Renee Basel
From:John Zoerhof <jzoerhof@HYPOWERINC.COM>
Sent:Monday, April 28, 2014 8:16 AM
To:Danny Brannon
Cc:Cliff Spitzer
Subject:RE: A05CK159 Primary Routing
Ok, thanks. Just checking
Thanks,
John Zoerhof
Division Manager – Power Services
From: Danny Brannon \[mailto:DBrannon@BnGEngineers.com\]
Sent: Monday, April 28, 2014 8:13 AM
To: John Zoerhof
Subject: Re: A05CK159 Primary Routing
Yes, that open delta station is on the return cables. That is to provide a pulling location without adding a pillbox . It
needs to be installed to plan so the loop sequencing is correct .
Danny Brannon, P. E.
Brannon & Gillespie LLC
Sent from my iPhone
On Apr 28, 2014, at 8:04 AM, John Zoerhof <jzoerhof@HYPOWERINC.COM> wrote:
Danny,
On the attached drawing I have circled what looks to be a TX connected to the
return conduits of the 2 phases from the Pump Station.
We are just verifying that is correct. Or should we connect to the conduits on the
way back instead.
,
Regards
John Zoerhof
Division Manager – Power Services
Direct 954.917.1439
Cell 954.448.0369
<image001.jpg>
954.978.9300 – Main 954.978.8666. - Fax
Please consider the environment before printing this e-mail
NOTICE: This email is intended solely for the use of the individual to whom it is addressed and may contain information that is privileged, confidential
or otherwise exempt from disclosure. If the reader of this email is not the intended recipient or the employee or agent responsible for delivering the
message to the intended recipient, you are hereby notified that any dissemination, distribution, or copying of this communication is strictly prohibited. If
you have received this communication in error, please immediately notify us by telephone and return the original message to us at the listed email
address. Thank You.
1
<A05CK159.pdf>
2