Loading...
HomeMy Public PortalAboutRitz-Mason proposal P.A.STOWN OF GULF STREAM Subsurface Utility Engineering (SUE) Services for Watermain Location at Place Au Soleil DATE: October 21, 2022 SCOPE OF WORK The Town of Gulf Stream (Town) has requested Baxter & Woodman, Inc. (Consultant) to provide subsurface utility engineering (SUE) services for the locating of the existing watermain in the Place Au Soled neighborhood. Consultant will subcontract these services to Ritzel-Mason, Inc. to provide the services as described in the attached Fee Proposal by Ritzel-Mason dated October 13, 2022. Consultant shall provide services for preparation of the contract and to provide invoicing services to the Town. ASSUMPTIONS In addition to the work items discussed above, the following assumptions were made in establishing the scope of this Task Order and associated fee. Changes and/ or modifications in the above work items or these assumptions are considered an Additional Services Item under the terms of the contract. Assumptions include: • No engineering design or field inspection services are provided with this contract. The work will be a "pass -though" of Ritzel-Mason's services contract. ADDITIONAL SERVICES The following are examples of some specific Additional Services Items that may be required but are not included within this Proposal. Generally, a condition contrary to the work description in or assumptions in the previous sections are considered an Additional Services Item. SUMMARY OF PROPOSED FEES: Compensation by the Town to Consultant for the services described in this Work Order will be in accordance with the method of payment indicated below and detailed in Exhibit B. Tasks Task 1 — Contract coord & Invoicing Ritzel-Mason (subconsultant) Incl 10% markup 10/22/22 Cost $ 342 (Lump Sum) $ 2,299 (Lump Sum) Total $ 2,641.00 IN WITNESS WHEREOF, the parties have made and executed this Agreement on the respective dates under each signature. TOWN OF GULF STREAM, through an authorized official of the Town and Baxter & Woodman, Inc. signing by and through Rebecca Travis (Executive Vice President) duty authorized to execute same. TOWN OF GULF STREAM: BAXTER & WOODMAN, INC.: By: By: Rebecca Travis, Executive Vice President Date: Date: 10/21/2022 10/22/22 « / C } _ \ \ es ] \ / ) ) J co §cu / z M G � L; } � & ^)C - 2 / / k )°) } } §}/}\ ±)> — J) - | _ !E|<(�) (\)\)7 k §|(( (TC)77) )f)})\ LXU / g|)) /|3;3 f ))(/)] J I j fQ RITZEL -MASON October 13, 2022 Rebecca Travis, PE Baxter & Woodman 477 S. Rosemary Avenue, Suite 330 West Palm Beach, Florida 33401 Subject: Fee Proposal for Utility Investigation Services Project: Place Au Soleil — Town of Gulfstream Dear Ms. Travis: Ritzel-Mason appreciates the opportunity to prepare this fee proposal for providing subsurface utility engineering (SUE) services on the above referenced project. Ritzel-Mason is registered and licensed in the state of Florida. This letter will serve as our official scope of services and is accompanied by the included fee estimate. The combination of our resources and experience will provide Baxter & Woodman (the Client) with the confidence that Ritzel-Mason is the right choice to complete the project on time and on budget. Ritzel- Mason has been requested by the Client to provide horizontal and vertical data on utilities. Proiect Limits: The limits of our investigation will include a portion of the entrance to Place Au Soleil being Avenue Au Soleil in Gulfstream, Florida. See attached exhibit for a depiction of the limits as highlighted in red. Scope of Services: Ritzel-Mason proposed SUE services as described below: Ritzel-Mason will complete a SUE investigation in general accordance with ASCE Standard 38-02: Standard Guidelines for the Collection and Depiction of Existing Subsurface Utility Data. This investigation will be exclusively focused on the watermain only. Ritzel-Mason will search for the existence and approximate location of subsurface utilities within the project limits except those listed under Exclusions below. The specific work includes: A. Records Research through customary means: a. Identify utilities anticipated to exist in the project limits. b. Document responses and compile record information. B. Field Investigation using appropriate surface geophysical techniques: a. Documented conductive utilities — designate with the objective of achieving Quality Level B for conductive utilities. Where not possible, lower Quality Levels will be established. Utilities of non-conductive material installed with serviceable tracer wire or tape will be considered conductive. It is important Ritzel-Mason, Inc. 5119 Beechwood Road Delray Beach, FL 33484 Phone: 786.472.0358 www.ritzel-mason.com Place Au Soleil Entrance October 13, 2022 ft\ QRITZEL -MASON to note, however, that the depicted location of such utilities represents the tracer rather than the actual utility. b. Documented non-conductive utilities — investigate with the objective of achieving Quality Level C. Where not possible, depict at Quality Level D. c. Undocumented utilities — are those utilities that may exist in the project area that have not been previously identified, are not discovered during records research, and for which there is no prior knowledge. Ritzel will use our standard search protocol in an attempt to determine the existence and approximate location of undocumented utilities; however, this work cannot guarantee that all utilities will be found and depicted. C. Quality Level exceptions — the following utilities will be investigated with the objective of achieving the specific Quality Level stated: a. Gravity sanitary sewers — Quality Level C. b. Non-conductive utilities with ready access allowing sonde, metal tape or detection rod insertion and tracking — Quality Level B. c. Subaqueous crossings — Quality Level D. D. Vacuum Excavation — Test holes a. Ritzel-Mason proposes to use vacuum excavation