HomeMy Public PortalAboutTask Order 2022-07 Foxwood Estates Low Pressure Sewer System DesignTASK ORDER 2022 - 07
THIS TASK ORDER IS ISSUED PURSUANT TO THE PROFESSIONAL ENGINEERING CONTINUING SERVICES CONTRACT DATED
MAY 3, 2021 (AGREEMENT), FOR THE CITY OF CRESTVIEW, FLORIDA, WHICH IS INCORPORATED HEREIN BY THIS REFERENCE,
WITH RESPECT TO
Professional Engineering and Consulting Services for the Foxwood Estates Low -
Pressure Sewer System Design
Article A. Purpose
The City of Crestview (City) annexed the Foxwood Estates Subdivision and golf course into the city
limits in recent years. This subdivision community is currently serviced with septic tanks for sewer
treatment and field line disposal. The City plans to convert the subdivision from septic tanks to
public sewer with the installation of a low-pressure sewer system in the Foxwood Subdivision. The
City has requested Jacobs Engineering Group Inc. (Jacobs) provide professional engineering services
to design the low-pressure sewer system mains and force main to connect to the 4 -inch low-
pressure main currently in construction on Antioch Road. The following sections outline the tasks for
this project.
Article B. Scope of Services:
The scope of services provided with this task order is detailed below.
Task 1— Design and Permitting
1.1 Site Survey - ROW
Jacobs will subcontract with a professional surveyor to conduct a topographic and utility survey of
the subdivision. The survey will be limited to the streets and areas within the right-of-way. The
survey file will be used as the basis for preparing the design documents.
1.2 Site Survey — Septic Tanks
The professional surveyor will field locate the existing septic tanks at each residence. The tank
locations will be documented in the complete site survey and will be available for utilization in the
future for completing the low-pressure infrastructure at each residence beyond the right-of-way.
1.3 Final Design Drawings (90% Design)
Jacobs will prepare 90% Design Drawings for the low-pressure sewer system for submission to the
City for review. The drawings will detail the locations for low-pressure mains installed on both sides
of the subdivision streets and 4 -inch force main along Antioch Road. The scope of work for this task
order is limited to work within the right-of-way. The design will include lateral service connections
to each property parcel capped at the right-of-way line.
It is assumed the low-pressure sewer system will be incorporated into the Blackwater Lift Station
and Force Main construction contract. Therefore, Jacobs will not be responsible for preparing front-
end or technical specifications nor preparing a bid package. Jacobs will coordinate with the
construction Contractor to discuss construction methods that may be beneficial in preparing the
design documents.
A review meeting will be conducted to review the final design drawings and solicit/receive
comments. Jacobs project manager and project engineer will attend the meeting. Agreed upon
comments will be incorporated into the 100% design drawings.
1.4 Permitting
Jacobs will prepare the application for wastewater permits to authorize the construction and
operation of the new low-pressure sewer force mains. Jacobs submit FDEP form 62-604.300(3)(a),
Notification/Application for Constructing a Domestic Wastewater Collection/Transmissions System
application.
Jacobs will provide written responses for one (1) request for additional information submitted by
FDEP to the City.
Jacobs will prepare and submit up to two (2) Notification of Completion of Construction for a
Domestic Wastewater Collection/Transmission System applications to FDEP.
1.5 Construction Drawings (100% Design)
The purpose of this task is to finalize the contract drawings. Jacobs will incorporate the agreed upon
comments into the 100% design drawings and will prepare a change order form to incorporate the
documents into the Blackwater contract.
Deliverables
Under this subtask, Jacobs will deliver to City the following items:
• 90% Design Drawings
• FDEP 62-604.300(3)(a) Permit Application
• Notification of Completion of Construction for a Domestic Wastewater System
• 100% Design Drawings
• Change Order Documents
Meetings
• 90% Design Review Meeting
Task 1 Assumptions
• The design documents will only include the low-pressure mains within the right-of-way. Work
associated with septic tank abandonment, grinder pump stations, and service laterals outside
the right-of-way are outside this scope of work.
• Design of the low-pressure sewer will be based on the attached schematic provided by the City.
• Jacobs will identify the location for placement of lateral service connections but cannot
guarantee their alignment with the grinder pump stations since the work outside the right-of-
way is outside this scope of work.
2
• The design drawings will include plan view drawings for the sewer mains. No profile view
drawings of the sewer mains will be prepared.
