Loading...
HomeMy Public PortalAboutResolution 1393RESOLUTION NO. 1393 A RESOLUTION AUTHORIZING A CHANGE ORDER IN THE CONTRACT BETWEEN THE VILLAGE OF PLAINFIELD AND ABBEY PAVING CO., INC. WHEREAS, the Village of Plainfield and' Abbey Paving Co., Inc, previously entered into a contract for the construction of improvements tQ Settler's Park; and WHEREAS, it has been determined that it is in the best interest of the Village to add certain work and' remove certain work from the original contract; and WHEREAS the circumstances necessitating said change were not reasonably foreseeable at the time the contract was executed and said change order is in the best interest of the Village of Plainfield, as authorized by law, and the change is germane to the original contract as signed. NOW THEREFORE BE IT RESOLVED BY THE PRESIDENT AND BOARD OF TRUSTEES OF THE VILLAGE OF PLAINFIELD, WILL COUNTY, ILLINOIS AS FOLLOWS: That it is hereby determined that it is in the best interest of the Village of Plainfield to authorize Change Order No. 1 and that the circumstances necessitating said change were not reasonably foreseeable at the time the contract was executed and that said change order is in the best interest of the Village of Plainfield, as authorized by law, and the change is germane to the original contract as signed. II. The Village President is hereby authorized to execute said proposed change order, a copy of which is attached hereto and made a part hereof as Exhibit "A", and that a copy of this Resolution and Exhibit "A" shall be preserved in a file regarding said contract which shall be open to the public for inspection pursuant to 720 Illinois Compiled Statutes 5/33E-9. Passed this 15th day of December , 2003. AYES: Swalwell, O'Connell, Thomson, Fay, Waldorf and Collins. RiAYS: p ABSENT: 0 --. . Distribution List: Contract Administration Owner Architect G70~ Change Order Contractor (Instructions on the reverse side) Fieltl Other .'and address): CHANGE ORDER NUMBER: 1 zS' Park Trail Extension DATE: 11/20/03 ~.'eld, IL - `'p (Name and address): ARCHITECT'S PROJECT NUMBER: 04-0536-001--x02-04-08 ..paving Co . , Inc . CONTRACT DATE: $ / 11 / 03 );iehl Road ~;~, IL 60504 CONTRACT FOR: General Construction ~` ,T 15 CHANGED AS FDI.LDWS: ~e applicable, any undisputed amount attributable to previously executed Construction Change Directives) L< Move transformer for total add of $500.00 Reduction in materials (see attahced list) due to shortened path for total deduct of ($33, 217.,05) Undercuts made on path fox .total add of $876.00 ~ 299 4$7.00 Contract Sum) ( was S " , 0 ge by previously authorized Change Orders ~' ~ 2gg .487:00 t Sum) prior to this Change Order was t Su.m) will be ~• (deereased)~ . S , , 31 841.OS ~e Order in the amount of ''"~ `267 645.95' ntract Sum) ($>~~~ including this Change Order will be Time will be ~) (unchanged) by ( )days. iuhstantial Completion as of the date of this Change Order therefore is _ change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Pnce which have been authorized Gy I Chanqe Directive until the cost and time have been agreed upon by Goth the Owner and Contractor, in which case a Change t7rder is executed the Construction Change Directive. r.= S__-- Y?"~ UNTIL 51GNED BY THE ARCHITECT, CONTRACTOR AND OWNER. ,; cock Desi n Grou Abbe Pavin Co. Inc. Villa e of Plan d CONTRACTOR (Firm name) OWNER (Firm name) .-. . ~((Firm name) 24000 Lockport Street ' ~1. Jefferson Avenue 2319 Da.ehl Road ADDRHEESS. ~; ADppursora, IL 60504 Plainfield`, IL 60544 ~rv'ille, IL 60540 A BY (Signature) BY (Signature) ie Mica 1, Gilliam; (Typed na e) (Typed name) ~Z~ ~~ _ ~l ~~ ~p°Z ` DATE DATE ati....u ~;~.