HomeMy Public PortalAboutChange Order No. 1 to Contract No. 54-2023 - Brackney Inc. - construction for lift station for Hayes RICHMOND SANITARY DISTRICT
2380 liberty Avenue,Richmond,IN 47374
CHANGE ORDER#1
Change Order Date: February 27, 2024
Owner: Richmond Sanitary District Contract No.: 54-2023
Contractor: Brackney,Inc. Contract Date: April 11,2023
Project: Hayes Lift Station and Forcemain Improvements Project Project No.: 520150
SRF Project No.: WW22198909
CHANGE IN CONTRACT PRICE
Original Contract Price: $3,315,715.00
Net change from Previous Change Orders: $0.00
Contract price prior to this Change Order: $3,315,715.00
Net increase/(decrease)of this Change Order: 65,000.00)
Contract price with all approved Change Orders: $3, 50,715.00
Percentage of Increase/(decrease)with Change Orders: -1.96%
CHANGE IN CONTRACT COMPLETION TIME
Original Completion Time(days): (545 Substantial,575 Final)]
Net change from Previous Change Orders: (0 Substantial,0 Final)
Completion time prior to this Change Order: (545 Substantia,575 Final)
Net increase/decrease of this Change Order: (0 Substan ial,0 Final)
Completetion time with all approved Change Orders: (545 Substantial,575 Final)
This Change Order is for complete and final settlement of all direct and indirect costs, impact costs and time
extensions incurred at any time resulting from the performance of the changed work or associated claims.
This Change Order is Subject to Final Approval by Funding Agency(SRF).
Recommended by: - 02/22/2024
Richmond Sanitary District Engineer Date
Accepted by: //
/ c.44 27
Owner: 74
Richmond Sanitary District bard President Signature Date
Contractor:
63.7-02;'4262
Brackney, Inc. Authorize,• Signature Date
Page 2 of 2
RICHMOND SANITARY DISTRICT
2380 Liberty Avenue,Richmond,IN 47374
CHANGE ORDER
Change Order Date: Februa 27,2024
Owner: Richmond Sanitary District Contract No.: 54- 023
Contractor: Brackney, Inc. Contract Date: April 1 ,2023
Project: Hayes Lift Station and Forcemain Improvements Project Project No.: 520150
SRF Project No.: WW22198909
The Contract Documents are modified as follows upon execution of this Change Order and Approval by SRF:
Item# Description Ctty Change Unit Cost/Unit Totatincrea /(Decrease)
Decrease 11-01 Bore and Jack-18-INCH Diameter Casing -325 IF $ 1,000.00 $ (325,000.00)
Add 11-01A Bore and Jack-18-INCH Diameter Casing-HDPE 325 IF $ 800.00 $ 260,000.00
NET CHANGE $ (65,000.00)
Page lof2