HomeMy Public PortalAbout2006-39 Work Authorization with Tetra Tech, IncRESOLUTION NO. 2006-39
A RESOLUTION OF THE VILLAGE COUNCIL OF THE
VILLAGE OF KEY BISCAYNE, FLORIDA, AUTHORIZING
THE FURTHER PROCUREMENT OF ENGINEERING
SERVICES INCLUDING SURVEY, DESIGN, PERMITTING,
BIDDING AND CONSTRUCTION ADMINISTRATION
ENGINEERING SERVICES FOR DRAINAGE
IMPROVEMENT PROJECT (THE "PROJECT") FOR
WOODCREST ROAD, GLENRIDGE ROAD AND
BUTTONWOOD DRIVE (EAST AND WEST), FROM THE
FIRM OF TETRA TECH, INC. (FORMERLY KNOWN AS
WILLIAMS HATFIELD & STONER); PROVIDING FOR
APPROVAL OF WORK AUTHORIZATION PURSUANT TO
CONTINUING CONTRACT; PROVIDING FOR
IMPLEMENTATION; PROVIDING FOR AN EFFECTIVE
DATE.
WHEREAS, pursuant to Resolution No. 98-34, the Village of Key Biscayne entered into
a series of continuing contracts with engineering firms for necessary services; and
WHEREAS, the engineering firm of Williams Hatfield & Stoner, now known as Tetra Tech,
Inc. (the "Engineer") is under a continuing contract to the Village as authorized by Resolution No.
98-34; and
WHEREAS, the Village finds that it is in the best interest of the Village to utilize the
Engineer for the purpose of performing all necessary engineering services for the drainage
improvement project, which includes Woodcrest Road, Glenridge Road and Buttonwood Drive (East
and West), (the "Project"), in accordance with the attached Work Authorization and with the Village
Manager's Memorandum, which accompanies this Resolution.
NOW, THEREFORE, IT IS HEREBY RESOLVED BY THE VILLAGE COUNCIL
OF THE VILLAGE OF KEY BISCAYNE, FLORIDA, AS FOLLOWS:
Section 1. Recitals Adopted. That each of the above stated recitals is hereby adopted
and confirmed.
Section 2. Work Authorized, Specification of Funds. That pursuant to the existing
continuing contract between the Village and the Engineer, the performance of additional engineering
services for survey, design, permitting, bidding and construction administration services for the
Project is hereby authorized, subject to the funding source and any limitation set forth in the above -
referenced Village Manager's Memorandum.
Section 3. Agreement Approved. That the Village Manager is hereby authorized to
execute the Work Authorization in substantially the form attached hereto, for the Engineering work
authorized hereunder between the Village and the Engineer, once approved by the Village Attorney
as to form and legal sufficiency.
Section 4. Implementation.
That the Village Manager is hereby authorized to take any and all action which is necessary
to fully implement the purposes of this Resolution and the Work Authorization.
Section 5. Effective Date. That this Resolution shall be effective immediately upon
adoption hereof.
PASSED AND ADOPTED this 5th day of September, 2006.
AT
CHITA H. ALVAREZ, CMC, VILLAGE CLERK
Cetpt_.6(1,--,
MAYOR ROBERT OLDAKOWSKI
APPROVED AS TO ORM AND LEGAL SUFFICIENCY:
VILLAGE ATTO
103.001/Resolutions/Authorizing f her engineering services 8.31.06
2
VILLAGE OF KEY BISCAYNE
Office of the Village Manager
Village Council
Robert Oldakowski, Mayor
Robert L. Vernon, Vice Mayor
Enrique Garcia
Steve Liedman
Jorge E. Mendia
Thomas Thornton
Patricia Weinman
Village Manager
Jacqueline R. Menendez
DATE: August 21, 2006
TO: Honorable Mayor and Members of the Village Council
FROM: Jacqueline R. Menendez, Village Manag '° ;" I '....
RE: Drainage Improvement Project
!)6,0
RECOMMENDATION
It is recommended that the Village Council approves the proposal submitted by Tetra Tech, Inc.
for the Drainage Improvement Project for Woodcrest Road, Glenridge Road and Buttonwood
Drive (East and West) in the Village of Key Biscayne, as per their analysis attached hereto.
