HomeMy Public PortalAbout080_016_Probable CTC_25March15 (2) CITY OF TYBEE ISLAND, GA
DERELICT STRUCTURE REMOVAL PROJECT
PROBABLE COST-TO-CONSTRUCT
• CONTRACTOR COST (Documented Structure locations) $1,156,000
• CONTRACTOR COST (Undocumented Structure locations—TBD) $250,000.
Subtotal(1) $1,405,883.
• O.D.C.'s
o Permitting/Agency Liaison $21K
o Design/Doc. Prep $28.5K
o Survey Update $6.5K
o RFP Process $22K
Subtotal $78,000.
o Contract admin; Construction
oversite; Project management $135K Subtotal $135,000.
TOTAL $1,608,883.
w/ 5% Contingency $1,689,327.
(1)Actual costs to be determined by a Request For Proposals from qualified marine contractors.