HomeMy Public PortalAboutResolutiion No. 24-069- Resolution authorizing contract amendment with Diamanti Construction to include additional renovations to the police station command staff officesSponsored By: City Manager
RESOLUTION NO. 24-069
A RESOLUTION OF THE CITY COMMISSION OF THE
CITY OF OPA-LOCKA, FLORIDA, RATIFYING THE CITY
MANAGER'S DECISION TO CHANGE THE SCOPE OF
SERVICES FOR THE POLICE DEPARTMENT
DEMOLITION AND REBUILD/RELOCATION PROJECT
AND FURTHER AUTHORIZES THE CITY MANAGER TO
EXECUTE AN AMENDMENT TO THE AGREEMENT
WITH DIAMANTI CONSTRUCTION &
DEVELOPMENT, INC TO INCLUDE ADDITIONAL
WORK TO RELOCATE THE NEW POLICE
DEPARTMENT COMMAND STAFF OFFICES, IN AN
AMOUNT NOT TO EXCEED SEVENTY-SEVEN
THOUSAND SIX HUNDRED FIFTY DOLLARS
($77,650.00), IN A FORM ACCEPTABLE TO THE CITY
ATTORNEY; PROVIDING FOR INCORPORATION OF
RECITALS; PROVIDING FOR AN EFFECTIVE DATE
WHEREAS, in 2021, the City of Opa-Locka ("City") received a grant from the
Florida Department of Law Enforcement for the Demolition and Rehabilitation of the Old
Police Station (2495 Ali Baba Avenue) and Relocation of the new Police Station in the
amount of One Million, One Hundred Twenty -Five Thousand Dollars ($1,125,000.00) and
WHEREAS, due to dilapidated conditions of the previous Police Station, the City
was unable to provide a safe workspace for the City's Police Force; and
WHEREAS, the grant that was provided to the City for the Project was not
sufficient enough to repair or replace the Police Station, with a cost projection at the time
of Ten Million Dollars ($10,000,000); and
WHEREAS, utilizing the City's Municipal Building, the original cost of
construction was One Million, Three Hundred Twenty -Three Thousand, Eight Hundred
Fifty Dollars ($1,323,850.00). The City Manager later determined that there should be a
relocation of the Police Station from the third floor to the first floor of the City's Municipal
Building; and
WHEREAS, to ensure all Police Force Departments were in one centralized space
for cohesive access and service as well as to avoid disruption in operations, the Command
Resolution No. 24-069
Staff (Chief, Captains, and Administration) offices were relocated; and
WHEREAS, a proposal in the amount of One Hundred Ninety -Nine Thousand
Five Hundred Dollars ($199,500.00) was received for this project; and
WHEREAS, however, during the construction phase of the project it was
determined that the existing HVAC System presented a major failure, with one
compressor inoperable and the second compressor performing at only Twenty -Five
percent (25%) of its capacity; and
WHEREAS, electrical upgrades were completed to adjust to a brand-new system
and layout that would comply with fire safety and ensure compliance with building
codes; in addition, architectural and engineering plans had to be developed. Acoustic
ceiling tiles were also modified due to the demolition of the old HVAC system and
installation of the new system. Further modifications to the framing were completed to
adjust and stabilize the bulletproof glazing, which was installed for safety and security
purposes; and
WHEREAS, the HVAC System installed on the Municipal Building's roof
represented an additional cost of Fifty -Seven Thousand, Five Hundred Dollars
($57,500.00). The additional necessary structural modifications performed due to this
change amounted to Twenty Thousand, One Hundred Fifty Dollars ($20,150.00), for a
total additional amount of Seventy -Seven Thousand Six Hundred Fifty Dollars
($77,650.00), as reflected in the invoices attached hereto as Exhibit "A"; and
WHEREAS, the City Manager is requesting an additional amount of Seventy -
Seven Thousand Six Hundred Fifty Dollars ($77,650.00) to relocate the Police Station
Command Staff Offices as a change to the scope for work to be performed. An
amendment to the project agreement is also necessary; and
WHEREAS, since this project was related and subject to a grant completion and
reporting schedule as well as constrained timelines and constrained reporting for funding
and to avoid delays and the risk of losing the grant, we are bringing this to the attention
of the City Commission at the time the project has been finalized; and
WHEREAS, the City Commission finds it is the best interest of the City to ratify
the City Manager's decision to change the Scope of Services for the Police Department
Demolition and Rebuild/Relocation Project and further authorize the City Manager to
2
Resolution No. 24-069
execute an amendment to the agreement with Diamanti Construction & Development,
Inc to include additional work to relocate the New Police Department Command Staff
Offices, as described herein and in Exhibit "A" attached hereto, in an amount not to
exceed Seventy -Seven Thousand Six Hundred Fifty Dollars ($77,650.00), in a form
acceptable to the City Attorney.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF THE
CITY OF OPA-LOCKA, FLORIDA, THAT:
Section 1. Adoption of Representations. The foregoing "Whereas" clauses are
hereby ratified and confirmed as being true and the same are hereby made a specific part
of this Resolution.
