HomeMy Public PortalAboutChange Order No. 10 to Contract No. 175-2019 - Kokosing Industrial - Miscellaneous Repairs RICHMOND SANITARY DISTRICT
2380 Liberty Avenue,Richmond,IN 47374
CHANGE ORDER#10
Change Order Date: March 22,2022
Owner: Richmond Sanitary District Contract No.: 175-2019
Contractor: Kokosing Industrial,Inc. Contract Date: November 25,2019
Project: Wm.E.Ross WWTP Phase I Improvements Project Project No.: 13451
SRF Project No.: WW19018901
CHANGE IN CONTRACT PRICE
Original Contract Price: $13,875,000.00
Net change from Previous Change Orders: $841,764.84
Contract price prior to this Change Order: $14,716,764.84
Net increase/(decrease)of this Change Order: $ 12,821.00
Contract price with all approved Change Orders: $14,729,585.84
Percentage of increase/(decrease)with Change Orders: 6.16%
CHANGE IN CONTRACT COMPLETION TIME
Original Completion lime(days): (578 Substantial,639 Final)
Net change from Previous Change Orders: (144 Substantial,173 Final)
Completion time prior to this Change Order: (722 Substantial,812 Final)
Net increase/decrease of this Change Order: (0 Substantial,37 Final)
Completetion time with all approved Change Orders: (722 Substantial,849 Final)
This Change Order is for complete and final settlement of all direct and indirect costs,impact costs and time
extensions incurred at any time resulting from the performance of the changed work or associated claims.
This Change Order is Subject to Final Approval by Funding Agency(SRF).
,, 03/16/22
Recommended by:
Richmond Sanitary District Engineer Date
Accepted by:
Owner: i •,=3`�3/2-
Richmond Sanitary District oard resident Signature Date
Contractor:
31i to/22-
Kokosing Industrial,Inc. Autho ze Signature Date
Page 2 of 2
RICHMOND SANITARY DISTRICT
2380 Liberty Avenue, Richmond,IN 47374
CHANGE ORDER#10
Change Order Date: March 22,2022
Owner: Richmond Sanitary District Contract No.: 175-2019
Contractor: Kokosing Industrial,Inc. Contract Date: November 25,2019
Project: Wm. E. Ross WWTP Phase I Improvements Project Project No.: 13451
SRF Project No.: WW19018901
The Contract Documents are modified as follows upon execution of this Change Order and Approval by SRF:
Item# Description Qty Change Unit Cost/Unit Total Increase/(Decrease)
51 Installation of Sidewalks and Underdrain 1 LS $ 12,821.00 $ 12,821.00
NET CHANGE $ 12,821.00
Page 1 of 2