HomeMy Public PortalAbout2007-60 Public Beach-Sand Dune Restoration ProjectRESOLUTION NO. 2007-60
A CAPITAL PROJECT AUTHORIZING RESOLUTION OF
THE VILLAGE COUNCIL OF THE VILLAGE OF KEY
BISCAYNE, FLORIDA, CONCERNING THE PUBLIC
BEACH, SAND DUNE RESTORATION PROJECT (THE
"PROJECT"); AUTHORIZING PURCHASE OF SAND AND
SAND TRANSPORT AND DELIVERY SERVICES; AND
AUTHORIZING PURCHASE OF ADDITIONAL SERVICES
CONCERNING PLACEMENT OF SAND FOR
IMPLEMENTATION OF THE PROJECT; AUTHORIZING
VILLAGE MANAGER TO EXECUTE PURCHASE ORDERS
AND RELATED DOCUMENTS AND AGREEMENTS FOR
THE PROJECT; AUTHORIZING EXPENDITURE OF FUNDS;
AUTHORIZING IMPLEMENTATION; PROVIDING FOR AN
EFFECTIVE DATE.
WHEREAS, the Village Council, upon the recommendation of the Village Manager,
desires to restore the sand dunes at a portion of the public beach situated in the Village (the
"Project") pursuant to the plans prepared by the Project engineer, Coastal Systems International, Inc.;
and
WHEREAS, the Village Council finds that the purchase of the sand, the transport of the sand
to the public beach site, and the placement of the sand on the public beach for the Project, are in
whole or in part, exempt from competitive bidding pursuant to Village Code Section 2-86, as being
based upon a bid awarded by Miami -Dade County, and that, in any event, the Council hereby
further finds that pursuant to Village Code Section 2-85 competitive bidding is impractical for the
Project and does hereby waive competitive bidding for the purchase, transport, delivery and
placement of the necessary sand and for related activities for the Project; and
WHEREAS, the Village Council finds that the Project is necessary for the enhancement of
the use and enjoyment of the public beach and is in the best interests of the Village.
NOW, THEREFORE, IT IS HEREBY RESOLVED BY THE VILLAGE COUNCIL
OF THE VILLAGE OF KEY BISCAYNE, FLORIDA, AS FOLLOWS:
Section 1. Recitals Adopted. That each of the recitals stated above is hereby adopted
and confirmed.
Section 2. Capital Project Authorizing Resolution.
A. That pursuant to Village Charter Section 3.07(b), this Resolution shall constitute a
Capital Project Authorizing Resolution. The Capital Project is the implementation of the above
described Project at a total cost not to exceed Three Hundred Thousand ($300,000) Dollars.
B. That the components of the Project consist of the following:
(1) The purchase of approximately 3,500 cubic yards of sand;
(2) The transport and delivery of all of the purchased sand to the public beach staging
area of the Project site; and
(3) The preparation, placement and contouring of sand placed at the dune restoration
area of the Project site.
Section 3. Project Authorized; Transaction Approved.
A. That the Project is hereby authorized. The Project is further described in the Project
Engineer's plans, a copy of which are on file with the Village Clerk.
B. That the Village Council hereby authorizes the Village Manager to provide for the
completion of the Project for a cost which is consistent with this Resolution, to be funded from the
funding source which is identified in the Village Manager's memorandum which accompanies this
Resolution.
2
C. That the Village Manager is hereby authorized to execute the necessary purchase
orders and related documents and agreements for the Project, once approved by the Village Attorney
as to form and legal sufficiency.
D. That the Village Manager is authorized to expend Village funds or third party funds
obtained for such purpose for the accomplishment of the Project in accordance with Village budget
appropriations and this Resolution.
E. That the Village Manager is authorized to take any action which is necessary to
implement the Project, including, but not limited to, arranging for the provision of engineer
inspections of the Project work by the Project Engineer.
Section 4. Effective Date. That this Resolution shall be effective immediately upon
adoption hereof
PASSED AND ADOPTED this 4th day of December, 2007.
ATT
4
oyAi
HITA H. ALVAREZ, CMC, VILLAGE CLERK
APPROVED AS 0 FORM AND LEGAL SUFFICIENCY:
VILLAGE ATTO Y
F:\100\103001\Resolutions\Capital Project Re Restoration of the Public Beach Sand Dune.doc
MAYOR ROBERT L. VERNON
3
VILLAGE OF KEY BISCAYNE
Office of the Village Manager
Village Council
Robert L. Vernon, Mayor
Jorge E. Mendia, Vice Mayor
Michael Davey
Enrique Garcia
Steve Liedman
Thomas Thornton
Patricia Weinman
Village Manager
Genaro "Chip" Iglesias
DATE: November 28, 2007
TO: Honorable Mayor and Members of the V ge Coun
FROM: Genaro "Chip" Iglesias, Village Man
RE: Dune Restoration Project
RECOMMENDATION
It is recommended that the Village Council authorizes the Village Manager to utilize Miami
Dade County's pre -approved vendor list for the purchase, transportation and placement of
sand to be used in the Village's Dune Restoration Project.