Section 2. Approval of Agreement Amendment. The City Commission of the
City of Opa-Locka hereby ratifies the City Manager's decision to change the Scope of
Services for the Police Department Demolition and Rebuild/Relocation Project and
further authorizes the City Manager to execute an amendment to the agreement with
Diamanti Construction & Development, Inc to include additional work to relocate the
New Police Department Command Staff Offices, as described herein and in Exhibit "A"
attached hereto, in an amount not to exceed Seventy -Seven Thousand Six Hundred Fifty
Dollars ($77,650.00), in a form acceptable to the City Attorney.
Section 3. Scrivener's Errors. Sections of this Resolution may be renumbered
or re -lettered and corrections of typographical errors, which do not affect the intent of
this Resolution may be authorized by the Interim City Manager, following review by the
City Attorney, without need of public hearing, by filing a corrected copy of same with
the City Clerk.
Section 4. Effective Date. This Resolution shall be effective immediately upon
adoption hereof and approval by the Governor of the State of Florida or Governor's
designee.
PASSED and ADOPTED this 24th day of April, 2024.
3
Resolution No. 24-069
ATTEST:
APPROVED AS TO FORM
AND LEGAL SUFFICIENCY:
a Flores, City Clerk
Bii/404-6/ 1
6,-,
urnadette Norris-Welks,T'.A.
Moved by: Commissioner Bass
Seconded by: Vice Mayor Ervin
VOTE: 4-0
Commissioner Bass Yes
Commissioner Kelley Yes
Commissioner Williams Absent
Vice Mayor Ervin Yes
Mayor Taylor Yes
4
DocuSign Envelope ID: Al A4D6A5-59A7-4C4C-81C0-8B3A691A2847
City of Opa-Iocka
Agenda Cover Memo
Department
Manager:
Adelina Gross
Department
Manager
Signature:
Docu5I7nad by.
[t �
ErazacaPQ 44Slgned by:
City
Manager:
Darvin Williams
CM Signature:
pp,,
0U� --
`—C46C07C1E8DE492...
Commission
Meeting
Date:
April 24,
2024
Item Type:
(EnterX in
the box)
Resolution
Ordinance
Other
X
Fiscal Impact:
(EnterX in the
box)
Yes
No
Ordinance Reading:
(EnterX in the box)
1st Reading
2nd
Reading
X
Public Hearing:
(Enter X in the box)
Yes
No
Yes
No
X
X
Funding
Source:
Account#: 44-
538638
(Enter Fund &
Dept.)
CIP-Safe
Neighborhood
Advertising Requirement:
(Enter X in the box)
Yes
No
X
Contract/P.O.
Required:
(Enter Xin the
box)
Yes
No
RFP/RFQ/Bid#:
N/A
X
Strategic Plan
Related (Enter
X in the box)
Yes
No
Strategic Plan Priority
Enhance Organization
Bus. & Economic
Public Safety
Quality of Education
Qual. of Life & City
Lommunicauon
Strategic Plan
Obj./Strategy: (list the
specific
objective/strategy this
item will address)
Area: •
X
•
Development
Ni
•
Image
n
I I
Sponsor
Name:
City Manager
Department:
Capital Improvements Program
Department
Submission
Date:04/8/2024
Short Title:
A resolution of the City Commission of the City of Opa-locka authorizing the ratification of the
additional expenditures for the Police Department Command Staff located in Suite 110.
Staff Summary:
In 2021 the City received a grant from the Florida Department of Law Enforcement for the Demolition
of the Old Police Station (2495 Ali Baba Avenue) Rehabilitation of the building and Relocation of the
Police Station in the amount of $1,125,000.00. Due to the conditions of mold, mildew, and the
dilapidated condition of the previous Police Station, it was unable to provide a safe work space for our
Police Force. The amount of the grant was insufficient to repair or replace the Police Station which costs
average approximately $10 million. Accordingly, the grantor approved a request to utilize the grant
funds to develop a new Police Station inside City Hall at 780 Fisherman Street.
DocuSign Envelope ID: A1A4D6A5-59A7-4C4C-81 C0-8B3A691A2847
To ensure all Police Force Departments were in one centralized space for cohesive access and service
and to avoid disruption in operations, the Command Staff (Chief, Captains, and Administration) offices
which were slated to remain on the 3rd Floor of the Municipal Building, it was later recommended that
Command Staff also be relocated to the First Floor adjacent to the new Main Station. Since this space,
which was previously rented by Workforce, was vacated by the tenant and was available it became the
best option.
