Renee Basel
From:Rob McDonald <rmcdonald@seasidebuildersfla.com>
Sent:Saturday, July 27, 2013 7:08 PM
To:Danny Brannon
Subject:Fwd: Undergrounding Overhead facilities in Gulf Stream - 1200 N. Ocean Blvd
Danny,
Can we meet prior to August 2nd?
Thanks.
Sent from my Verizon Wireless 4G LTE DROID
-------- Original Message --------
Subject: Re: Undergrounding Overhead facilities in Gulf Stream - 1200 N. Ocean Blvd
From: Tom Laudani <tlaudani@northpointllc.com>
To: Danny Brannon <DBrannon@BnGEngineers.com>,Charles Arthus <Charles.Arthus@fpl.com>,John Lehr
<john_lehr@FPL.com>
CC: Robert McDonald <rmcdonald@seasidebuildersfla.com>," tlaudani@seasidebuildersfla.com"
<tlaudani@seasidebuildersfla.com>
This is an urgent matter that needs to be addressed asap. Please set up a meeting to review,also I will be away from
Aug2nd till Aug 11th.thanks
From: Danny Brannon <DBrannon@BnGEngineers.com>
Date: Sat, 27 Jul 2013 14:22:21 -0400
To: Charles Arthus <Charles.Arthus@fpl.com>, John Lehr <john_lehr@FPL.com>
Cc: Robert McDonald <rmcdonald@seasidebuildersfla.com>, <tlaudani@seasidebuildersfla.com>
Subject: Undergrounding Overhead facilities in Gulf Stream - 1200 N. Ocean Blvd
John,
The Town has received the bids on the undergrounding of the overhead lines. The Town has executed the contracts with
FPL and will begin the work as provided in the FPL plans by the end of September. In a meeting with the developers,
Seaside Builders, at 1200 N. Ocean Blvd, they have indicated that the plan for running power into these 6 new lots does
not comply with the plan agreed to with the developer during the platting process which was based on the FPL
undergrounding plan. I had sent Charles a copy of the FPL plan via email, but it could have been derailed by FPL’s email
security. It is critical that we have a meeting (Charles Arthus, John Lehr, Seaside Project Mgr Robert McDonald, Seaside
Principal Thomas Laudani, and myself) to get on the same page.
1
Change from original plan – Install two transformers on the south side.
Danny P. Brannon, P.E.
Brannon & Gillespie,
LLC
Consulting Engineers
12798 West Forest Hill Blvd, Ste 102
Wellington, FL 33414-4704
Off: (561)795-0833 - Cell: (561) 307-9454
Website: www.BnGEngineers.com