HomeMy Public PortalAboutResolution 1112RESOLUTION NO. 1112
RESOLUTION AUTHORIZING A CHANGE ORDER IN THE CONTRACT BETWEEN THE
VILLAGE OF PLAINFIELD AND AM-COAT PAINTING, INC.
WHEREAS, the Village of Plainfield and Am-Coat Painting, Inc.
entered into a certain agreement dated April 3, 1995, for painting
the Mill Street Water Tower and;
WHEREAS, it has been determined that it is in the best
interest of the Village of Plainfield to approve Change Order No.
1, a copy of which is attached hereto and made a part hereof as
Exhibit "A";
WHEREAS, THE Village's Engineer has determined that said
Change Order is in the best interest of the Village of Plainfield;
NOW, THEREFORE, BE IT RESOLVED BY THE PRESIDENT AND BOARD OF
TRUSTEES OF THE VILLAGE OF PLAINFTELD, AS FOLLOWS:
1. It is hereby determined, that it is in the best interest
of the Village of Plainfield to authorize certain changes in
the agreement dated, April 3, 1995, between the Village of
Plainfield and Am-Coat Painting, inc. as set forth in the
attached Exhibit "A", and said Change Order is authorized by
law.
2. That the circumstances which necessitated the Change Order
were not reasonably foreseeable at the time the contract was
executed, and were not within the contemplation of the
contract as signed, and it is in the best interest of the
Village of Plainfield to approve said Change Order, which is
authorized by law.
3. That the Village President is hereby authorized to execute
said proposed Change Order, a copy of which is attached hereto
and made a part hereof as Exhibit "A" to be preserved in a
permanent contract file open to the public pursuant to 720
ILLS 5/33 E-9.
PASSED THIS
5th DAY OF June 1995.
5th DAY OF June
1995.
AFPROVED THIS
ILLAGE PRESIDENT
ATTEST : '"
~y ~ ..
?J
VILLAGE. ERK
~; ----
CHANGE ORDER NO. 1
PROJECT: ~ - DATE OF ISSUANCE: 5 10 95
Mill Street Elevated Water Storage Tank .
Repainting
OWNER: Village of Plainfield, 111inois ENGINEER: Baxter & Woodman, Inc.
CONTRACTOR: AM-Coat Painting, Inc. ENGINEER'S Project No. 950149/
92091$
You are directed to make the following changes in the Contract Documents:
Description: Project Manual, General Conditions, Article 12 - Change of
Contract Times. To enable the Contractor to complete the.
Project under conditions more suitable to paint application and
curing, a time extension shall be granted.
Purpose oz Change Order:
Attachments: None
CHANGE IN CONTRACT PRICE:
Original Contract Price:
Previous Change Orders
No.~ - to NO. -
Current Contract Price:
Change in Contract Time.
CHANGE IN CONTRACT TIME:
$162 370.00 Original Contract Time:
Substantial Completion: 6/1/95
Completion: 7/1L95_
$ 0.00 Change from previous. Change Orders:
None
$162 370.00 Current Contract Time:
Substantial Completion: 6/1/95
Com letion: 7/1/95
Net increase/decrease of this
Change Order: ~ $ 0.00 Net increase of this Change Order:
Sub. Completion: 43 calendar days
Completion: 44 calendar__da~rs
Contract Price with this
Change Order: $ 162,370.00._ Contract Time with this Change Order:
Substantial Completion: 7/14/95
Completion: 8/14/95 _
Pursuant to Public Act 85-1295, the circumstances which necessitate this Change
Order were not reasonably foreseeable at the time the Contract was signed, were
not within the contemplation of the Contract as signed, and are in the best
interest of the Village.
RECOMMENDED:
BAXTER & WOODMAN, INC.
By
Charles A. Brunner, P.E.
Project Manager
By ~ .~_.__
awrence E. Thomas, P.E.
Client Manager
changeor/col.hrk
APPROVED: VILLAGE OF ACCEPTED: AM--COAT
PLAINFIELD, ILLINOIS PAINTING, INC.
B BY
ohn E. Peterson Thomas Tyrakowski
President Vice President
B ~~ er
ti'~o~odman
consulting engineers
C~~G~~'(
May 10, 1995
Mr. Thomas Tyrakowski,
Am-Coat Painting, Inc.
850 North State Street
Lockport, Illinois 60
Subject: Plainfield -
Dear Mr. Tyrakowski:
Vice President
Suite 3
441
Mill Street Elevated Water Storage
Tank Repainting
Four copies of a Change Order No. 1 are enclosed for Contractor
acceptance.
Please sign and return all copies to us. Upon approval by the
Owner, we will return one copy to you for your records.
Very truly yours,
BAXTER & WOODMAN, INC.
CONSULTING ENGINEERS
~~~ ~~~~
Harold R. Kivle
Y
HRK:jg
Enc.
cc/enc: Mr. David P. Van Vooren, Administrator
Mr. Harry Countryman, Superintendent of Water
950149\collte.hrk
8678 RIDGEFIELD ROAD / CRYSTAL LAKE, IL 60012 / 815/459-1260
. John E. Peterson
~. `PRE51pENT
TRUSTEES
Jeffrey Dement
VILLAGE OF PLAINFIELD Jack Fleimerdinger
Michael Lambert
WILL COUNTY'S OLDEST COMMUNITY Richard Rock
Raymond Smolich
Kurt Stelzer
Susan Janik
VILLAGE CLERK
MEMO TO: JOHN E. PETERSON, VILLAGE PRESIDENT
BOARD OF TRUSTEES
FROM: DAVID P. VAN VOOREN, VILLAGE ADMINISTRATOR
DATE: MAY 24, 1995
SUBJECT: CHANGE ORDER #1
BACKG ROU N D
On April 3, 1995 the Village Board entered into a contract for painting the Mill Street
Water Tower with Am-Coat Painting, Inc. This project was advertised and bids were open
on January 17, 1995. The delay in the opening and award of the contract was due to the
review and discussion on the concern for the disposal of the paint waste. In that the Staff
spent several weeks on this matter, the proposed completion dates in the contract
documents were unrealistic. To that end, at the April 11, 1995 pre-construction conference
Staff proposed the following completion dates.
1) Substantial Completion 7/14/95
2) Completion 8/14/95
The proposed Resolution would authorize the change in the completion dates.
RECOMMENDATION
Staff recommends that the Village Board authorize the Resolution to execute Change
Order #1 extending the completion dates as listed.