewer line replacement.
Park Acquisition Fund
The City has a Park Acquisition Fund which requires the payment of$500 per unit on any new dwelling constructed within the City.
Funds collected are used exclusively for the acquisition or improvement of community parks,in general conformance with the
priorities established by the City's General Plan.
Lighting&Landscape Fund
The City consolidated several county lighting districts into a municipal lighting district in 1969 to provide a Citywide lighting
program. Lighting District revenues are collected through a property tax(Ad Valorem)to pay for lighting, energy and maintenance
costs.With the passage of Proposition 13, property tax revenue was decreased substantially.
The City created a special assessment district pursuant to the provisions of the 1972 State Landscape&Lighting Act in order to
maintain and improve existing street lighting.The Lighting District was amended in Fiscal Year 1991-1992 to add other eligible
programs, including trees and parkways, park maintenance and traffic signal maintenance.
246
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM
FUNDING SOURCE SUMMARY
FISCALYEAR FISCALYEAR FISCAL YEAR
2013-2014 2014-2015 2015-2016
Funding Source Abbreviations Estimated Proposed Proposed
General Fund GF 302,200 565,525 -
General Fund(Received from Cal-Frans) GF-CT 332,970 - -
General Fund-Economic Development GF-ED 2,268,420 -
(and Assigned General Fund) 340,000 225,000
Proposition A PROP A 1,500,000 - -
Proposition C PROP C 80,000 175,000 -
Gas Tax GT 225,000 1,535,000 455,000
Proposition 113 PROP 1B 10,000 - -
CDBG CDBG 115,500 200,000 -
Measure R MR 794,230 - -
Sewer Reconstruction SR 400,000 10,000 -
Highway Safety Improvement Program HSIP 340,000 1,253,200 -
Lighting/Landscape District L/LD 2,000,000 - -
Rubberized Asphalt Concrete Grant RAC 110,250 - -
Surface Transportation Program Local STPL 1,007,815 - -
Safe,Accountable,Flexible,Efficient SAFE LU 719,920 - -
Transportation Equity Act:A Legacy
for Users(SAFETEA-LU)
Environment Protection Agency EPA 194,000 - -
Beverage Container Reyclable(State Recycling Fund) BCR - - - i,
Safe Routes To School SR2S 431,900 - -
Bicycle Transportation Account BTA 713,000 205,425 -
Congestion Mitigation and Air Quality CMAQ 2,249,985 - -
i
TOTAL 14,135,190 3,944,150 680,000
247
r
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM
PROJECT COST SUMMARY
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2015 FISCAL YEAR 2015-2016
Proiect Expenditures Adopted Estimated Carry Over Proposed Carry Over Proposed
Parks-Maintenance/Facilities 110,500 84,700 - 102,000 - 225,000
Traffic Engineering
250,000 1.00,000 - 10,000 - -
Street Cleaning 300,000 - -
Traffic Signal Maintenance - - - 1.,392,900 - -
Street Construction/Maintenance 3,447,650 1.,682,900 519,750 1,485,000 - 455,000
N ±
W Street Construction/Maintenance 13,443,280 10,508,170 - - -
-
(For the Rosemead Boulevard Improvement Project Only)
Sidewalk Maintenance 295,000 115,500 - 200,000 -
General Government Buildings 1,701,175 1,643,920 4,500 30,000 -
Parking Facilities 230,000 - 200,000 - - -
TOTAL 19,777,605 14,135,190 724,250 3,219,900 - 680,000
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM PARKS-MAINTENANCE/FACILITIES
PROJECT DETAIL ACCT.NO.60-980-59-4810
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2015 FISCAL YEAR 2015-2016 '..
