HomeMy Public PortalAboutResolution 1393RESOLUTION NO. 1393
A RESOLUTION AUTHORIZING A CHANGE ORDER IN THE CONTRACT
BETWEEN THE VILLAGE OF PLAINFIELD AND ABBEY PAVING CO., INC.
WHEREAS, the Village of Plainfield and' Abbey Paving Co., Inc, previously
entered into a contract for the construction of improvements tQ Settler's Park; and
WHEREAS, it has been determined that it is in the best interest of the Village
to add certain work and' remove certain work from the original contract; and
WHEREAS the circumstances necessitating said change were not reasonably
foreseeable at the time the contract was executed and said change order is in the best
interest of the Village of Plainfield, as authorized by law, and the change is germane
to the original contract as signed.
NOW THEREFORE BE IT RESOLVED BY THE PRESIDENT AND BOARD OF
TRUSTEES OF THE VILLAGE OF PLAINFIELD, WILL COUNTY, ILLINOIS AS FOLLOWS:
That it is hereby determined that it is in the best interest of the Village
of Plainfield to authorize Change Order No. 1 and that the circumstances
necessitating said change were not reasonably foreseeable at the time
the contract was executed and that said change order is in the best
interest of the Village of Plainfield, as authorized by law, and the change
is germane to the original contract as signed.
II. The Village President is hereby authorized to execute said proposed
change order, a copy of which is attached hereto and made a part hereof
as Exhibit "A", and that a copy of this Resolution and Exhibit "A" shall
be preserved in a file regarding said contract which shall be open to the
public for inspection pursuant to 720 Illinois Compiled Statutes 5/33E-9.
Passed this 15th day of December , 2003.
AYES: Swalwell, O'Connell, Thomson, Fay, Waldorf and Collins.
RiAYS: p
ABSENT: 0 --. .
Distribution List:
Contract Administration Owner
Architect
G70~ Change Order Contractor
(Instructions on the reverse side) Fieltl
Other
.'and address): CHANGE ORDER NUMBER: 1
zS' Park Trail Extension DATE: 11/20/03
~.'eld, IL -
`'p (Name and address): ARCHITECT'S PROJECT NUMBER: 04-0536-001--x02-04-08
..paving Co . , Inc . CONTRACT DATE: $ / 11 / 03
);iehl Road
~;~, IL 60504
CONTRACT FOR: General Construction
~`
,T 15 CHANGED AS FDI.LDWS:
~e applicable, any undisputed amount attributable to previously executed Construction Change Directives)
L<
Move transformer for total add of $500.00
Reduction in materials (see attahced list) due to shortened
path for total deduct of ($33, 217.,05)
Undercuts made on path fox .total add of $876.00
~ 299 4$7.00
Contract Sum) ( was S " , 0
ge by previously authorized Change Orders ~' ~ 2gg .487:00
t Sum) prior to this Change Order was
t Su.m) will be ~• (deereased)~ . S , , 31 841.OS
~e Order in the amount of ''"~ `267 645.95'
ntract Sum) ($>~~~ including this Change Order will be
Time will be ~) (unchanged) by ( )days.
iuhstantial Completion as of the date of this Change Order therefore is _
change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Pnce which have been authorized Gy
I Chanqe Directive until the cost and time have been agreed upon by Goth the Owner and Contractor, in which case a Change t7rder is executed
the Construction Change Directive.
r.= S__--
Y?"~
UNTIL 51GNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
,;
cock Desi n Grou Abbe Pavin Co. Inc. Villa e of Plan d
CONTRACTOR (Firm name) OWNER (Firm name) .-. .
~((Firm name) 24000 Lockport Street '
~1. Jefferson Avenue 2319 Da.ehl Road
ADDRHEESS.
~; ADppursora, IL 60504 Plainfield`, IL 60544
~rv'ille, IL 60540 A
BY (Signature) BY (Signature)
ie Mica 1, Gilliam;
(Typed na e) (Typed name)
~Z~ ~~ _ ~l ~~ ~p°Z
` DATE DATE
ati....u ~;~.~ an original AIA Contract Document, on which this text appears In RED. An nriginat assures changes will not be obscured.
