Renee Basel
From:Rob McDonald <rmcdonald@seasidebuildersfla.com>
Sent:Monday, July 29, 2013 5:02 PM
To:Arthus, Charles
Cc:Tom Laudani; Danny Brannon; Lehr, John; tlaudani@seasidebuildersfla.com
Subject:Re: Undergrounding Overhead facilities in Gulf Stream - 1200 N. Ocean Blvd
When is everyone available to meet.
Sent from my Verizon Wireless 4G LTE DROID
"Arthus, Charles" <Charles.Arthus@fpl.com> wrote:
Tom,
There is no plan to do anything else at this time. We will move forward as planned. At this time, you should pick up the
materials and install them per FPL drawing. AS a reminder, once you install all the materials, it will take about 8 weeks
for FPL to complete the job. I hope you install the materials soon so I can release the job. Should you have any other
questions, please contact me.
Regards,
Charles Arthus
9329 S Military Trl
Boyton Beach, FL 33436
Phone: \[561\] 742-2085
Fax: \[561\] 742.2016
From: Tom Laudani \[mailto:tlaudani@northpointllc.com\]
Sent: Saturday, July 27, 2013 5:09 PM
To: Danny Brannon; Arthus, Charles; Lehr, John
Cc: Robert McDonald; tlaudani@seasidebuildersfla.com
Subject: Re: Undergrounding Overhead facilities in Gulf Stream - 1200 N. Ocean Blvd
This is an urgent matter that needs to be addressed asap. Please set up a meeting to review,also I will be away from Aug2nd
till Aug 11th.thanks
From: Danny Brannon <DBrannon@BnGEngineers.com>
Date: Sat, 27 Jul 2013 14:22:21 -0400
To: Charles Arthus <Charles.Arthus@fpl.com>, John Lehr <john_lehr@FPL.com>
Cc: Robert McDonald <rmcdonald@seasidebuildersfla.com>, <tlaudani@seasidebuildersfla.com>
Subject: Undergrounding Overhead facilities in Gulf Stream - 1200 N. Ocean Blvd
1
John,
The Town has received the bids on the undergrounding of the overhead lines. The Town has executed the contracts with
FPL and will begin the work as provided in the FPL plans by the end of September. In a meeting with the developers,
Seaside Builders, at 1200 N. Ocean Blvd, they have indicated that the plan for running power into these 6 new lots does
not comply with the plan agreed to with the developer during the platting process which was based on the FPL
undergrounding plan. I had sent Charles a copy of the FPL plan via email, but it could have been derailed by FPL’s email
security. It is critical that we have a meeting (Charles Arthus, John Lehr, Seaside Project Mgr Robert McDonald, Seaside
Principal Thomas Laudani, and myself) to get on the same page.
Change from original plan – Install two transformers on the south side.
Danny P. Brannon, P.E.
Brannon & Gillespie,
LLC
Consulting Engineers
12798 West Forest Hill Blvd, Ste 102
Wellington, FL 33414-4704
Off: (561)795-0833 - Cell: (561) 307-9454
Website: www.BnGEngineers.com