HomeMy Public PortalAbout2008-21 Agreement with Conquest Engineering Group Reclaimed Water Distribution SystemRESOLUTION NO. 2008-21
A RESOLUTION OF THE VILLAGE COUNCIL OF THE
VILLAGE OF KEY BISCAYNE, FLORIDA, AUTHORIZING
AND AWARDING CONSTRUCTION CONTRACT BETWEEN
THE VILLAGE AND CONQUEST ENGINEERING GROUP
(THE "CONTRACTOR") TO PROVIDE FOR THE
CONSTRUCTION OF THE RECLAIMED WATER
DISTRIBUTION SYSTEM PURSUANT TO MIAMI-DADE
COUNTY FUNDING; PROVIDING FOR
IMPLEMENTATION; PROVIDING FOR EFFECTIVE DATE.
WHEREAS, pursuant to public bidding process, the Village of Key Biscayne (the "Village")
has sought bids for the construction of the reclaimed water distribution system (the "Project") which
shall be constructed by the contractors of the Village as a facility of Miami- Dade County using
funds provided by Miami- Dade County (the "County") for such purpose; and
WHEREAS, the Village Manager has caused the ten (10) bids which were submitted for
the Project to be reviewed for the Village by the firm of Corzo Castella Carballo Thompson Salman,
P.A. ("C3TS"); and
WHEREAS, C3TS has reviewed the bids and has recommended that the Project be awarded
to the lowest, responsible, responsive bidder, to wit: Conquest Engineering Group (the "Contractor")
in the amount of Seven Hundred Eighty Nine Thousand, Eighty Four ($ 789,084) Dollars; and
WHEREAS, the Village Council finds that since the improvements constituting this Project
shall constitute a facility of the County, and the Project is funded by the County, that a capital project
authorizing ordinance is not required under the Village Charter, but in any event, finds that the
Project has previously been authorized, to the extent required, by Capital Project authorizing
Ordinance No. 2006-6; and
WHEREAS, the Village Council finds that it is in the best interest of the Village to proceed
as indicated in this Resolution.
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE VILLAGE
OF KEY BISCAYNE, FLORIDA, AS FOLLOWS:
Section 1. Recitals Adopted. That each of the recitals stated above is hereby adopted
and confirmed.
Section 2. Agreement Approved, Specification of Funds, Conditions.
A. Agreement Approved. That the Contract for construction (the "Agreement"), in
substantially the form attached hereto, between the Contractor and the Village for construction of
the Project is hereby approved, and the Village Manager is hereby authorized to execute the
Agreement on behalf of the Village, once approved as to form and legal sufficiency by the Village
Attorney, and subject to the provisions and conditions of this Resolution.
B. Funding Source. That funding for the Project shall be provided in accordance with
the Village Manager's memorandum which accompanies this Resolution, in an amount which shall
not exceed the Agreement cost amount which is expressly set forth in the above stated recitals.
C. Conditions. That the Agreement shall be subject to the condition precedent that funds
(as provided to the Village by the County) are available and budgeted, as applicable, for the
accomplishment of the work for this Project. Further, the Agreement shall be subject to the
conditions which have been incorporated into the Agreement, including, but not limited to, the
conditions which are set forth in Section 1.12.2 (B) and (C) of the Agreement.
Section 3. Implementation. That the Village Manager is hereby authorized to take
any and all action which is necessary to implement the purposes of this Resolution and the
2
Agreement.
Section 4. Effective Date. That this Resolution shall be effective immediately
upon adoption hereof.
PASSED AND ADOPTED this 13th day of May, 2008.
CONCHITA H. ALVAREZ, CMC, VILLAGE CLERK
APPROVED AS TO FORM AND LEGAL SUFFICIENC
C:\Authorizing Reclaimed Water Distribution Project Contract
3
MAYOR ROBERT L. VERNON
SECTION 00500
CONTRACT
THIS AGREEMENT, made and entered into this ?1 lay of /a'- , 2008, A.D., by and between the
Village of Key Biscayne, party of the first part (hereinafter sometimes called the OWNER), and Conquest
Engineering Group, party of the second part (hereinafter sometimes called the "CONTRACTOR").