A proposal in the amount of $199,500.00 was received for this project and during the construction of
the project it was determined that the existing HVAC System presented a major failure with one
compressor not working and the second compressor only working at 25% of its capacity. Electrical
Upgrades were needed to be completed to adjust to a brand-new system and layout that would comply
with fire safety and ensure compliance with building codes in addition Architectural and Engineering
Plans had to be developed. Acoustic Ceiling tiles had to be modified due to the demolition of the old
HVAC system and installation of the new system, in addition, modifications to the framing were needed
to adjust and stabilize the bulletproof glazing which was installed for safety and security purposes.
The HVAC System installed on the Roof represented an additional cost of $57,500 and the additional
structural modifications needed to be performed due to this change amounted to $20,150, for a total
additional amount of $77,650.00.
Since this project was related and subject to a grant completion and reporting schedule as well as
constrained timelines and constrained reporting for funding and to avoid delays and the risk of losing
the grant, we are bringing this to the attention of the City Commission at the time the project has been
finalized.
Staff recommends the approval of the additional $77,650.00 to the project to pay the Contractor who
completed the project in good faith and without any issues.
Financial Impact:
The additional funding for the project will be addressed under Budget Amendment No.3 after the City
Commission's Approval.
Proposed Action:
Staff recommends the City Commission authorize the Interim City to add the additional funding of
77,600.00 to the project of relocating the Command Staff of the Police Department to Suite 110 of the
Municipal Building.
Attachment(s):
1. Agenda
2. OLPD Suite 110 Change Order List
OLPD - Ste. 110 Renovations
Change Orders List
CO #
Name
Cost
Reason For Change
1
Storefront Wall Framing
$ 4,500.00
Storefront Wall Framing.
2
Architectural and Engineering D
$ 8,500.00
Development of Architectural and Engineering Plans.
- Architectural
- Mechanical
- Electrical
- Fire Safety
3
New HVAC System
$ 57,500.00
New HVAC system installation.
Tests were performed to the existing HVAC system and they failed.
Final decision was made to replace the AC system.
4
Electrical
$ 5,575.00
Original bid included just repairing and using the existing electrical system, but during demolition, it was
noticed that the conditions and layout of existing electrical system were not in compliance.
Electrical engineer developed the plans to install a dedicated panel and a new electrical run from suite
5
Acoustic Ceiling
$ 1,575.00
The Initial bid of $5,000 was only for repairs and using the existing grid and panels.
Because the demolition of the old HVAC system and the installation of a new one, the entire ceiling grid
and panels had to be installed new.
Total $ 77,650.00
CONSTRUCTION CHANGE ORDER
PROJECT NAME
OLPD - Ste. 110 Renovations -
LOCATION OF WORK
780 Fisherman St. Ste. 105, Opa-Iocka
CHANGE ORDER #.
OLPD Cmd CO - 1 (Storefront Wall Framing)
CONTRACT #.
2023-01-015
DATE OF REQUEST
10/27/2023
REQUESTING PARTY
Diamanti Construction
RFI #.
OWNER
City of Opa-locka
CONTRACTOR
Diamanti Construction
ARCHITECT
BEA Architects
ENGINEER
CHANGE REQUEST OVERVIEW
REASON FOR CHANGE
Storefront Wall Framing.
SUPPORT & JUSTIFICATION
DOCUMENTS
See attached.
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIMES
NET CHANGES OF PREVIOUS
CHANGE ORDERS
$
NET CHANGES OF PREVIOUS
CHANGE ORDERS IN DAYS
No impact
NET INCREASE / DECREASE
$ 4,500.00
NET INCREASE / DECREASE
No impact
TOTAL APPROVED CHANGE
ORDERS
4'500'00
TOTAL CONTRACT TIME WITH
APPROVED CHANGES
No impact
APPROVAL
SUBMITTED BY
CONTRACTOR
DATE
APPROVED BY
OWNER
DATE
r,
REVIEWED BY
ARCHITECT
DATE
Mohammed S. Islam
Diamanti Const. President
Nader Goubran, Architect
Darvin William
Interim City Manager
CONSTRUCTION CHANGE ORDER
PROJECT NAME
OLPD - Ste. 110 Renovations - COMMAND STAFF STATION
LOCATION OF WORK
780 Fisherman St. Ste. 105, Opa-locka
CHANGE ORDER #.
OLPD Cmd CO - 2 (A/E Drawings)
CONTRACT #.
2023-01-015
DATE OF REQUEST
10/27/2023
REQUESTING PARTY
Diamanti Construction
RFI #.
OWNER
City of Opa-locka
CONTRACTOR
Diamanti Construction
ARCHITECT
BEA Architects
ENGINEER
Nader Goubran, Architect
CHANGE REQUEST OVERVIEW
REASON FOR CHANGE
Development of Architectural and Engineering Plans.
