HomeMy Public PortalAboutRE_ RCO 6247-001
Renee Basel
From:John Zoerhof <jzoerhof@HYPOWERINC.COM>
Sent:Tuesday, September 2, 2014 12:13 PM
To:Danny Brannon (DBrannon@BnGEngineers.com)
Subject:RE: RCO 6247-001
Attachments:Hypower RCO 6247-001.xlsx
Danny I have prepared an all inclusive CO for the lighting that might help. Take a look and let
me know your thoughts.
,
Regards
John Zoerhof
Division Manager – Power Services
Direct 954.917.1439
Cell 954.448.0369
954.978.9300 – Main 954.978.8666. - Fax
Please consider the environment before printing this e-mail
NOTICE: This email is intended solely for the use of the individual to whom it is addressed and may contain information that is privileged, confidential or otherwise exempt
from disclosure. If the reader of this email is not the intended recipient or the employee or agent responsible for delivering the message to the intended recipient, you are
hereby notified that any dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, please immediately
notify us by telephone and return the original message to us at the listed email address. Thank You.
From: John Zoerhof
Sent: Thursday, August 28, 2014 4:58 PM
To: Danny Brannon (DBrannon@BnGEngineers.com)
Subject: RCO 6247-001
Danny,
As discussed, here is the CO for the light pole by the police station for work completed to date.
Let me know if you would like another CO for the conduit or adjust this one
,
Regards
John Zoerhof
Division Manager – Power Services
Direct 954.917.1439
1
Cell 954.448.0369
954.978.9300 – Main 954.978.8666. - Fax
Please consider the environment before printing this e-mail
NOTICE: This email is intended solely for the use of the individual to whom it is addressed and may contain information that is privileged, confidential or otherwise exempt
from disclosure. If the reader of this email is not the intended recipient or the employee or agent responsible for delivering the message to the intended recipient, you are
hereby notified that any dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, please immediately
notify us by telephone and return the original message to us at the listed email address. Thank You.
2
5913 NW 31 AVERequest for Change Order6247-001
Fort Lauderdale, FL 33309Job Number2012-13-50
Date5/24/13
P 954-978-9300 F 954-978-8666Page1 OF 3
Location:
Narrative Description of Required Change
REMOVE STREET LIGHTING ALTERNATE LESS WORK PERFORMED TO DATE
Lighting Alternate removed from Contract
• Lighting along Ocean (Type S Poles & Fixtures) deleted due to FDOT issue
• Lighting on interior areas (Type S2 Poles and Fixtures) deferred pending
confirmation of design
• Ground Fixtures (Type FL ) deferred due to design / application clarifications
Work completed on this contract
• Procured / Replaced pole, fixture and base @ Police Station (See Sheet 3)
• Installed 2” UG Conduit to future FL location @ SE corner of Ocean & Pelican from
T-9 (186’ Bore)
• Installed 2” UG Conduit to Pole directly S of 1060 N Ocean from T-9 (150’ Bore)
• Installed 2” UG Conduit to Pole S of Pelican on W side of Andrews from T-6 (50’
Hand Trench Rock)
• Installed 2” UG Conduit to future S21 from T-6 (60’ Bore)
• Installed 2” UG Conduit to future ground light from S21 (30’ Hand Trench Rock)
• Installed 2” UG Conduit to future S22 from T-5 (40’ Bore)
• Installed Service HH @ future S22 location
• Installed 2” UG Conduit to Pole @ 4 Driftwood Landing from T-4 ( 30’ Hand Trench)
Change Order Cost from Breakdown Page 2
$ (213,611.20)
Change Order Cost from Breakdown Page 3
$ 10,097.61
Change Order Cost Total
$ (203,513.59)
Change Order Duration Impact
0
Submitted By:
Name &Title:John Zoerhof, Hypower, Inc
Recommended:
Name &Title:
Approved:
Name &Title:
Hypower reserves the right to correct this quote for errors and omissions.