WITNESSETH: That the parties hereto, for the consideration hereinafter set forth, mutually agree
as follows:
1.01 SCOPE OF THE WORK
A. The CONTRACTOR shall furnish all labor, materials, equipment, machinery, tools, apparatus, and
transportation and perform all of the Work indicated on the Drawings and described in the
Specifications entitled:
The Village of Key Biscayne
Reclaimed Water Distribution System
as prepared by Post, Buckley, Schuh & Jernigan, Inc., acting as, and in the Contract Documents
entitled the ENGINEER, and shall do everything required by this Contract and the other Contract
Documents.
The work includes the construction of reclaimed water mains including service lines, valves and
appurtenances, and roadway/right-of-way restoration, and other related work as shown on the plans.
1.02 THE CONTRACT SUM
A. The OWNER shall pay to the CONTRACTOR for the faithful performance of the Contract, in lawful
money of the United States, and subject to addition and deductions as provided in the Contract
Documents, a total sum as follows:
Based upon the prices shown in the Proposal heretofore submitted to the OWNER by the
CONTRACTOR, a copy of said Proposal being a part of these Contract Documents, the aggregate
amount of this Contract (obtained from either the lump sum price, the application of unit prices to the
quantities shown in the Proposal, or the combination of both) being the sum of Seven Hundred Eighty
Nine Thousand Eighty Four Dollars ($789,084).
1.03 COMMENCEMENT AND COMPLETION OF WORK
A. The CONTRACTOR shall commence Work and the Contract Time will commence to run on the date
fixed in the Notice to Proceed.
B. The CONTRACTOR shall prosecute the Work with faithfulness and diligence and shall substantially
complete the Work no later than ninety (90) calendar days after the commencement date as fixed in the
Notice to Proceed. The work shall be completed within thirty (30) calendar days from the data
certified by Engineer as the date of substantial completion.
Project 01-1588.04 00500-1 Village of Key Biscayne
April 2008 Reclaimed Water Distribution System
1.04 CONTRACTOR'S ACCEPTANCE OF CONDITIONS
A. The CONTRACTOR hereby agrees that, by virtue of submitting a completed Proposal including his
declarations therein of full satisfaction, knowledge and understanding of the Contract Documents, site
conditions (surface and subsurface) and all other conditions affecting the Work, he assumes full
responsibility for performance of the Work as required under this Contract. It is expressly agreed that
under no circumstances, conditions, or situations shall this Contract be more strongly construed
against the OWNER than against the CONTRACTOR and his Surety.
B. It is understood and agreed that the passing, approval and/or acceptance of any part of the Work or
material by the OWNER, ENGINEER, or by any agent or representative, as being in compliance with
the terms of this Contract and/or of the Contract Documents, shall not operate as a waiver by the
OWNER of strict compliance with the terms of this Contract, and/or the Contract Documents covering
said Work; and the OWNER may require the CONTRACTOR and/or his surety to repair, replace,
restore and/or make to comply strictly and in all things with this Contract and the Contract Documents
any and all of said Work and/or materials which within a period of one year from and after the date of
the acceptance of any such Work or material, are found to be defective or to fail in any way to comply
with this Contract or with the Contract Documents. This provision shall not apply to materials or
equipment normally expected to deteriorate or wear out and become subject to normal repair and
replacement before their condition is discovered. The CONTRACTOR shall not be required to do
normal maintenance work under the guarantee provisions. Failure on the part of the CONTRACTOR
and/or his Surety, immediately after notice to either, to repair or replace any such defect.
