HomeMy Public PortalAbout080_016_Probable CTC_25March15 (2) CITY OF TYBEE ISLAND, GA DERELICT STRUCTURE REMOVAL PROJECT PROBABLE COST-TO-CONSTRUCT • CONTRACTOR COST (Documented Structure locations) $1,156,000 • CONTRACTOR COST (Undocumented Structure locations—TBD) $250,000. Subtotal(1) $1,405,883. • O.D.C.'s o Permitting/Agency Liaison $21K o Design/Doc. Prep $28.5K o Survey Update $6.5K o RFP Process $22K Subtotal $78,000. o Contract admin; Construction oversite; Project management $135K Subtotal $135,000. TOTAL $1,608,883. w/ 5% Contingency $1,689,327. (1)Actual costs to be determined by a Request For Proposals from qualified marine contractors. Olsen Associates,Inc. 1 25 March 2015