No. Praise Priority Adopted Estimated Carry Over Proposed Cann Over Proposed
P12-02 Citywide Parks&Open Space Master Plan (D) 70,000 OF 60,000 OF
P13-01 Additional Concrete for the Performing Arts (D)
Pavillion Area
P14-01 Repair Operable Walls in Community Center (D) 15,000 OF 14,200 OF - - - -
P14-02 Installation of Hand Dryers in Park Restrooms (D) 10,500 GF 10,500 OF - - - -
P14-03 New Playground Equipment for Temple City (D) 6,000 OF
Park 9,000 BCR
p 15,000 - - - -
P]5-01 Retrofit Existing Walkway Lights at Live Oak (1)) - - - 22,000 GP` - -
Park with LED Fixture Heads
P15-02 Public Art at Live Oak Park (D) - - - 25,000 OF - -
P15-03 Painting of Metal Poles and Rails at LOP (D) - - - 20,000 OF
P15-04 LOP and TC Parks Master Plan Development (D) - - - 35,000 GF - -
P16-01 Expansion of,LOP Community Center (D) - - - - - 225,000 GF
Recap of Funding Sources 101,500 GF 84,700 OF - 102,000 GF - 225,000 OF
9,000 BCR - - - - -
TOTAL CIP-PARKS-MAINT/FACILITIES 110,500 84,700 102,000 225,000
(E)=Essential (N)=Necessary (M)=Mandated (R)=Routine (D)=Discretionary
CITY
OF TEMPLE CITY
PROPOSED BUDGET '.
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM TRAFFIC ENGINEERING
PROJECT DETAIL ACCT.NO.60-980-62-4810
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2015 FISCAL YEAR 2015-2016 'i
No. Project Priority Adopted Estimated Carry ver Proposed Carry Over Proposed
P12-07 Citywide Traffic Calming Study Master Plan (N) 100,000 MR - - - _ -
P14-04 Citywide Traffic Calming Implementaton (N) 150,000 GF 100,000 GF - - - -
P15-05 Citywide Sewer Master Plan Update (N) - - - 10,000 SR - -
0
Recap of Funding Sources 1.50,000 GF 100,000 GF - - - -
100,000 MR - - - - -
10,000 SR '..
TOTAL CIP-TRAFFIC ENGINEERING 260,000 100,000 10,000 '..
(E)=Essential (I)=Necessary (M)=Mandated (R)=Routine (D)=Discretionary
i
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM STREET CLEANING
PROJECT DETAIL ACCT.NO. 60-950-72-4510
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2015 FISCAL YEAR 2015-2016
No. Project Prioritv Adopted Estimated Carry Over Proposed Carry Over Proposed
P14-05 Street Sweeping Signage (D) 300,000 GT - - - - -
Recap of Funding Sources 300,000 GT
TOTAL CIP-STREET CLEANING 300,000
(E)=Essential (N)=Necessary (M=Mandated (R)=Routine (D)=Discretionary
i
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM TRAFFIC SIGNAL MAINTENANCE
PROJECT DETAIL ACCT.NO. 60-950-73-4510
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2015 FISCAL YEAR 2015-2016
No. ProTect Priori t Adopted Estimated Carry Over Proposed Carry Over Proposed
P15-06 Upgrade Traffic Signals on Temple City Blvd. (N) 970,300 HSIP
between El Camino Real Avenue and Ellis Lane, 108,100 GF
and other safety improvements - - - 1,078,400 -
P15-07 Upgrade Traffic Signals Citywide and install (N) 282,900 HSIP
other Safety Improvements 31,600 GF
314,500
ti
Recap of Funding Sources 139,700 GF
1,253,200 HSIP
TOTAL CIP-STREET CLEANING 1,392,900
(E)=Essential (N)=Necessary (M)=Mandated (R)=Routine (D)=Discretionary
I
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM STREET CONSTRUCTION/MAINTENANCE
PROJECT DETAIL ACCT.NO.60-980-75-4810
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2015 FISCAL YEAR 2015-2016
No. ProTect Priorit Adopted Estimated Carry Over Proposed Carry Over Proposed