1.05 LIQUIDATED DAMAGES
A. It is mutually agreed that time is of the essence of this Contract and should the CONTRACTOR fail to
complete the work within the specified time, or any authorized extension thereof, there shall be
deducted from the compensation otherwise to be paid to the CONTRACTOR, and the OWNER will
retain the amount of two thousand dollars ($2000) per calendar day until substantial completion, as
fixed, agreed and liquidated damages for each calendar day elapsing beyond the specified time for
completion or any authorized extension thereof. After substantial completion, should contractor fail to
complete the remaining work within the time specified in Section 1.03 above, the owner will retain the
sum of one thousand dollars ($1000) per calendar day until completion. These amounts shall represent
the actual damages which the OWNER will have sustained by failure of the CONTRACTOR to
complete the work within the specified time; it being further agreed that said sum is not a penalty, but
is the stipulated amount of damages sustained by the OWNER in the event of such default by the
CONTRACTOR.
B. For the purposes of this Article, the day of final acceptance of the work shall be considered a day of
delay, and the scheduled day of completion of the work shall be considered a day scheduled for
production.
C. For the purposes of this Contract, the day of final acceptance of the work shall be considered a day of
delay, and the scheduled day of completion of the work shall be considered a day scheduled for
production.
1.06 REIMBURSEMENT OF ENGINEERING EXPENSES
A. Should the completion of the Contract be delayed beyond the specified or adjusted time limit,
Contractor shall reimburse Owner for all expenses of engineering and inspection incurred by Owner
Project 01-1588.04 00500-2 Village of Key Biscayne
April 2008 Reclaimed Water Distribution System
during the period between said specified or adjusted time and the actual date of substantial
completion. All such expenses for engineering and inspection incurred by Owner will be charged to
Contractor and be deducted from payments due Contractor as provided by this Contract. Said
expenses shall be further defined as engineers charges associated with the construction contact project
management, including resident project representative costs. These expenses are not included in the
daily rate for liquidated damages as defined in Article 1.05 of this Contract. These are additional
expenses to be paid whether or not the liquidated damages are assessed.
1.07 PARTIAL AND FINAL PAYMENTS
A. In accordance with the provisions fully set forth in the General Conditions, and subject to additions
and deductions as provided, the OWNER shall pay the CONTRACTOR as follows:
1. Within 30 days after receipt by the OWNER of the CONTRACTOR's request for partial
payment, the OWNER shall make partial payments to the CONTRACTOR, on the basis of
the estimate of Work as approved by the ENGINEER, for work performed during the
preceding calendar month, less ten percent (10%) of the amount of such estimate which is to
be retained by the OWNER until all Work has been performed strictly in accordance with this
Agreement and until such Work has been accepted by the OWNER.
2. Upon submission by the CONTRACTOR of evidence satisfactory to the OWNER that all
payrolls, material bills and other costs incurred by the CONTRACTOR in connection with the
construction of the Work have been paid in full, and also, after all guarantees that may be
required in the specifications have been furnished and are found acceptable by the OWNER,
final payment on account of this Agreement shall be made within sixty (60) days after
completion by the CONTRACTOR of all Work covered by this Agreement and acceptance of
such Work by the OWNER.
1.08 ADDITIONAL BOND
A. It is further mutually agreed between the parties hereto that if, at any time after the execution of this
Agreement and the Performance and Payment Bonds hereto attached for its faithful performance, the
OWNER shall deem the surety or sureties upon such bonds to be unsatisfactory, or if, for any reason,
such bond(s) ceases to be adequate to cover the performance of the Work, the CONTRACTOR shall,
at his expense, and within three days after the receipt of notice from the OWNER to do so, furnish an
additional bond or bonds, in such form and amount, and with such sureties as shall be satisfactory to
the OWNER. In such event, no further payment to the CONTRACTOR shall be deemed due under
this Agreement until such new or additional security for the faithful performance of the Work shall be
furnished in manner and form satisfactory to the OWNER.
