INSPECTION SCHEDULE
The building permit holder is responsible for arranging the required inspections before proceeding with additional work. Failure to do
so may result in reinspection fees, having to expose concealed work, or issuance of a Stop Work Order. Inspections must be scheduled
at least 24 hours in advance by emailing the building department at Building@Brewster-MA.Gov or by calling (508) 896-3701 x1125.
We Do Not accept inspection requests via the ViewPoint/OpenGov online permitting system!!
Sono-tubes/Footings
After sono-tubes/footing forms are in place, 48” min. depth from grade, but before any concrete is poured
Pre-cast footings: 48” depth min. from grade, must be inspected prior to backfill
Footings & Foundations with Rebar
Inspection of UFER Ground by Wiring Inspector
First inspection of footings with forms, rebar, and UFER Ground in place before concrete is poured
Second inspection after walls are poured, stripped, and waterproofed, prior to backfilling
Footing & Foundation without Rebar
Shallow footings/Mono-pours for accessory buildings: inspection prior to pour
Footing form inspection prior to footing being poured and walls are formed
Second inspection after walls are poured and stripped, before backfill and after waterproofing
Sheathing/Nailing
After exterior plywood is installed, prior to house wrap being installed and prior to installation of siding and trim or windows.
Structural/Wind Code elements such as roof rafter strapping and portal frame embedded tie-downs must be installed/exposed
Deck Frame
After Sono-tube/footing inspection (see above)
After framing and all structural connections including lateral tension devices are complete
Prior to covering framing with decking or trim
Rough Frame
After being made tight to the weather
After any required rough electrical, plumbing and gas inspections are complete
After any required HVAC ducting or sheet metal work is installed and inspected
After all required fire caulk and fire blocking are complete
Structure must meet MA Wind Code Requirements 780 CMR 1611.0 Wind Load in addition to standard Building Code Requirements
Insulation
After Framing inspection is approved, after insulation, vapor barriers, air barriers, and draft stopping are installed
Certificate from Insulation Contractor required
Window and Door Replacement work: - inspection must be prior to installation of interior trim
Final
After final electrical, plumbing, gas, mechanical and fire inspections have been approved
After any required duct/HERS testing has been completed
NOTES: First Re-inspection Fee: $75. Subsequent: $125. Applies to Inspection Failures, and No-Access Visits.
Brewster Building Department Will Perform Partial Inspections but Re-Inspection Fees Will Apply
Any Questions, Please Contact Us at building@brewster-ma.gov or (508) 896-3701 x1125
Photos will not be accepted without prior approval from the Building Commissioner
We Do Not Accept Inspection Requests via the ViewPoint/OpenGov online permitting system!!