HomeMy Public PortalAbout2006-45 Conversion to Underground FacilitiesRESOLUTION NO. 2006-45
A RESOLUTION OF THE VILLAGE COUNCIL OF THE
VILLAGE OF KEY BISCAYNE, FLORIDA, AUTHORIZING
THE FURTHER PROCUREMENT OF ENGINEERING
SERVICES INCLUDING DESIGN, PERMITTING, BIDDING
AND CONSTRUCTION ADMINISTRATION ENGINEERING
SERVICES FOR THE CONVERSION OF OVERHEAD
POWER -TELEPHONE -CABLE UTILITIES TO
UNDERGROUND FACILITIES FOR THE VILLAGE OF KEY
BISCAYNE, FROM THE FIRM OF CORZO CASTELLA
CARBALLO THOMPSON SALMAN, P.A. ("C3TS");
PROVIDING FOR APPROVAL OF WORK
AUTHORIZATION PURSUANT TO CONTINUING
CONTRACT; PROVIDING FOR IMPLEMENTATION;
PROVIDING FOR EFFECTIVE DATE.
WHEREAS, pursuant to Resolution No. 98-34, the Village of Key Biscayne entered into
a series of continuing contracts with engineering firms for necessary services; and
WHEREAS, the engineering firm of Corzo Castella Carballo Thompson Salman, P.A.
("C3TS") is under a continuing contract to the Village as authorized by Resolution No. 98-34; and
WHEREAS, the Village finds that it is in the best interest of the Village to utilize C3TS for
the purpose of performing all necessary engineering services for the conversion of overhead power
— telephone -cable utilities to underground facilities (the "Project") in accordance with the attached
Work Authorization and with the Village Manager's memorandum, which accompanies this
Resolution.
NOW, THEREFORE, IT IS HEREBY RESOLVED BY THE VILLAGE COUNCIL
OF THE VILLAGE OF KEY BISCAYNE, FLORIDA, AS FOLLOWS:
Section 1. Recitals Adopted. That each of the recitals stated above is hereby adopted
and confirmed.
Section 2. Work Authorized, Specification of Funds. That pursuant to the existing
continuing contract between C3TS and the Village, the performance of additional engineering
services for design, permitting, bidding and construction administration services for the Project, is
hereby authorized, subject to the funding source and any limitations set forth in the above referenced
Village Manager's memorandum.
Section 3. Agreement Approved. That the Village Manager is hereby authorized to
execute the Work Authorization in substantially the form attached hereto, for the engineering work
authorized hereunder between the Village and C3TS, once approved by the Village Attorney as to
form and legal sufficiency.
Section 4. Implementation. That the Village Manager is hereby authorized to take any
necessary action to implement the purposes of this Resolution and the Work Authorization.
Section 5. Effective Date. That this Resolution shall be effective immediately upon
adoption hereof.
PASSED AND ADOPTED this 24th day of October, 2006.
/to Ve,t,a L, —
MAYOR ROBERT OLDAKOWSKI
CONCHITA H. ALVAREZ, CMC, VILLAGE CLERK
APPROVED AS TO FORM AND LEGAL SUFFICIENCY
VILLAGE TO
103.001/R.esolutions/Convers 'n to nderground Facilities 10.18.06
2
Village Council
Robert Oldakowski, Mayor
Robert L. Vernon, Vice Mayor
Enrique Garcia
Steve Liedman
Jorge E. Mendia
Thomas Thornton
Patricia Weinman
Village Manager
Jacqueline R. Menendez
VILLAGE OF KEY BISCAYNE
Office of the Village Manager
October 17, 2006
MEMORANDUM
TO: Honorable Mayor and Members of the Village Council
FROM: Jacqueline R. Menendez, Manager' Village Man ..
'' Pit
RE: Conversion of Overhead Utilities
RECOMMENDATION
It is recommended that the Village Council approve the Work
Professional Services between Corzo Castella Carballo Thompson Sal an, for
("C3TS") and the Village for the purpose of performing all necessary en an, P.A.
services for the conversion of overhead power, telephone, and cable engineering
underground facilities. utilities to
BACKGROUND
The engineering firm of Corzo Castella Carballo Thompson Salman, P.