1.09 CONTRACT DOCUMENTS
A. The Contract Documents which comprise the entire agreement between the Village and the Contractor
concerning the work consist of this Contract for Construction, the Drawings, Plans and Specifications,
the Invitation for Bids, the Addenda , the Bid, Instructions to Bidders, the General and Supplementary
Conditions, FDEP supplementary conditions (construction), the Performance Bond, Insurance
Certificates, the Notice of Award, the Notice to Proceed, any Change Orders and any other Contract
Documents, not specifically listed herein which shall be considered incorporated into and made a part
of this Contract by this reference and shall govern this Project. Contractor is reminded and hereby
recognizes that all Work under this contract must comply with applicable county, state and federal
Project 01-1588.04 00500-3 Village of Key Biscayne
April 2008 Reclaimed Water Distribution System
regulations, which shall be deemed to be incorporated herein immediately upon Village's written
request.
B. This document incorporates and includes all prior negotiations, correspondence, conversations,
agreements, or understandings applicable to the matters contained herein and the parties agree that
there are no commitments, agreements, or understandings concerning the subject matter of these
Contract Documents that are not contained herein. Accordingly it is agreed that no deviation from the
terms hereof shall be predicated upon any prior representations or agreements, whether oral or written.
C. The Contract Documents shall remain the property of the Village. The Contractor shall have the right
to keep one record set of the Contract Documents upon the completion of the Project: however, that in
no event shall the Contractor use, or permit to be used, any or all of such Contract Documents on other
Projects without the Village' s prior written authorization.
1.10 WAIVER OF JURY TRIAL
Village and Contractor knowingly, irrevocably, voluntarily and intentionally waive any right either may
have to a trial by jury in State and or Federal court proceedings in respect to any action, proceeding, lawsuit
or counterclaim based upon the Contract for Construction, arising out of, under, or in connection with the
Construction of the Work, or any course of conduct, course of dealing, statements or actions or inactions of
any party.
1.11 ASSIGNMENT
Neither party shall assign the Contract or any sub -contract in whole or in part without the written consent
of the other, nor shall contractor assign any monies due or to become due to it hereunder, without the
previous written consent of the Village Manager.
1.12 MISCELLANEOUS
1.12.1 INSURANCE REQUIREMENTS
Contractor shall provide and maintain in force until all the Work to be performed under this Contract has
been completed and accepted by Village (or for such duration as is otherwise specified hereinafter), the
insurance coverages set forth in the Contract Documents.
1.12.2 VILLAGE'S RIGHT TO TERMINATE CONTRACT
A. If Contractor fails to timely begin the Work, or fails to perform the Work, with sufficient workers
and equipment or with sufficient materials to insure the prompt completion of the Work, or shall
perform the Work unsuitably, or cause it to be rejected as defective and unsuitable, or
discontinue the prosecution of the Work pursuant to the accepted schedule or if the Contractor
shall fail to perform any material term set forth in the Contract Documents or if Contractor shall
become insolvent or be declared bankrupt or insolvency, or shall make an assignment for the
benefit of creditors, or from any other cause whatsoever shall not carry on the Work in any
acceptable manner, Village may, upon seven (7) days written Notice of Termination, terminate
the services of Contractor, exclude Contractor from the Project site and take the prosecution of
Work out of the hands of the Contractor, and use any or all materials on the Project site which
have been paid for by the Village, as may be suitable and acceptable and may finish the Work by
whatever methods it may deem expedient. In such case Contractor shall not be entitled to receive
Project 01-1588.04 00500-4 Village of Key Biscayne
April 2008 Reclaimed Water Distribution System
any further payment until the Project is completed. All damages, costs and charges incurred by
Village, together with costs of completing the Project, shall be deducted from any monies due or
which may become due to Contractor. In case the damages and expenses so incurred by Village
shall exceed the unpaid balance, then Contractor shall be liable and shall pay to Village the
amount of said excess.