equipment to perform up to 2 test holes at locations as directed by the client. Vacuum excavation methods will enable Ritzel-Mason to visualize the utility in question for a high degree of certainty. Ritzel-Mason will make every effort to vacuum excavate to a depth of eight (8) feet using high pressure air methods. However, vacuum excavation will cease when these methods are unable to progress below refusal, such as bedrock or flowable fill. Ritzel-Mason will not employ destructive methods, such as jackhammers or chipping hammers, to break up bedrock or other refusal within a test hole due the high risk of damage to buried utilities and safety risk to employees. Utilities deeper than 8 feet may not be found. b. At the completion of each excavation Ritzel-Mason will place an iron rod and cap or a nail and disk at the test hole location and further identify the test hole location with paint marks on the ground surface. We will backfill with native material and compact the soil in 6"-12" lifts as well as provide a permanent restoration of the pavement or ground surface within the limits of the original excavation. We will record maximum depth of the test hole as well as vertical depth of any utility encountered. If a utility is encountered, we will also provide utility type, size, shape, material, and orientation to the extent we are able to ascertain this information c. Ritzel-Mason will notify Sunshine 811 2 full business days in advance of excavation. Ritzel-Mason will mark the conductive utilities by inductive methods utilizing electromagnetic geophysical prospecting equipment. Known non-conductive utilities will be marked utilizing 2-D Radar (GPR). d. Due to mobilization costs a minimum of 4 test holes can be requested or mobilization costs will be charged. This cost is waived for this project. e. Ritzel-Mason cannot provide vacuum excavation in areas where obstructions, such as unmovable vehicles or storage exist. www.ritzel-mason.com Place Au Soleil Entrance October 13, 2022 ft\ 7 RITZEL -MASON Basis and Assumptions: Unless specifically stated otherwise in the Scope of Services, this proposal is conditioned on the following. Differences may result in necessary changes to the proposed scope and fee. • Ritzel-Mason will have ready access to the project area. Construction or clearing activities required for access to perform field services are not included. • Standard Maintenance of Traffic (MOT) is included. Extraordinary MOT such as lane closures, route detouring, crash trucks, off -duty police officer, railroad flagging fees and other efforts deemed atypical are not included. • Field work can be completed within normally accepted business hours and without the need for overnight or weekend work. • Possible delays due to weather conditions will be discussed with the client and may affect schedule. • Confined space entry is excluded. • Entry onto private property beyond incidental, or where prohibited, is not included. • Entry into buildings is not included. • Permits are not included but can be requested, if needed at additional cost. Client Responsibilities: • Participate in permit applications as needed. • Assist Ritzel-Mason as able in obtaining records of utilities in the project area owned by others. • Provide or facilitate access to project area for field investigations. Deliverables: • Paint marks and flags will depict the approximate horizontal position of underground utilities detected • Test hole data sheets Schedule: We propose to mobilize for this work 5 business days from receipt of this proposal duly signed and barring any unforeseen condition. Fees: Utility Designating SUE Services as described above for a lump sum fee of $1,290 (includes minor MOT services) Vacuum Excavation Services as described above for a lump sum fee of $800 for up to 2 test holes. Invoices: All invoices are due and payable in full upon receipt of survey. Surveyor reserves the right to withhold certified prints and files to client or client's consultants until payment is made in full. CAD file (if part of deliverables) will not be released until invoice is paid in full. If payment is not received within 35 days of the invoice date, a late charge may be added to the invoice in an amount not to exceed 1'/2 percent per month on the outstanding balance. If payment is not received within 60 days of the invoice date, Surveyor may terminate this agreement or suspend work under the agreement until payments have been made in full. The undersigned agrees to pay reasonable www.ritzel-mason.com Place Au Solell Entrance October 13, 2022 zt\ `QRITZEI., -MASON attorney fees up to 50% and all costs and expenses incurred by Ritzel-Mason in the collection of any past due obligation of the undersigned pursuant hereto. Basis: The fees listed above are based on Ritzel-Mason's crews being able to work during the hours of 7:00am to 6:00pm and being granted access to the site. Nighttime or weekend work may incur additional fees. Nighttime work shall be any time outside of regular work hours being 7:00am to 6:00pm. Ritzel-Mason is equipped to supply minor MOT services. The client will be responsible for providing major MOT assistance, such as lane closures. Ritzel- Mason's field crews and equipment are not equipped or prepared to work in any area that possibly are, or may have been, contaminated with hazardous materials at any time. Any fee or permit requested in order to perform the work will be submitted to the client at cost. Again, we appreciate the opportunity to provide our surveying services for Baxter & Woodman. Please call me directly at 786.472.0358, if you have any questions or comments. We look forward to beginning work on this project upon receiving your authorization to proceed. Sincerely, Dennis Ritzel, PSM Director of Business Operations 786.472.0358 Email: den nis(o)-ritzel-mason.com Date Accepted: Company: Signature: Title: Exhibit www.ritzel-mason.com