~ an original AIA Contract Document, on which this text appears In RED. An nriginat assures changes will not be obscured. 701 Change Order ®2001 The American Institute of Architects • Washington, CC • www.aia.org • WARNING: Reproduction, unucenseu . _..~_,,,_,;,,; ,,,,,,+~,;,,„ „~,he ,.,~~er;Ai hero+n without written permission of the AIA violates the copyright laws of the United States and will ili ~ ~r vv ~ . i~;,,~ ice, u~ ln_ l/MU JV~ ~ ~{u nLUIL:'1 i nr ii,.a Phone: (630) 585-7220 ' FAX: (830) 585-7216 A BEY - P , AVING CO. 1NC. r - ,~ Heavy Anky Asphalt Paving , gip;: 2319 Mehl Road, Auror November 12, 2003 Steve Konters ~: Hitchcock Design Group .221 W. Jefferson Avenue Naperville, Illinois 60540 Re: Change orders Dear Steve, - Please find below the quantities and prices for the reduction in the path: -~-~ Description Unit Quantity U nit Price Sub-total Tree protection Lf 30 $ 2.00 $ 60.00 Grind Existing Curbs Lf 12 $ 2.50 $ 30.00 Site excavation & grading Cyd 166 $ 10.00 $ 1,660.00 a Bituminous Paving (8' wide) Syd 635 $ 15.37 $ 9,759.95 Bituminous Paving (fi' wide) Syd 25 $ 16.37 $ 409.25 5 ~ Accessible Ramps Sf 72 $ 17,00 $ 1,224.00 ' - Turf Seed Syd 938 $ 1.20 $ 1.,125.60 ;~ Conduit, wire, trench & backfill Lf 815 $ 0.55' $ 448.2'5 Light Pole fixtures & foundations Each 5 $ 3,700.00 $1 8.500.00 Total $33,217.05 '`~' ,T~ In addition to the above and per our conversation the extra for the undercuts and moving; transformer pad can be incorporated in this change order. Sincerely, -~~ ~ ~~ Michael.!, it ian Secretary/Tre su er ~~; t1,tSt5~T~ Yt'1~Y 11V1a 13:44 CHA 43 W' Jd3 ! G1~7 is3o> sss-izao (63Q)585-7216 3B~Y PAV{NG CO. ,INC. Heavy nuh' Asphalt Paring pctober 27, 2003 Steve Konters Hitchcock Design Group 221 W. Jefferson Avenue Naperville, Illinois 60540 2319 ~ieh1 Road, Aurora, IL 60504 Dear Steve, . unclosed please find Pizzo's reply to the wsrwiph Van Mack about this,rbut haven't received a adjustment. I have had several discussion formal reply as of yet (Larry Evans has been out sick for a couple of days). ' d listed below the undercuts accomplished on the path. David Countryman from the Please fin Village came out Tuesday afternoon to finish off the proof rol . 2" u 35'x9'=315 sf fir. uul 1Tx9'=153sf 47' x 5' = 235 sf 70'x9'-630sf 6'x 9'=54sf 11'x6.5'=71.5sf 20'x9'~180sf 315sf ~ 12"=11.ficyds Total 1323.5 sf ®6° = 24.5 cyds l ~ far the undercuts of Total 36 cyds of dirt out and stone in. A unit pran soe `nd opose a un t price ated can remain P contract. Since the dirt excav extra: $876.80. $24.35/cyd which would $ Bobcat C~ 75 00/hr Backhoe ® $135.00/hr Laborer ~ $60.00/hr Six Wheeler ~ 70.00/hr $340.00/hr x 1.5hrs $510.00 Total 49 tons of stone ~ $366.03 $7.47/1"an = $876.00 Total Sincerely, ,~~ ichael i lion Secretary asurer 10/21/03 TI1E 15:°04 FAX 630 585 1216 ~ ABBF~' PAVING I EY PAVING CO., INC. ~~ Heavy Duty Asphalt Paving 2319 Diehl Road Aurora, Yllinois 6Q50a Phone: ~63U/SSS-7224 Facsimile Transmission Date: 1D/2D/2Q03 Time: 4:D4 PM To; Steve Konters Dept: Company: Hitchkock Design Grau Fax No: b30/961-9925 Phone No: 63Q/951-1787 From; Michael J. Gillian There are page(s) including this cover sheet with this transmission. If there are any difficulties in transmission, please telephone our office at (630) 585-7220., Subject: Settler's Park Please review the enclosed schedule and the fax from Van-Mack regarding moving the transformer. Adding S% to his price makes the extra approximately $5UD.D0. Please advise.