B. Contractor agrees that in the event that a referendum or initiative measure is adopted at an
election by the majority of the electors of the Village voting on such measure, which operates to
prohibit the construction of the Project in accordance with the Plans: the Village Council shall
have the authority, within (30) days after any such event, to terminate the Contract by providing
written notice of termination to the Contractor. In the event of such termination, the Village shall
not be liable to Contractor for payment to any supplemental compensation, penalties, damages,
loss of profits, termination fee or demobilization fee as a result of such termination, and the
Contractor shall only be paid by the Village in accordance with the Contract, for the portion of
the Work for the Project which has been performed by Contractor up to the time of notice of
termination of Contract. The Contractor shall be entitled to recover from the Village payment for
proven loss with respect to materials, equipment, tools, and construction equipment and
machinery, including reasonable overhead, and profit earned on the Project prior to the date of
termination.
C. In the event that a referendum or initiative measure is adopted at an election by the majority of
the electors of the Village voting on such measure, which operates to prohibit the fmancing for
the construction of the Project in accordance with the Plans: the Village Council shall have the
authority, within thirty (30) days after any such event, to terminate the Contract by providing
written notice of termination to the Contractor. In the event of such termination, the Village shall
not be liable to Contractor for payment of any compensation, penalties, damages, loss of profits,
termination fee or demobilization fee as a result of such termination, and the Contractor shall
only be paid by the Village in accordance with the Contract, for the portion of the Work of the
Project which has been performed by the Contractor up to the time of notice of termination of
Contract. The Contractor shall be entitled to recover from the Village payment for proven loss
with respect to materials, equipment, tools, and construction equipment and machinery, including
reasonable overhead, and profit earned on the Project prior to the date of termination.
1.12.3 CONTRACTOR TO CHECK PLANS, SPECIFICATIONS AND DATA:
1.12.4
Contractor shall verify all dimensions, quantities and details shown on the plans, specifications or
other data received from Village's Project Engineer, and shall notify Village's Project Engineer
in writing of all errors, omissions and discrepancies found therein within three (3) calendar days
of discovery and Village's Project Engineer will promptly review the same. Any Work done after
such discover, but prior to written authorization of the Village's Project Engineer, will done at
the Contractor's sole risk.
CONTRACTOR'S RESPONSIBILITY FOR DAMAGES AND ACCIDENTS:
A. Contractor shall accept full responsibility for the Work against all loss or damage of any nature
sustained until fmal acceptance by Village, and shall promptly repair any damage done from any
cause.
B. Contractor shall be responsible for all materials, equipment and supplies pertaining to the Project.
In the event any such materials, equipment and supplies are lost, stolen, damaged or destroyed
prior to final acceptance by Village, Contractor shall replace same without cost to Village.
Project 01-1588.04
April 2008 Reclaimed Water Distribution System
00500-5 Village of Key Biscayne
1.12.5 DEFECTIVE WORK/GUARANTEE:
A. Village shall have the authority to reject or disapprove Work which the Village finds to be
defective. If required by the Village, Contractor shall promptly either correct all defective Work
or remove such defective Work and replace it with non -defective Work. Contractor shall bear all
direct, indirect and consequential costs of such removal or corrections including cost of testing
laboratories and personnel.
B. Should Contractor fail or refuse to remove or correct any defective Work or to make any
necessary repairs in accordance with the requirements of the Contract Documents within the time
indicated in writing by Village's Project Consultant, Village shall have the authority to cause the
defective Work to be removed or corrected, or make such repairs as may be necessary at
Contractor's expense. Any expense incurred by Village in making such removals, corrections or
repairs, shall be paid for out of any monies due or which may become due to Contractor. In the
event of failure of Contractor to make all necessary repairs promptly and fully, Village may
declare Contractor in default.
