TASK ORDER 2023-02
THIS TASK ORDER IS ISSUED PURSUANT TO THE STANDARD MASTER AGREEMENT FOR PROFESSIONAL SERVICES
DATED MAY 11, 2021 (AGREEMENT), FOR THE CITY OF CRESTVIEW, FLORIDA, WHICH IS INCORPORATED HEREIN BY
THIS REFERENCE, WITH RESPECT TO
Professional Engineering and Consulting Services for Design and Permitting of
Brookmeade Park Improvements Project.
Article A. Purpose
The purpose of this project is to develop plans for and permit the expansion of Brookmeade Park to include a
concession facility, RV camping sites, food truck parking, and event parking areas for the existing and proposed
amenities. The project is located along the east side of Brookmeade Drive, south of Covell Road. The Okaloosa County
Parcel ID number is: 28-3N-23-0000-0011-0000
The property listed above is owned by the City of Crestview (Client).
Article B. Scope of Services
Introduction
The purpose of Task Order 2023-02 is to authorize Alday-Howell Engineering, Inc. (AHE) to proceed with professional
engineering and consulting services for the development/expansion of the 17.92 acre Brookemeade Park. Central
sewer services are available via a proposed force main connection within the Brookemeade Drive right of way. Water
is also already located within the property and will provide sufficient capacity needed to the proposed park expansion.
Individual service connections for the new amenities will be part of this Scope. AHE is to prepare plans and calculations
necessary to obtain federal, state and local permit approvals for a development order to establish the park expansion
project and associated infrastructure onsite.
The scope of services provided with this task order is outlined in detail below.
Task 1— Site Investigations
Site -specific investigations will be required to obtain the field data needed to evaluate site characteristics, design
requirements, and potential impacts of the proposed development project.
Geotechnical Exploration
This subtask will be performed by Magnum Engineering, Inc. (MEI) and includes mobilization to the site, sampling and
testing of the existing soil, and preparing a Geotechnical report. MEI will perform the following investigations as part of
their analysis:
• Estimate Twelve (12) 5 -feet to 10 -feet deep Auger Borings in proposed pavement and stormwater areas
• Estimate One (1) Double Ring Infiltrometer Test (DRI) in proposed stormwater area
• Estimate Three (3) 25 -feet deep Standard Penetration Test (SPT) borings in proposed building areas.
Mailing Address
Post Office Box 494
Marianna, FL 32447
Marianna Office
3017 Highway 71 North
Marianna, FL 32446
info@aidavhowelt.com
Ph: (850) 526-2040
Fax: (850) 526-4740
Crestview Office
4100 S. Ferdon Blvd, Ste B2
Crestview, FL 32536
crestview@aldavhowell.com
Ph: (850) 634-6084
jIJj
� Alday-Howdll
ENGINEERING, INC.
Civil Engineering
Site and Subdivision Design
Environmental Permitting
Land Use Planning
• Engineering Evaluation and Report to include Site/Soil Preparation Recommendations, Pavement
Recommendations, Foundation Recommendations, and Soil Related information to aid in the design of an
effective stormwater system in accordance with ERP and/or local municipal regulations.
Task 2 — Conceptual Plan and Pre -Application Meeting
The intended outcome of this task will be to obtain preliminary design approval from the CLIENT for the park expansion
project. A concept plan will be developed to meet the requirements of the City of Crestview Land Development Code.
AHE will attend a pre -application meeting with City of Crestview Community Development Services and all other
appropriate parties to review the concept plan and obtain any additional questions that should be addressed in the
permit documents, construction plans and specifications.
Under this Task, AHE will deliver the following items:
• Conduct a field review of the site and coordinate with the client and other subcontractors.
• Prepare a concept plan for submittal to Community Development Services in accordance with the
City of Crestview submittal requirements for a Development Order. Sheets will include a single page
site plan with pertinent planning information. It should be noted that the City of Crestview Community
Development Services (CDS) allows the use of the ITE Parking Generation Manual in lieu of the
City's parking requirements in the Land Development Code. This approach will be used to reduce
the required parking onsite for the development. Based on conversations with CDS, this will not
require any additional data or reporting since it is directly from the ITE manual, as allowed by Section
8.06.06 E of the Land Development Code.
• Attend a Pre -Application meeting with City of Crestview Community Development Services.
Task 3 — Detailed Plans and Specifications for Permitting
Upon completion of the Conceptual Approval phases, AHE will provide design services to develop construction plans
and detailed technical specifications for the park expansion project utilizing the City of Crestview Land Development
Code.
Subtask 3.1- Utility Coordination
Utility Coordination for this project will be conducted by AHE. This coordination will include field meetings with individual
utility owners, as needed.
Subtask 3.2 — Permit Submittal
The Permit Submittal package will provide detailed Civil drawings that include a cover sheet, existing conditions plan,
demolition/erosion control plan, site paving and striping plan, lighting plan, grading and drainage plan, utility plan with
profiles, landscape plan, any special details required and a copy of the draft technical specifications for the project.
• This subtask will also include preparing stormwater calculations and report.
• Prepare and submit for NWFWMD Environmental Resource Permit (stormwater permit).
• Prepare gravity sewer connection plans including plan and profiles for the onsite portion. The sewer
design will also include a lift station design and connection to the existing force main along
Brookmeade Drive.
City of Crestview - Task Order 2022-02 Page 2 of 5
j%i Atday-Howell
111 ENGINEERING, INC.
Civil Engineering
Site and Subdivision Design
Environmental Permitting
Land Use Planning
Subtask 3.3 — Respond to Comments and Plan Revisions
This subtask will include providing responses to comments received from reviewers of the development order submittal
and other permit submittals. This will include a written response letter and revisions to the plans based on the comments
provided.