• Front-end documents and general project related Division 01 specifications will not be included
within this Task Order. It is assumed this work will be added to the Blackwater Lift Station and
Force Main contract documents.
• Technical specifications will also not be prepared as they are generally included with the
Blackwater Lift Station and Force Main contract documents. Product specific data not previously
included in the Blackwater contract documents will be added to the design drawings with notes
and or written in the change order documents.
• The City will pay FDEP permit application fees.
• It is anticipated to take approximately 4 weeks for FDEP permit review and execution.
• No additional permit applications are assumed to be required nor are assumed to be within
Jacobs current scope.
• Task 1.2 assumes up to 150 septic tank locations will be surveyed within the subdivision.
• It is assumed the City will coordinate with Florida Power and Light and pay for a new power
pole, meter, and service installation.
• It is assumed that only one combined set of design drawings will be prepared and a separate
equipment procurement package will not be prepared in this scope.
• Geotechnical testing is not included in this task order.
Task 2 — Services During Construction
Jacobs will provide limited engineering services during construction for the construction of the
Blackwater Lift Station and Force Main project and this addition of the low-pressure sewer system in
the Foxwood Estates Subdivision. Items under this task generally include:
• Submittal Review
• Response to requests for information
• Preparation of change orders
• Contract closeout documentation
• (8) "As -needed" site visits
• (8) Monthly site visits
Final Inspection
Jacobs will review the work at the substantial completion and final stages. Jacobs will prepare one
(1) punch list of items requiring completion or correction. Jacobs will make recommendations to City
regarding acceptance of the work based on the results of the final inspection.
Task 2 Assumptions
3
• Site visits are anticipated to be such that it can maximize the purpose of the visit at key
milestones during construction on an "as -needed" basis. Each site visit will require
approximately 4 hours, including travel, field observation and report development.
• It is assumed that monthly progress meetings will not be conducted and are not included in this
task order.
Article C. Project Schedule
Work will begin upon execution of this task order. A preliminary milestone schedule is shown
below.
TABLE 1- PRELIMINARY SCHEDULE
Foxwood Estates Low -Pressure Sewer System Design
Task
Projected Completion Date
Task 1 - Design and Permitting
1.1 - Survey
1.2 - Survey (Septic Tanks)
1.3 - 90% Documents
1.4 - Permitting
1.5 - 100% Documents
Task 2 - Services During Construction
Within 8 weeks of NTP
Within 8 weeks of NTP
Within 8 weeks of completion of Task 1.1
Within 2 weeks of completion of Task 1.3
Within 3 weeks of receiving the approved
FDEP Permit
Within 8 months of completion of Task 1
4
Article D. Compensation
As compensation for providing the services described in Article B. Scope of Services of this task
order, the City shall pay Jacobs in accordance with Section 5 of the Agreement, on a time and
material basis with a not -to -exceed amount of $124,100. This amount includes work performed by
drilling and surveying subcontractors. The estimated breakdown of fees is shown in Table 2 below.
TABLE 2 - ESTIMATED FEE SUMMARY
Foxwood Estates Low -Pressure Sewer System Design
Task Estimated Fee Amount
Task 1 - Design and Permitting
1.1 - Survey $30,000
1.2 - Survey (Septic Tanks) $23,000
1.3 - 90% Documents $36,200
1.4 - Permitting $3,500
1.5 - 100% Documents $11,400
Task 2 - Services During Construction $20,000
Total $124,100
5
Article E. Authorized Representatives
The Authorized Representatives designated below are authorized to act with respect to Task
Order 2022-07. Communications between the parties and between Jacobs's subcontractors shall be
through the Authorized Representatives:
For the City of Crestview, Florida
For Jacobs Engineering Group Inc.
Name: Mike Criddle
Name Scott Jernigan
Address: 198 North Wilson Street
Crestview, Florida 32536
Address: 25 W. Cedar Street, Suite 350
Pensacola, Florida 32502
Telephone: (850) 682-6134
Telephone: (850) 941-7282
Article F. Authorization:
Task Order 2022-07 is effective as of 9 —1Z-- , 2022
Accepted for CITY by:
Accepted for Jacobs Engineering Group Inc. by:
2J-1q•e'ed
N .B. Whitten
Name: Nick Freeman, PE.
Title: Mayor
Title: Manager of Projects
6