HomeMy Public PortalAboutChange Order No. 3 to Contract No. 164-2021 - SAK Construction - sewer lining RICHMOND SANITARY DISTRICT 2380 Liberty Avenue,Richmond,IN 47374 CHANGE ORDER#3 Change Order Date: July 12,2022 Owner: Richmond Sanitary District Contract No.: 164-2021 Contractor: SAK Construction, LLC Contract Date: December 8,2021 Project: 2021 Sewer Lining Project Project No.: The Contract Documents are modified as follows upon execution of this Change Order: Item# Description city Change Unit Cost/Unit Total Increase/(Decrease) (Undistributed) CIPP Lining-10"Sewer 1 LF $ 30.00 $ 30.00 (Undistributed) CIPP Lining-8"Sewer -476 LF $ 23.50 $ (11,186.00) (Undistributed) CIPP Lining-18"Sewer 10 LF $ 108.00 $ 1,080.00 (Undistributed) CIPP Lining-24"Sewer 5 LF $ 100.00 $ 500.00 2 Protruding Tap Removal(Undistributed) 12 EA $ 500.00 $ 6,000.00 51 Lateral/Sewer Reinstatement -82 EA $ 25.00 $ (2,050.00) Add 57 Special Cleaning 1 LS $ 8,782.40 $ 8,782.40 NET CHANGE $ 3,156.40 Page 1 of 2 RICHMOND SANITARY DISTRICT 2380 Liberty Avenue,Richmond,IN 47374 CHANGE ORDER#3 Change Order Date: July 12,2022 Owner: Richmond Sanitary District Contract No.: 164-2021 Contractor: SAK Construction, LLC Contract Date: December 8,2021 Project: 2021 Sewer Lining Project Project No.: CHANGE IN CONTRACT PRICE Original Contract Price: $347,831.50 Net change from Previous Change Orders: $51,361.25 Contract price prior to this Change Order: $399,192.75 Net increase/(decrease)of this Change Order: $3,156.40 Contract price with all approved Change Orders: $402,349.15 Percentage of increase/(decrease)with Change Orders: 15.67% CHANGE IN CONTRACT COMPLETION TIME Original Completion Time(days): (225 Substantial,255 Final) Net change from Previous Change Orders: (45 Substantial,45 Final) Completion time prior to this Change Order: (270 Substantial,300 Final) Net increase/decrease of this Change Order: (7 Substantial,7 Final) Completetion time with all approved Change Orders: (277 Substantial,307 Final) This Change Order is for complete and final settlement of all direct and indirect costs,impact costs and time extensions incurred at any time resulting from the performance of the changed work or associated claims. Recommended by: CS'/'— Zt,GX__-- 10/28/2022 Richmond Sanitary District Engineer Date Accepted by: Owner: Richmond Sanitary District Board President Signature Date Contractor: C -Z:2- 10.28.2022 SAK Construction, LLC Authorized Signature Date Page 2 of 2