The intended outcome of this task will be to obtain construction permits from applicable agencies such as NWFWMD
and to obtain a Development Order from the City of Crestview for the planned work by the CLIENT.
Task 4 — Construction Plans and Specifications
Subtask 4.1- Construction Plans and Engineer's Opinion of Probable Construction Cost (EOPCC)
A detailed EOPCC will also be provided at this phase as well as final construction plans and detailed technical
specifications.
Under this Task, AHE will deliver all permits required for the construction of the proposed development project.
Assumptions
The following assumptions have been taken into consideration in the preparation of this Scope of Services and
compensation. These assumptions are based on the project scope, which is to deliver the CLIENT a completed set of
construction plans and specifications of sufficient detail to obtain a reasonably accurate bid for services to construct
the proposed improvements, for the selected contractor to be able to construct the improvements, to assist the CLIENT
with the monitoring of the construction of the project, and to provide limited post -construction assistance. Should
deviations from these assumptions be required to deliver the services provided in this Scope of Services, the scope of
work and compensation shall be modified accordingly and approved by the CLIENT in writing prior to executing the
changes to the Scope of Services. The assumptions are as follows:
• The CLIENT will be responsible for providing survey data and utility designations within the proposed project
limits and any areas that may need to be surveyed in order to construct the project.
• The CLIENT will be responsible for the acquisition of land needed to complete this project. This includes making
offers and negotiations with property owners.
• The CLIENT will conduct public awareness campaigns to inform stakeholders of the project and its anticipated
construction timelines.
• The CLIENT will pay all permit fees for applications and subsequent reviews
• It is understood that the CLIENT will perform all inspections of day-to-day construction activities.
• It is understood that the CLIENT will be responsible for the advertisement for bids related to the construction
of the project and shall qualify the bids received. This shall also include preparation bid documents.
Items not Included
Items that are not included in the task order may include, but are not limited to the following:
1. Geotechnical, surveying, landscape architecture, architecture, biological, and archeological services except
as specified above.
2. Electrical engineering.
3. Meetings with homeowners associations and adjacent property owners.
4. Request for services by the CLIENT that are not specifically described in the above services.
5. Request from govemmental agencies which require services not described in the Scope of Services.
City of Crestview - Task Order 2022-02 Page 3 of 5
� Alday-Howell
\� 1L ENGINEERING, INC.
Civil Engineering
Site and Subdivision Design
Environmental Permitting
Land Use Planning
6. Services associated with the permitting, design, and coordination of off -site utility extensions except as
specifically described in the above task.
7. Services associated with FEMA Floodplain mapping and permitting.
8. Services during construction.
9. Services required due to changes in codes and regulations that occur after the date of this agreement.
10. Service required for an off -site tum lane design and permitting that may arise as a condition of traffic approval.
11. Services associated with retaining wall design and permitting.
12. FDEP and/or COE dredge and fill permitting except as indicated in the Scope of Services.
13. Sewage treatment plants and sewage pumping stations, except as described above.
14. Consumptive Use/Well permitting with NWFWMD.
15. As -built survey.
16. Permitting fees. (Client will be responsible for paying all permit fees directly to the permit authority at the time
of submittal.)
Article C. Compensation Provisions
As compensation for providing the services described in Article B. Scope of Services in this task order, the CLIENT
shall pay AHE, in accordance with Section 5 of the Agreement, on a lump sum basis in the total amount of $220,590.
These fees will be billed monthly by percent of completion. The estimated breakdown of fees is shown in Table 1 below.
Table 1— Compensation
Milestone:
Task 1— Site Investigations
Task 2 — Concept Plan and Pre -Application Meeting
Task 3 — Detailed Plans and Specifications for Permits
Task 4 — Construction Plans and Specifications
Estimated Fee Amount:
$5,590
$12,500
$200,000
$2,500
Article D. Period of Service
Work will begin upon execution of this task order. A preliminary milestone schedule is shown below. The total estimated
timeframe to deliver the final construction plans is 26 weeks from task order execution.
Table 2 — Preliminary Schedule
Milestone: Estimated Fee Amount:
Task 1— Site Investigations
Task 2 — Concept Plan and Pre -Application Meeting 10 weeks from NTP
Task 3 — Detailed Plans and Specifications for Permits
Task 4 — Construction Plans and Specifications
6 weeks from NTP
26 weeks from NTP
Immediately upon approval of all permits
City of Crestview - Task Order 2022-02 Page 4 of 5
1 Ir Alday-Howell
11111 rmmi ENGINEERING, INC.
Civil Engineering
Site and Subdivision Design
Environmental Permitting
Land Use Planning
Article E. Authorized Representatives
The Authorized Representatives designated below are authorized to act with respect to Task Order 2023-02.
Communications between the parties and between AHE's subcontractors shall be through the Authorized
Representatives:
For the City of Crestview, FL _
For Alday-Howell Engineering, Inc.
Name: Jayce Vanderford
Name: John Feeney, PE
Address: P.O. Drawer 1209
Crestview, FL 32536
Address: 4100 S. Ferdon Boulevard, Suite B2
Crestview, FL 32536
Telephone: (850) 682-6134
Telephone: mg 634-6084
Email: jaycevanderford(cityofcrestview.org
Email: John@aldayhowell.com
Article F. Authorization
Task Order 2023-02 is effective as of
Accepted for CLIENT by:
Name: Tim Bolduc
Title: City Manager
2023
Accepted for Alday-Howell Engineering, Inc.
Travis Howell
2023.10.12 16:49:22 -05'00'
Name: Travis Howell, PE
Title: Principa ce President
City of Crestview - Task Order 2022-02 Page 5 of 5