HomeMy Public PortalAboutTO 2023-03 Main Street Improvements Alday-HowellPTil
- Alday-Howeil
N _=.INl_r rIN ;, IN
Civil Engineering
Site and Subdivision Design
Environmental Permitting
Land Use Planning
CITY OF CRESTVIEW TASK ORDER 2023.03
THIS TASK ORDER IS ISSUED PURSUANT TO THE STANDARD MASTER AGREEMENT FOR PROFESSIONAL SERVICES
DATED MAY 11, 2021 (AGREEMENT), FOR THE CITY OF CRESTVIEW, FLORIDA, WHICH IS INCORPORATED HEREIN BY
THIS REFERENCE, WITH RESPECT TO
PROJECT: City of Crestview— Main Street Improvements
FOOT FPID # 449302.1.54-01
DATE: 511512023
SCOPE OF SERVICES:
• Task 1: Perform CEI services for the City of Crestview throughout the duration of the construction
activities for the above referenced project.
Task 1 Lump Sum: $280,670 (based on 365-day contract duration). A supplemental agreement will
be requested should the contract duration be extended beyond 365 days. See the man hour estimate
below:
Construction Days = 365 days to final completion (estimated) 52 weeks
CLASSIFICATION
Principal/Senior Project Engineer
Senior Inspector
Asphalt Plant Inspector
Inspector
Inspector's Aide
Contract Support Specialist
Secretary
MANHOURS
208
416
70
2,080
1,040
104
208
HOURLY RATE
$200
$75
$65
$65
$50
$65
$45
Total Hours = 3,918 Grand Total =
City of Crestview - Task Order 2023-03
COST
$41,600 4 hrs/week
$31,200 8 hrs/week
$4,550 7 days @ 10 hrslday
$135,200 40 hrs/week
$52,000 20 hrs/week
$6,760 2 hrs/week
$9,360 4 hrs/week
$280,670
Page 1 of 2
ACCEPTED BY:
John Feeney, PE
Atday-I-lowelt Engineering, inc.
4100 S. Ferdon Blvd, Suite B2
Crestview, FL 32536
(Tim Bolduc, City Manager)
City of Crestview
198 N. Wilson Street
Crestview, FL 32536
Date
Date
-2v23
City of Crestview - Task Order 2023-03 Page 2 of 2