HomeMy Public PortalAboutChange Order No. 2 to Contract No. 130-2022 - SAK Construction - sewer rehabilitation RICHMOND SANITARY DISTRICT 2380 Liberty Avenue,Richmond,IN 47374 CHANGE ORDER#2 FINAL Change Order Date: April 3,2023 Owner: Richmond Sanitary District Contract No.: 130-2.022 Contractor: SAK Construction,LLC Contract Date: September 7,2022 Project: 2022 Sewer Lining Project Project No.: The Contract Documents are modified as follows upon execution of this Change Order: Item# Description Qty Change Unit Cost/Unit Total Increasel(Decrease) Increase 1 Protruding Tap iemoyal(Undistributed) 3 [a $ 425.00 $ 1,275,00 Increase 3 Lateral/Sewer Reinstatement 1. Ea $ 100.00 $ 100.00 Increase 4 CIPP Lining-8"Sewer from WM14.6-04.0 to MH#1.46-039 2 LF $ 32.00 $ 64.00 Increase 5 CIPP Lining-8"Sewer from MH#146-039 to MH#146-038 24 Li $ 32.00 $ 768.00 Increase 9 CIPP Lining-8"Sewer from MH#202-043 to MH#202-070 1 LF $ 32.00 $ 32.00 Decrease 10 Lateral/Sewer iā€¢einstatement .-4 Ea $ 100,00 $ (400,00) Increase 11. CIPP Lining-12'Sewer from MH#164-089 to MH#183-099 1 LF $ 51.00 $ 51..00 Decrease 12 Lateral/Sewer Reinstatement -2 Ea $ 100.00 $ (200.00) Increase 14 Lateral/Sewer Reinstatement 3 Ea $ 100.00 $ 300.00 Decrease 1.5 CIPP Lining-8"Sewer from MH#163-096 to MH#163-095 -165 LE $ 32.00 $ (5,280,00) Increase 15 CIPP Lining- 1.2'Sewer from MH#163-096 to MR41.63-095 1.62 Li $ 51.00 $ 8,262.00 Decrease 16 CIPP Lining-8"Sewer from MH#1.63-095 to MH#163-084. -212 Li $ 32.00 $ (6,784.00) Increase 16 CIPP Lining-1.2"Sewer from MH#1.63-095 to MH#163-084. 213 Li $ 51..00 $ 10,863.00 Decrease 17 Lateral/Sewer Reinstatement -1 Ea $ 1.00,00 $ (100.00) Decrease 1.8 CIPP Lining-8"Sewer from MH#129-007 to MH#129-02.4A -1.26 Li $ 32.00 $ (4,032.00) Increase 19 CIPP Lining-8''Sewer from MH#1.29-024A to MH#129-024 103 LF $ 32,00 $ 3,2916.00 Decrease 21 Lateral/Sewer Reinstatement -14 Ea $ 100.00 $ (1,400.00) Decrease 22 CIPP Lining-10"Sewer from MH#088-01.6 to MH#088-014 -40 If $ 36.00 $ (1,44I0.00) Increase 22 Cleaning-10"Sewer from MH#088-01.6 to MH#088-015 40 L.F $ 4.50 $ 1£30.00 Decrease 24 CIPP Lining-10°'Sewer from MH#088-018 to MI-1#088-021 -308 LI" $ 36.00 $ (11,088.00) Increase 24 Cleaning-10"3ewer from MH#088-01.8 to MH#088-02.1. 308 LF $ 4.50 $ 1,386.00 Decrease 25 CIPP Lining..10"Sewer from MH#088-021 to MH#088-020 -230 LF $ 36.00 $ (8,280.00) Increase 25 CIPP Lining-8'Sewer from MH#088-021 to MH#088-020 229 Li $ 32,00 $ 7,328.00 Decrease 2.6 CIPP Lining-.101"Sewer from MH#088-020 to MH#088-025 220 Li $ 36,00 $ (7,920.00) Increase 26 CIPP Lining-8 Sewer from MH#088-020 to MI34088-025 220 Li $ 32.00 $ 7,040.00 Decrease 28 CIPP Lining-8"Sewer from MH#088-0.1.4 to MH#088-023 -273 Li $ 32.00 $ (8,736.00) Add 28A CIPP Lining.