701 Change Order ®2001 The American Institute of Architects • Washington, CC • www.aia.org • WARNING: Reproduction, unucenseu
. _..~_,,,_,;,,; ,,,,,,+~,;,,„ „~,he ,.,~~er;Ai hero+n without written permission of the AIA violates the copyright laws of the United States and will
ili ~
~r vv ~
.
i~;,,~ ice, u~ ln_
l/MU JV~ ~ ~{u nLUIL:'1 i nr ii,.a
Phone: (630) 585-7220
'
FAX: (830) 585-7216
A
BEY -
P ,
AVING CO. 1NC. r -
,~
Heavy Anky Asphalt Paving , gip;:
2319 Mehl Road, Auror
November 12, 2003
Steve Konters ~:
Hitchcock Design Group
.221 W. Jefferson Avenue
Naperville, Illinois 60540
Re: Change orders
Dear Steve, -
Please find below the quantities and prices for the reduction in the path:
-~-~
Description Unit Quantity U nit Price Sub-total
Tree protection Lf 30 $ 2.00 $ 60.00
Grind Existing Curbs Lf 12 $ 2.50 $ 30.00
Site excavation & grading Cyd 166 $ 10.00 $ 1,660.00 a
Bituminous Paving (8' wide) Syd 635 $ 15.37 $ 9,759.95
Bituminous Paving (fi' wide) Syd 25 $ 16.37 $ 409.25 5
~
Accessible Ramps Sf 72 $ 17,00 $ 1,224.00 '
-
Turf Seed Syd 938 $ 1.20 $ 1.,125.60 ;~
Conduit, wire, trench & backfill Lf 815 $ 0.55' $ 448.2'5
Light Pole fixtures & foundations Each 5 $ 3,700.00 $1 8.500.00
Total $33,217.05 '`~'
,T~
In addition to the above and per our conversation the extra for the undercuts and moving;
transformer pad can be incorporated in this change order.
Sincerely, -~~
~ ~~
Michael.!, it ian
Secretary/Tre su er
~~;
t1,tSt5~T~ Yt'1~Y 11V1a
13:44 CHA 43 W' Jd3 ! G1~7
is3o> sss-izao
(63Q)585-7216
3B~Y
PAV{NG CO. ,INC.
Heavy nuh' Asphalt Paring
pctober 27, 2003
Steve Konters
Hitchcock Design Group
221 W. Jefferson Avenue
Naperville, Illinois 60540
2319 ~ieh1 Road, Aurora, IL 60504
Dear Steve, .
unclosed please find Pizzo's reply to the wsrwiph Van Mack about this,rbut haven't received a
adjustment. I have had several discussion
formal reply as of yet (Larry Evans has been out sick for a couple of days).
' d listed below the undercuts accomplished on the path. David Countryman from the
Please fin
Village came out Tuesday afternoon to finish off the proof rol .
2" u
35'x9'=315 sf
fir. uul
1Tx9'=153sf
47' x 5' = 235 sf
70'x9'-630sf
6'x 9'=54sf
11'x6.5'=71.5sf
20'x9'~180sf 315sf ~ 12"=11.ficyds
Total 1323.5 sf ®6° = 24.5 cyds
l
~
far the undercuts of
Total 36 cyds of dirt out and stone in. A unit pran soe `nd opose
a un t price
ated can remain P
contract. Since the dirt excav
extra: $876.80.
$24.35/cyd which would $
Bobcat C~ 75 00/hr
Backhoe ® $135.00/hr
Laborer ~ $60.00/hr
Six Wheeler ~ 70.00/hr
$340.00/hr x 1.5hrs $510.00
Total
49 tons of stone ~ $366.03
$7.47/1"an = $876.00
Total
Sincerely,
,~~
ichael i lion
Secretary asurer
10/21/03 TI1E 15:°04 FAX 630 585 1216 ~ ABBF~' PAVING
I
EY PAVING CO., INC.
~~ Heavy Duty Asphalt Paving
2319 Diehl Road
Aurora, Yllinois 6Q50a
Phone: ~63U/SSS-7224
Facsimile Transmission
Date: 1D/2D/2Q03 Time: 4:D4 PM
To; Steve Konters Dept:
Company: Hitchkock Design Grau
Fax No: b30/961-9925 Phone No: 63Q/951-1787
From; Michael J. Gillian
There are page(s) including this cover sheet with this transmission.
If there are any difficulties in transmission, please telephone our office at
(630) 585-7220.,
Subject: Settler's Park
Please review the enclosed schedule and the fax from Van-Mack regarding moving the
transformer. Adding S% to his price makes the extra approximately $5UD.D0. Please
advise.