BACKGROUND
Tetra Tech, Inc. (formerly known as Williams Hatfield & Stoner) is the engineering firm who
developed, designed and administered the construction of the VKB Stormwater Master Plan.
The engineering fee for this project is sixty one thousand dollars ($61,000.00). The drainage
improvements will consist of installing a series of inlets and pipes that connect to an existing
deep drainage well, installed under a previous project. The services provided will be the
following:
• Surveying the areas
• Permitting
• Design
• Bid/Award Process
• Construction Administration/Inspection
The funding for this project is a matching state grant, covering fifty (50%) percent of the costs
incurred during this project. The remaining funds will come from the capital outlay fund.
cc: Randy White, Village Finance Director
David M. Wolpin, Esq., Village Attorney
88 West McIntyre Street • Suite 210 • Key Biscayne, Florida 33149 • (305) 365-5500 • Fax (305) 365-8936
MISSION STATEMENT "TO PROVIDE A SAFE, QUALITY COMMUNITY ENVIRONMENT FOR ALL ISLANDERS THROUGH RESPONSIBLE GOVERNMENT."
www. keyb iscayne. f l.gov
TETRA TECH, INC.
June 16, 2006
Mr. Armando Nunez
Public Works Director
Village of Key Biscayne
85 West McIntyre Street
Key Biscayne, FL 33149
Mr. Nunez:
Village of Key Biscayne
Drainage Improvements For:
Woodcrest Road, Glenridge Road, and Buttonwood Drive (East and West)
Professional Services Fee Proposal
Tetra Tech, Inc. is pleased to present this professional services fee for the Drainage Improvements Project
for Woodcrest Road, Glenridge Road, and Buttonwood Drive (East and West). TetraTech, Inc. (formerly
known as Williams Hatfield & Stoner) has been providing professional engineering services for the Village
of Key Biscayne (VKB) for over ten (10) years. We developed the VKB Stormwater Master Plan and
designed and administered the construction for virtually all of the drainage improvements that exist within
the VKB city limits today.
The drainage improvements for Woodcrest Road and Glenridge Road areas will consist of installing a
series of inlets and pipes that connect to an existing deep drainage well installed under a previous project
The drainage improvements for Buttonwood Drive (Fast and West) will consist of similar components,
except a new deep drainage well will need to be installed for this portion of the project. Our Fee includes
surveying the areas, permitting the new drainage system at Buttonwood Drive, developing construction
documents for the drainage improvements, assisting with the Bidding, and providing construction services.
We have attached our Proposed Schedule to perform this work, and have included duration of time
estimated for bidding, award and construction.
Our proposed fee for professional services is detailed below:
Topographic Survey $6,000
Permitting $2,500
Design $26,000
Bid/Award $1,500
Construction Administration/ Inspection $25,000
Fee Total $61,000
We look forward to working with the Village on the Project. Geotechnical and Soils Testing will be billed
directly to the Village on a pass through basis.
Respectfully,
Andrew Kacer, P.E.
Senior Project Manager
TetraTech, Inc.
201 West Canton Avenue, Suite 125
Winter Park, Florida 32789
Voice: 407.644.0857
Fax: 407.644.7544
Cell: 352.279.4979
TETRA TECH, INC.
VILLAGE OF KEY BISCAYNE
FOR: DRAINAGE IMPR O VEVIENTS AT WOODCREST ROAD,
GLENRIDGE ROAD, AND BUTTONWOOD DRIVE
PROJECT SCHEDULE
TASK DAYS DATES
DESIGN NTP 1 TBD
SURVEY 21
DESIGN 60
BIDDING 30
AWARD 30
CONSTRUCTION 120
Prepared By:
Andrew Kacer, FL PE No. 44720
TetraTech, Inc.
201 West Canton Avenue, Suite 125
Winter Park, Florida 32789
Voice: 407.644.0857
Fax: 407.644.7544
Cell: 352.279.4979