The project cost is not to exceed $300,000 as per the attached resolution. Funding will be
obtained from the capital outlay beach renourishment line item.
BACKGROUND
Due to past hurricanes, the dune areas in front of the Silver Sands Motel and the Ocean
Club have been compromised. The dunes need to be restored and enhanced.
On November 14, 2006, Council awarded Coastal Systems International the consulting
engineering contract for the Restoration Project.
cc:
Randy White, Village Finance Director
David M. Wolpin, Esq., Village Attorney
88 West McIntyre Street • Suite 210 • Key Biscayne, Florida 33149 • (305) 365-5500 • Fax (305) 365-8936
MISSION STATEMENT FO PROVIDE A SAFE QUALITY COMMUNITY ENVIRONMENT FOR ALL ISLANDERS THROUGH RI-SPONSIBLE GOVERNMENT'
www.keybiscayne.fl.gov
( O A S I A 1
SV STF'1S
1S 1, N'a llll\;
O \0, i V •,}'S I I ,N1c, I'C'I 1:RN_A 1 10v \I ., I \(
164 :-.,4,uth I )tvu 11iihu a% • ( -t oral (rt) ilc�, f Ir>r �1,t 5 1(1
i el. .;(P- (,(,1 ;655 • 1 ax: i(t' 661 1'914
�t \\ UnsInt cum
January 4. 2008
Mr. Armando Nunez
Public Works Director
1/11AAGE OF KEN BISc.AI NE
88 West McIntyre Street
Key Biscay ne. Florida 33149
1 5040,01-A
RE: CONSULTING SERVICES FOR VILLAGE OF KE1 BtSCa%NI•; BEACH RENOt RISH1-IEN1, MIAMI-
DADE COI NT1, FLORIDA
Dear Mr. Nunez:
Pursuant to our recent discussions. Coastal Systems International, inc. (Coastal Systems) is pleased
to submit this addendum proposal relative to the above referenced project. This scope of services is
for the construction administration and surveying required for the dune restoration project.
Specifically. the following, presents a detailed scope of work for additional sere ices to be provided by
Coastal Systems for the Village of Key Biscayne (Village):
PART 27 — DUNE CONSTRICTION ADMINISTRATION
a. Dune Construction Administration: Coastal Systems will provide construction administration
services for the dune restoration project. The restoration project will be procured through
approved Miami -Dade vendors, and no bid process will he conducted. These services \vill
include the following during the estimated construction schedule of 1.5 months. as applicable:
• Attend one ( 1 ) Pre -Hid Meeting with approved Vendors
• Prepare construction budget based on Vendor unit rates and estimated quantities
• Attend one ( 1 ) Preconstruction Meeting
• Attend t\ () (2) construction progress meetings
• Sand samplinu and testing with five (5) gradation tests
• Coordinate survey efforts under Part 28 services
• Weekly email updates to Client on Construction Progress
• Responses to Requests for information (RFIs)
• Prepare and process DEP Progress Reports
• Reviev. and approval of payment applications.
Coastal, l'.n‘ ii minental, Civil F,n nnccnnt; and Management
135040.01-A
Mr. Armando Nunez
January 4. 2008
Page 2
h. Dune Construction Site Visits: Coastal Systems skill make fifteen (15) site visits to observe the
construction progress over the estimated 1.5 month construction schedule. These site visits will
occur approximately 3 times per week. or as directed by the Client. Coastal System, will observe
construction progress to ensure the work is conducted in accordance with the construction
documents and permits. Photographs will be obtained to document the ongoing construction.
Held reports will he prepared with representative photographs incorporated for distribution to the
Client.
PART 28 — DUNE CONSTRICTION SURVEN {1G
a. Pre -Construction Dune Restoration Survey: Coastal Systems wilt conduct beach profile
surveys of the proposed dune restoration project areas within 30 days prior to construction.
Profiles will he surveyed from the landward edge of the dune out to wading depth. and survey
data will he obtained with total station or RTK (BPS equipment. 'Temporary survey control will
he established and provided to the contractor for use in construction staking, and the limits of the
project delineated in the field. The survey data will be processed in the office and compared to
the dune design data. Estimated volumes to fill the dune design template will he updated and
compared to the contract quantities. The quantities will be reviewed with the Client, and updated
cross sections provided to the contractor as applicable.