- Architectural
- Mechanical
- Electrical
- Fire Safety
SUPPORT & JUSTIFICATION
DOCUMENTS
See attached.
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIMES
NET CHANGES OF PREVIOUS
CHANGE ORDERS
4,500.00
NET CHANGES OF PREVIOUS
CHANGE ORDERS IN DAYS
No Impact
NET INCREASE / DECREASE
$ 8,500.00 NET INCREASE / DECREASE
No impact
TOTAL APPROVED CHANGE
ORDERS
TOTAL CONTRACT TIME WITH
13,000.00 APPROVED CHANGES
No Impact
APPROVAL
SUBMITTED BY
CONTRACTOR
DATE
APPROVED BY
OWNER
DATE
t,_ _._
REVIEWED BY
ARCHITECT
DATE
Mohammed S. Islam
Diamanui Const. President
Nader Goubran, Architect
Darvin William
Interim City Manager
OLPD — 780 Fisherman St. Ste 110
Construction Change Order Details
CO 3 — New HVAC System
CONSTRUCTION CHANGE ORDER
PROJECT NAME
OLPD - Ste. 110 Renovations - COMMAND STAFF STATION
LOCATION OF WORK
780 Fisherman St. Ste. 105, Opa-locka
CHANGE ORDER #.
OLPD Cmd CO - 4 (Electrical)
CONTRACT #.
2023-01-015
DATE OF REQUEST
10/27/2023
REQUESTING PARTY
Diamanti Construction
RFI #.
OWNER
City of Opa-locka
CONTRACTOR
Diamanti Construction
ARCHITECT
BEA Architects
ENGINEER
CHANGE REQUEST OVERVIEW
REASON FOR CHANGE
Original bid included just repairing and using the existing electrical system, but during demolition, it was
noticed that the conditions and layout of existing electrical system were not in compliance.
Electrical engineer developed the plans to install a dedicated panel and a new electrical run from suite
115 (old kitchen).
SUPPORT & JUSTIFICATION
DOCUMENTS
See attached.
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIMES
NET CHANGES OF PREVIOUS
CHANGE ORDERS
$ 1 3,000.00
NET CHANGES OF PREVIOUS
CHANGE ORDERS IN DAYS
No impact
NET INCREASE / DECREASE
$ 5,575.00
NET INCREASE / DECREASE
No impact
TOTAL APPROVED CHANGE
ORDERS $
18,575.00
TOTAL CONTRACT TIME WITH
APPROVED CHANGES
No impact
APPROVAL
SUBMITTED BY
CONTRACTOR
DATE
APPROVED BY
OWNER
DATE
",
)` __—
REVIEWED BY
ARCHITECT
DATE
Mohammed S. Islam
Diamanti Const. President
Nader Goubran. Architect
Darvin William
Interim City Manager
OLPD — 780 Fisherman St. Ste 110
Construction Change Order Details
CO 4 — Electrical
CONSTRUCTION CHANGE ORDER
PROJECT NAME
OLPD - Ste. 110 Renovations - COMMAND STAFF STATION
LOCATION OF WORK
780 Fisherman St. Ste. 105, Opa-locka
CHANGE ORDER #.
OLPD Cmd CO - 5 (Acoustic Ceiling)
CONTRACT #.
2023-01-015
DATE OF REQUEST
10/27/2023
REQUESTING PARTY
Diamanti Construction
RFI #.
OWNER
City of Opa-locka
CONTRACTOR
Diamanti Construction
ARCHITECT
BEA Architects
ENGINEER
CHANGE REQUEST OVERVIEW
REASON FOR CHANGE
The Initial bid of $5,000 was only for repairs and using the existing grid and panels.
Because the demolition of the old HVAC system and the installation of a new one, the entire ceiling grid
and panels had to be installed new.
SUPPORT & JUSTIFICATION
DOCUMENTS
See attached.
CHANGE IN CONTRACT PRICE
CHANGE IN CONTRACT TIMES
NET CHANGES OF PREVIOUS
CHANGE ORDERS
13,000.00
NET CHANGES OF PREVIOUS
CHANGE ORDERS IN DAYS
No impact
p
NET INCREASE / DECREASE
$ 1,575.00
NET INCREASE / DECREASE
No impact
TOTAL APPROVED CHANGE
ORDERS
1 4,575.00
TOTAL CONTRACT TIME WITH
APPROVED CHANGES
No impact
p
APPROVAL
SUBMITTED BY
CONTRACTOR
DATE
APPROVED BY
OWNER
DATE
�__1
REVIEWED BY
ARCHITECT
DATE
Mohammed S. Islam
Diamanti Const. President
Nader Goubrau, Architect
Darvin William
Interim City Manager
OLPD — 780 Fisherman St. Ste 110
Construction Change Order Details
CO 5 — Acoustic Ceiling