-8"Sewer from MH#088-024 to MH#088-023 270 LE $ 32.00 $ 8,640.00 Increase 29 Lateral/Sewer Reinstatement 3 Ea $ 100.00 $ 300.00 Decrease 30 CIPP Lining-9'Sewer from MH#182-021 to MH#182-022 -2. L.F $ 64.00 $ (1.28.00) Add 30A 8"Wetout Liner 159 Li $ 1.0.15 $ 1,613.85 Increase 31 Lateral/Sewer Reinstatement 6 Ea $ 100.00 $ 600.00 Decrease 32 CIPP Lining-1.3"Sewer from MH#1.27-026 to MH#128-015 -1 Li $ 36.00 $ (36,00) Decrease 33 Lateral/Sewer Reinstatement .-36 Ea $ 100.00 $ (3,600.00) Decrease 34 CIPP Lining-8"Sewer from MH4159A-01.9 to Mil#159A-045 -144 Li $ :32.00 $ (4,608.00) Add 34A CIPP Lining-87'Sewer from Mil#1.59A-045.to MH#159A-021. 156 Li $ 32.00 $ 4,992.00 Decrease 35 CIPP Lining-87'Sewer from MH#1.59A-021 to MIlt11.59A-022. -1 Li $ 32..00 $ (32.00) Decrease 36 CIPP Lining-F"Sewer from Mil#159A-021 to MH#159A-023 -1 Li $ 32.00 $ (32.00) Increase 37 CIPP Lining-E"Sewer from MH#1.59-007 to Midti1..59A-01.0 1. Li $ :32..00 $ 32.00 Increase 38 CIPP Lining.g"Sewer from MH#159A-01.0 to Mil#1.59A-009 2 LF $ 32.00 $ 64.00 Increase 55 CIPP Lining-15" 5 Li $ 1.25.00 $ 625.00 Decrease 56 CIPP Lining-21" -206 Li $ 154.00 $ (31,724..00) Increase 56 CIPP Lining-21" 166 Li $ 1.81.06 $ :30,055,96 Decrease 57 CIPP Lining-24" -3 Li $ 220.00 $ (660.00) Add 58 Lateral/Sewe-Reinstatement 6 Ea $ 1.00.00 $ 600.00 NET CHANGE $ (8,012..19) Page 1 of 2 RICHMOND SANITARY DISTRICT 2380 Liberty Avenue,Richmond,IN 47374 CHANGE ORDER#2 FINAL Change Order Date: April 3,2023 Owner: Richmond Sanitary District Contract No.: 130-2022 Contractor: SAK Construction,LLC Contract Date: September 7,2022 Project: 2022 Sewer Lining Project Project No.: CHANGE IN CONTRACT PRICE Original Contract Price: $307,711.00 Net change from Previous Change Orders: $43,697.00 Contract price prior to this Change Order: $351,408.00 Net increase/(decrease)of this Change Order: ($8,012.19) Contract price with all approved Change Orders: $343,395.81 Percentage of increase/(decrease)with Change Orders: 11.60% CHANGE IN CONTRACT COMPLETION TIME Original Completion Time(days): (225 Substantial,255 Final) Net change fro-n Previous Change Orders: (0 Substantial,0 Final) Completion time prior to this Change Order: (225 Substantial,255 Final) Net increase/decrease of this Change Order: (0 Substantial,0 Final) Completetion time with all approved Change Orders: (225 Substantial,255 Final) This Change Order is for complete and final settlement of all direct and indirect costs,impact costs and time extensions incurred at any time'esulting from the performance of the changed work or associated claims, Recommended by: 4/26/23 Richmond Sanitary District Engineer Date Accepted by: Owner: Richmond Sanitary District Boar President Signature Date Contractor: 4.26.2023 SAK Construction,LLC Authorized Signature Date Page 2 of 2