Deliverables: Permit Sketches with updated profiles and dune fill volumes
b. Post -Construction Dune Restoration Survey: Coastal Systems will conduct beach profile
surveys of the proposed dune restoration project areas within 15 days after completion of
construction. Profiles will he surveyed from the landward edge of the dune out to wading depth,
and survey data will be obtained with total station or RTK GPS equipment. The survey data will
he processed in the office and compared to the pre -construction survey and dune design data.
Construction volumes will he compared to the delivery truck tickets.
1)eliverahle.s• Permit it Sketches with as -hunt data and dune fill volumes
c. DEP Permit Close -Out: Subsequent to completion of construction. Coastal Systems will
schedule and attend one (1) on -site Final Inspection meeting with the City, DEP Field
Representative and Project Contractor, as required by the Special Permit Conditions outlined in
the DEP Permit modification. Coastal Systems will distribute copies of the DEP Final Inspection
Report to the project team and follow up with the DEP to confirm that close-out of this phase of
the permit is documented in their system. If any project elements are not built in compliance
with the DEP permit and additional coordination and/or meetings are required. these services will
he provided under a separate scope.
(1. DEP Dune Restoration Suney Report: Coastal Systems will prepare and submit the as -built
survey data in standard DEP survey format, including the range files. ASCII XYZ data_ plots of
data on the aerials with range monuments identified, etc. A surveyor report will he prepared to
document all of the field work conducted.
Deliverables: As -Built Stirrer data and plots in /)EP format with surve>or report,
( c►.�•tal h nt 1r(nnrncntal. (:i Engineering and tanagt•rnt nt
135040.01-A
Mr. Armando Nunez
Januar;' 4. 2008
Page 3
ci,Q.1Je(isealed ht' a Florida Registered Surveyor .'11a/1)er
GENERAL
Fees for the services are attached as Table I. This fee proposal is valid for sixty (60) days. Services
will be provided as an addendum to the Beach Nourishment contract dated August I. 2006. Coastal
Systems is not responsible for circumstances beyond our immediate control. including but not limited
to. rule or legal interpretation changes. Client or agency staff delays, and litigation or other legal
actions. The Client shall make payment to Coastal Systems upon receipt of an invoice. Invoices not
paid within thirty (30) days and not in dispute shall incur interest at a rate of 1.5 percent per month,
The Client agrees to pay any cost of collection including reasonable attorneys fees incurred whether
or not a suit is commenced or an appeal is taken.
We look forward to working with the Village to finalize plans and authorization for this mitigation
project. Please return an executed copy of this addendum, which will serve as our Authorization to
Proceed. Should you hate any questions. please do not hesitate to contact me at (305) 661-3655 ext.
13 I or icederher�� a Loastalsv stemstnt.Lottt or Timothy, Blankenship at 305-661-8650 or
!blUnhe nshi _ a c oastalsv tits m tlit.cont.
Sincerely,.
J
CANTAL SI' TEN NTERNATIONAL, L C.
SIGNED:
Print:
FKB:mr
Enclosures
,LACE, OF KEN
SC ANAL
jeStei
Dame Title
Timothy K. Blankenship, P
Director
f c (0ntract Roil. A.count,;)., (JR 'MB IC JRC,JMS "+(1 L�
I Pnlect 1 ;cit4tt 01' P.np nal me Uo { :) PRO \*mnn3.h \ure: I)jrn• (0n. '4cno I idnnmaranon (t,X
ef
"A",
i)A FE:
( oastal, 1n\irunmental, Civil Engineering and \lanagcmn(•nt
3 40 /dk
TABLE 1
SUMMARY OF FEES FOR DUNE CONSTRUCTION ADMINISTRATION SERVICES
VILLAGE OF KEY BISCAYNE, FLORIDA
DESCRIPTION
TYPE
TOTAL COST
Part 27 - Dune Construction Administration
a) Construction Administration
b) Site Visits
Hourly, Estimated at
Hourly, Estimated at
$6,000
$8,300
Subtotal:
$14,300
Part 28 - Dune Construction Surveying
a) Pre - Construction Dune Restoration Survey
b) Post - Construction Dune Restoration Survey
c) DEP Close -Out
d) DEP Dune Restoration Survey Report
Lump Sum
Lump Sum
Lump Sum
Lump Sum
$3,100
$2,600
$2,100
$2,000
Subtotal:
$9,800
Estimated Reimbursable Expenses
$2,049
TOTAL FEES:_
$26,149