P08-07 Upgrade Server Line on Longden from (N) 400,000 SR 400,000 SR
Rosemead to Encinita 194,000 EPA 194,000 EPA
594,000 594,000 - - - -
P08-11 Rosemead Boulevard Improvement Project (N) 1,500,000 Prop A 1,500,000 Prop A
1,580,645 Prop C
14,465 Prop 111 10,000 Prop 1.B
794,230 NIR 794,230 MR
2,000,000 L/LD 2,000,000 LILD
1,007,815 STPL 1,007,815 STPL
340,000 HSIP 340,000 HSIP
eJ 719,920 SAFE-LU 719,920 SAFE-LU
w 110,250 RAC 110,250 RAC
1,350,000 GT
332,970 GF- CT 332,970 GF-CT
1,000,000 GF-ED 1,000,000 GF-ED
443,000 BTA 443,000 BTA
2,249,985 CMAQ 2,249,985 CMAQ
13,443,280 1.0,508,170 - - - -
P12-04 Citywide Upgrade Traffic Street Signage (NI) 300,000 MR - - 200,000 GT - -
P13-02 Repaving of Streets per Re-assessment (E) 150,000 GT 100,000 GT 50,000 GT 1,235,000 GT - 405,000 GT
Pavement Management Plan
P13-03 Generator for pump at Rosemead Boulevard (N) - - - - - -
P13-04 Redesign and Construction of Las Tunas Drive (N) 1,200,000 Prop C 80,000 Prop C 175,000 Prol - - -
P13-12 Bicycle Master Plan Implementation- (I) 479,900 BTA 270,000 BTA 205,425 BTA
Installation of 12.6 Miles of Class II&III 48,350 GF 30,000 GF 22,825 GF
Bicycle Lanes 528,250 300,000 228,250 - - -
(E)=Essential (N)=Necessary (NI)=Mandated (R)=Routine (D)=Discretionary
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
i
CAPITAL IMPROVEMENT PROGRAM STREET CONSTRUCTION/MAINTENANCE
PROJECT DETAIL ACCT.NO.60-950-75-4810
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2015 FISCAL YEAR 2015-2016
No. Project Prioritv Adopted Estimated Carry Over Proposed Carry Ovor Proposed
P13-13 Installation of 45 Separate Improvements (I) 631,900 SR2S 431,900 SR2S
around Nine School Sites 52,000 GF 52,000 OF
483,900 483,900 - - - -
P14-06 Citywido Street Striping (N) 125,000 GT 125,000 GT - 50,000 GT - 50,000 GT
P14-07 Catch basin inserts (E) 66,500 GF - 66,500 GF - - -
A
Recap of Funding Sources 166,850 GF 82,000 GF 89,325 GF
1,000,000 GF-ED 1,000,000 GF-ED
332,970 GF-CT 332,970 GF-CT
1,500,000 Prop 1,500,000 Prop
2,780,645 Prop C 80,000 Prop C 175,000 Prop C
14,465 Prop 113 10,000 Prop 1B
1,625,000 GT 225,000 GT 50,000 GT 1,485,000 GT 455,000 GT
1,094,230 MR 794,230 NIR
400,000 SR 400,000 SR j
2,000,000 L/LD 2,000,000 L/LD
1,007,815 STPL 1,007,815 STPL
340,000 HSIP 340,000 HSIP
719,920 SAFE LU 719,920 SAFE LU
110,250 RAC 110,250 RAC
194,000 EPA 194,000 EPA
922,900 BTA 713,000 BTA 205,425 BTA
431,900 SR2S 431,900 SR2S
2,249,985 CMAQ 2,249,985 CNIAQ
TOTAL CIP-STREET CONSTRUCTIONIMAINT. 16,890,930 12,191,070 519,750 1,485,000 455 000
(E)=Essential (N)=Necessary (M)=Mandated (R)=Routine (D)=Discretionary
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM SIDEWALK MAINTENANCE
PROJECT DETAIL ACCT.NO.60-980-76-4810
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2015 FISCAL YEAR 2015-2016
No. Proiect Priorit Adopted Estimated Carry Over Proposed Carry Over Proposed
P14-08 ADA Barrier Removal Program (M) 75,000 CDBG 7,500 - - - -
P14-14 Public Parking Lot ADA Accessibility (M) 115,000 CDBG 58,000 - - -
Improvement Project
P14-15 ADA Accessibility Improvement Temple (M) 105,000 CDBG 50,000 - - - -
City Boulevard Project ',,
P15-08 ADA Playground Improvement or ADA (NII) - - - 200,000 CDBG - -
Curb Ramps
Recap of Funding Sources 295,000 CDBG 115,500 CDBG 200,000 CDBG '..
