February 24, 2012
Brannon & Gillespie, LLC
12798 West Forest Hill Blvd, Ste 102
Wellington, FL 33414-4704
RE. • Gulfstream aerial to underground initiative
Mr. Brannon:
AT&T has received a request from you (or your company) to perform the following work:
RE: Undergrounding or aerial facilities in Gulfstream
Special construction charges apply to your request. A quotation preparation charge of $25,000must be paid in
advance to AT&T Florida to offset the expenditures incurred for providing the detailed special construction
quotation. After this payment is received, we will proceed with developing the detailed quotation charge for the
special construction associated with your request. After the quotation preparation payment has been received and
the detailed special construction charge has been developed, a contract with this information will be provided to
you for your approval. Once the agreement to pay the special construction charge is confirmed by returning the
original signed contract, AT&T will schedule the work to meet your request. You will be credited the quotation
preparation payment against the detailed special construction charge. This quotation preparation payment must be
received in the Manager Bill Center at the address shown below before AT&T Florida will proceed with any
work.
ff l can be of further assistance, please do not hesitate to contact me at 561-988-6535
Sincerely,
Outside Plant Enginer Contact Information
Printed Name Greg Kessell
Title Mgr Osp Planning & Design Engineering
Company AT&T Florida
Project # 8543825
Service Order N/A
Return this letter and payment to the address below. This letter must
accompany the payment in order for the Engineer shown above to be notified
to begin development of the detailed costs for your work request.
AT&T CWO Coordinator
3535 Colonnade Parkway
Room North W3D
Attention: Sandy Tribble
Birmingham, AL 35243
Contact Number: (205) 977-7181
k