C. The contractor shall unconditionally guarantee all materials and equipment furnished and Work
performed for a period of one (1) year from the date of substantial completion. If, within one (1)
year after the date of substantial completion, any of the Work is found to be defective of not in
accordance with the Contract Documents, Contractor, after receipt of written notice from Village,
shall promptly correct such defective or nonconforming Work within the time specified by
Village without cost to Village. Nothing contained here in shall be construed to establish a period
of limitation with respect to any other obligation which Contractor might have under Contract
Documents including but not limited to any claim regarding latent defects.
D. Failure to reject any defective Work or material shall not in any way prevent later rejection when
such defect is discovered.
1.12.6 LEGAL RESTRICTIONS AND TRAFFIC PROVISIONS:
Contractor shall conform to and obey all applicable laws, regulations, or ordinances with regard to
labor employed, hours of Work and Contractor's general operations. Contractor shall conduct its
operations so as not to interfere with or close any throughfare, except as provided for in the Contract
Documents, without the written consent of the proper authorities.
1.12.8 EXAMINATION AND RETENTION OF CONTRACTOR'S RECORDS:
A. The Village or any of their duly authorized representatives shall, until three (3) years after final
payment under this contract, have access to and the right to examine any of the Contractor's
books, ledgers, documents, papers, or other records involving transactions related to this contract
for the purpose of making audit, examination, excerpts and transcriptions.
B. The Contractor agrees to include in first -tier subcontracts under this contract a clause
substantially the same as subparagraph 1.12.7.A above. "Subcontract," as used in this clause,
excludes purchase orders not exceeding $10,000.
C. The right to access and examination of records in subparagraph 1.12.7.A shall continue until
disposition of any mediation, claims, litigation or appeals.
Project 01-1588.04 00500-6 Village of Key Biscayne
April 2008 Reclaimed Water Distribution System
1.12.8 DAMAGES FOR DELAY:
No claim for damages or any claim, other than for an extension of time shall be made or asserted
against Village by reason of any delays. Contractor shall not be entitled to an increase in the Contract
Price or payment or compensation of any kind from Village for direct, indirect, consequential, impact
or other costs, expenses or damages, including by not limited to, cost of acceleration or inefficiency,
arising because of delay, disruption, interference or hindrance be reasonable or unreasonable,
foreseeable or unforeseeable, or avoidable or unavoidable. Contractor shall be entitled only to
extensions of the Contract Time as the sole exclusive remedy for such resulting delay.
Notwithstanding the above, and in accordance with the requirements of Article 12 of the General
Conditions, the Contractor shall be granted an extension of time and suspension of liquidated damages
for any delay beyond the control of the Contractor. Should any delay, disruption, interference or
hindrance be caused by the Village, for a continuous period or cumulative period of thirty (30) days,
the Contractor may terminate the Contract upon seven days written notice to the Village.
1.12.9 PUBLIC ENTITY CRIMES AFFIDAVIT:
Contractor shall comply with Section 287.133, Florida Statues, (Public Entity Crimes Statute)
notification of which is hereby incorporated herein by reference, including execution of any required
affidavit.
1.12.10 INDEMNIFICATION:
Contractor shall indemnify and hold harmless Village, Village's officers and employees and Village's
Project Engineer and its officers and employees, from liabilities, damages, losses and costs, including,
but not limited to, reasonable attorney's fees, to the extent caused by the negligence, recklessness or
intentional wrongful conduct of Contractor and persons employed or utilized by Contractor in the
performance of the Agreement.
1.12.11 CAPITALIZED TERMS:
Capitalized terms shall have their plain meaning as indicated herein.
1.12.12 INDEPENDENT CONTRACTOR:
The Contractor is an independent contractor under the Contract. Services provided by the Contractor
shall be by employees of the Contractor and subject to supervision by the Contractor, and not as
officers, employees, or agents of the Village. Personnel policies, tax responsibilities, social security
and health insurance, employee benefits, purchasing policies and other similar administrative
procedures, applicable to services rendered under the Contract shall be those of the Contractor.