TOTAL CIP-SIDEWALK MAINTENANCE 295,000 115,500 200,000
(E)=Essential (N)=Necessary (M)=Mandated (R)=Routine (D)=Discretionary
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM GENERAL GOVERNMENT BUILDINGS
PROJECT DETAIL ACCT.NO.60-980-81-4810
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2015 FISCAL YEAR 2015-2016
No. Project Priority Adopted Estimated Carly Over Proposed Carry Over Proposed
P10-05 Council Chamber Renovation (N) 340,000 GF 340,000 GF - - -
P13-06 Remote/Motorizing Access Gate for City Yard (D) 7,000 GF - - - -
P13-08 Redesign City Hall Lobby, Conference Room (D) 28,000 GF 20,000 GF - - - -
and Management Office '..
P14-09 City Hall Server Room HVAC (D) 15,000 GF 15,000 GF - - - -
P14-10 Repainting Inside City Hall (D) 30,000 GF - - - -
P14-11 Rebuild the Roof for the City Yard Buildings (D) 5,000 GF 500 GF 4,500 GF 10,000 GF -
P14-16 Purchase of 5922 Primrose Property (D) 1,276,175 GF-ED 1,268,420 GF-ED - - - -
P15-09 Upgrade of EOC Infrastructure (N) - - - 20,000 GF - -
Recap of Funding Sources 425,000 GF 375,500 GF 4,500 GF 30,000 GF
1,276,175 GF-ED 1,268,420 GF-ED
TOTAL CIP-GEN GOVT BLDGS 1,701,175 1,643,920 4,500 30,000
(E)=Essential (N)=Necessary (M) Mandated (R)=Routine (D)=Discretionary
CITY OF TEMPLE CITY
PROPOSED BUDGET
FY 2014-2016
CAPITAL IMPROVEMENT PROGRAM PARKING FACILITIES
PROJECT DETAIL ACCT.NO. 60-980-82-4810
FISCAL YEAR 2013-2014 FISCAL YEAR 2014-2016 FISCAL YEAR 2016-2016
No. Proiect Priori t Adopted Estimated Carry Over Proposed Carry Over Proposed
P14-12 South Parking Lot (D) 30,000 GT - - - - -
P14-13 Demolition and site preparation for 6800 (D) 200,000 GF - 200,000 GF - - -
Temple City Blvd.Parking Lot
Recap of Funding Sources 200,000 GF - 200,000 GF - - -
30,000 GT
TOTAL CIP-PARKING FACILITIES 230,000 2005000
(E)=Essential (N)=Necessary (M)=Mandated (R)=Routine (D)=Discretionary
CITY OF TEMPLE CITY
PROPOSED BUDGET FY 2014-15
CAPITAL IMPROVEMENT PROJECT RECAP
Project General Sewer
Number Description Fund Prop C Gas Tax CDBG Reconstr HSIP BTA Total
P12-04 Citywide Upgrade Traffic Street Signage 200,000 200,000
P13-02 Repaving of Streets per Re-assessment Pavement Management Plan 1,285,000 1,285,000
P13-04 Redesign and Construction of Las Tunas Drive Project 175,000 175,000
P13-12 Bicycle Master Plan Implementation-Installation of 12.6 Miles 22,825 205,425 228,250 '
P14-06 Citywide Street Striping(Slurry Seal Program) 50,000 50,000
P14-07 Catch Basin Inserts 66,500 66,500
P14-11 Rebuild the Roof for the City Yard Builidngs 14,500 14,500
N P14-13 Demolition and Site Preparation for 5800 T.C.Blvd Parking Lot 200,000 200,000
Cc P15-01 Retrofit Existing Walkway Lights at LOP with LED Fixed Heads 22,000 22,000
P15-02 Public Art at Live Oak Park 25,000 25,000
P15-03 Painting of Metal Poles and Rails at Live Oak Park 20,000 20,000
P15-04 LOP and TC Parks Master Plan Development 35,000 35,000
P15-05 Citywide Sewer Master Plan Update 10,000 10,000
P15-06 Upgrade Traffic Signals on Temple City Blvd.and Other Safety Improvements 108,100 970,300 1,078,400
P15-07 Upgrade Traffic Signals Citywide and Install Other Safety Improvements 31,600 282,900 314,500
P15-08 ADA Playground Improvement or ADA Curb Ramps 200,000 200,000
P15-09 Upgrade of EOC Infrastructure 20,000 20,000
Total 565,525 175,000 1,535,000 200,000 10,000 1,253,200 205,425 3,944,150