1.12.13 PAYMENT TO SUB -CONTRACTORS:
Certification of Payment to Subcontractors: The term "subcontractor," as used herein, includes persons
or firms furnishing materials or equipment incorporated into the work or stockpiled for which the
Village made partial payment and firms working under equipment -rental agreements. The Contractor
is required to pay all subcontractors for satisfactory performance of their Contracts before the Village
will make a further progress (partial) payment. The Contractor shall also return all retainage withheld
to the subcontractors within 30 days after the subcontractor's work is satisfactorily complete, as
Project 01-1588.04
April 2008 Reclaimed Water Distribution System
00500-7 Village of Key Biscayne
determined by the Village. Prior to receipt of any progress (partial) payment, the prime contractor shall
certify that all subcontractors having an interest in the Contract were paid for satisfactory performance
of their Contracts and that the retainage is returned to subcontractors within 30 days after satisfactory
completion of the subcontractor's work. Contractor shall provide this certification in the form
designated by the Village.
The Village will not make any progress payments after the initial partial payment until the Contractor
completes the Equal Opportunity monthly report, unless the Contractor demonstrate good cause for
not making any required payments and furnishes written notification of any such good cause to both
the Village and the affected subcontractors and suppliers.
Within 30 days of the Contractor's receipt of the final progress payment or any other payments
thereafter, except the final payment, the Contractor shall pay all subcontractors and suppliers having
an interest in the Contract for all work completed and materials furnished. The Village will honor an
exception to the above when the Contractor demonstrates good cause for not making any required
payment and furnishes releases from subcontractors and suppliers within 30 -day period.
IN WITNESS WHEREOF, the parties hereto have made and executed this Agreement on the respective dates
under each signature: VILLAGE OF KEY BISCAYNE, FLORIDA, signing by and through its
Village Manager authorized to execute same by Council action on the /3 day of in, 2008,
and C6ai s/LJ28 / it 1 h& r; Q tg3-� P signing by and through
j• �
,'4l ?re 3 € eti 6 , du -1y authorized to execute sa e.
ST:
VILLAG • F KEY B : • YNE, FLO A
By:
'llage Clerk Village Manager
APPROVED AS TO FORM
AND LEGAL SUFFICIENC '
By:
VILLAGE ATT e RNE
This day of , 2008.
Project 01-1588.04
April 2008
00500-8 Village of Key Biscayne
Reclaimed Water Distribution System
CONTRACTOR MUST EXECUTE THIS CONTRACT AS INDICATED BELOW. USE CORPORATION
FORMAT, AS APPLICABLE.
A ' EST:
CONTRACTOR
k/Iie2etr //-1_4(,//76 1-itft9T‘ '
ecretary) _" = itle)
(Corporate Seal)
Thisa 'I -day of
, 2008.
Q va' 4, , -.i i?
-/
(T . e Name/Title signed above)
Project 01-1588.04 00500-9 Village of Key Biscayne
April 2008 Reclaimed Water Distribution System
CERTIFICATE
(Sample)
STATE OF FLORIDA
COUNTY OF
)
)
SS
I HEREBY CERTIFY that a meeting of the Board of Directors of
itee.e//16 ,e_Ao
�DZJ da , held on
ey
a
43V7.52,v i
, a corporation under the laws of the State of
, 20 the following resolution was duly passed and adopted:
"RESOLV D, that �C.—/cei/BYO G cl �,e,e3/!3% , as
7 - e President of the corporation, be and he is hereby
authorizgd to execute the Contract dated , 20_, between
the V/ /1446e 6/ ,t`and this corporation, and that his
execution thereo atte ted by Secretary of the corporation and with
corporate seal affixed, shall be the official act and deed of this corporation."
I further certify that said resolution is now in full force and effect.
IN WITNESS EREOF, I have hereunto set my hand and affixed the official seal of the corporation this
4,7ig i'Ite, day of , 201;1
END OF SECTION
Project 01-1588.04 00500-10 Village of Key Biscayne
Reclaimed Water Distribution System
April 2008