A. is under a continuing contract to the Village as authorized by Resolution ("C3TS")
98-34
At the direction of the Village Council on October 10th, 2006, C3TShas prepared 9p e.
a Work Order for Professional Services for the performance of engineering
services for design, permitting, bidding and construction administration services
eri or
the conversion of overhead utilities. C3TS will coordinate on behalf for
with FPL, Bellsouth and Adelphia Cable to coordinate and review the utility
y
conversion plans. the utility
Funding for these services will be taken from the Capital Outla 's Vision Projects. See attached proposal. Y line item for
88 West McIntyre Street • Suite 210 •
Key Biscayne, Florida 33149 • (305) 365-5500 •Fax (305) 365-8936
MISSION STATEMENT "TO PROVIDE A SAFE QUALITY COMMUNITY ENVIRONMENT FOR ALL ISLANDERS THROUGH RESPONSIBLE GOVERNMENT
www.keybiscayne; figou
11.„,-9
CORZO
Engineers
Architects
Planners
E80005022
AAC002142
TO:
ATTENTION:
PROJECT NAME:
WORK ORDER FOR PROFESSIONAL SERVICES
Village of Key Biscayne
88 West McIntyre Street
Key Biscayne, Florida 33149
Ms. Jacqueline Menendez
Village Manager
Conversion of Overhead Power/Telephone/Cable
Utilities to Underground Facilities
Village of Biscayne, Florida
SCOPE OF SERVICES:
initial Coordination
DATE: 10/16/06
FILE: 1108
A) Coordinate with FPL, BellSouth and Adelphia Cable to develop a phasing plan for the
proposed conversion in coordination with sewer project. We will obtain revised ball park
estimates. and initiate engineering design on behalf of the Village. During this phase,
we will consult with and update the Village Council on proposed phasing, costs and
schedules.
Utility Planning & Design Coordination
A) Coordination on behalf of the Village with FPL, BellSouth, and Adeiphia Cable to
coordinate and review preliminary utility conversion plans. This includes review of
existing and proposed systems, utility conflicts, establishment of preferred routes and
locations for the new facilities. This effort also involves meeting with affected
homeowners in up to three public meetings per phase.
B) Assist Village in obtaining required easements as needed by utilities for conversion work.
Our services do not include the preparation of survey sketches and legal descriptions or
recording of easements, but we will have these prepared by surveyors as needed, and
invoice the Village for these services as a reimbursable expense.
C) Coordination on behalf of the Village with FPL, BellSouth, and Adelphia to obtain from
each a final design for the new underground facilities, along with a firm proposal for the
conversion work. Coordination on behalf of the Village with FPL, BellSouth and
Adelphia to initiate the work.
Restoration Planning, Design and Bidding
A) Establish scope and extent of restoration needs for proposed utility work including
roadways, driveways, sidewalks and landscaping, Develop a set of restoration plans,
details and specifications and a set of general restoration guidelines to be included in a
unit -price restoration package for bid.
B) Assist Village in bidding the restoration package, reviewing bids obtained and providing
recommendation for award.
901 Ponce de Leon Blvd., Suite 900 Coral Gables, Florida 33134 305.445.2900 1.800.448.0227 Facsimile 305.445.3366
Web Site: www.c3ts.com Equal Opportunity Employer
W.O. Conversion Utilities Underground
October 16, 2006
Page 2
Utility Construction Monitoring
A) Monitor and coordinate on behalf of the Village the phased utility conversion work to be
performed by FPL, BellSouth, and Adeiphia Cable or their designated contractors.
Restoration Construction Administration
A) Prepare Contract Documents, Notice of Award and Notice to Proceed.
B) Attend pre -construction conference and periodic progress meetings and prepare
minutes for distribution.
C) Respond to Contractor request for information )RFI) and clarification/interpretation of
contract documents.
D) Process all Construction correspondence and maintain files.
E) Field measurement of completed restoration items.
F) Review and make Recommendations for Contractor payment requisitions.
G) Provide periodic inspection services.
M) Provide final inspection, punch -list, and contract close-out.
FEES
Our fee for the above described services shall be as follows:
Initial Coordination $6,500
Utility Planning & Design Coordination (assuming 4 phases) . . , . $18,500 per phase
Restoration Planning, Design and Bidding $35,000
Utility Construction Monitoring 1.0% of construction cost
for each phase
Restoration Construction Administration 3.0% of construction cost
W.O. Conversion Utilities Underground
October 16, 2006
Page 3
We are ready to begin working on this assignment upon your authorization to proceed. If acceptable
to you, we will accept a signed copy of this form as your written authorization to proceed with the
assignment.
Thank you.
..Ga Cast rballq Thorson Salman, P.A.
Ramon Castella,
Principal
RC/er
Villa• - o' Key Biscayne
A•.ro -d b
Date:
L', Proiects11108-001dV 0-Prd asalsl 0101606ConvitduiesUnderground doc
1 ' 4
5
Mon 10/16/06
ID Task Name
1 Initial Coordination
2 Utilities Phase 1
Initiate Utility Design
Preliminary Utility Design
Village Review & Approval
Final Utility Design & costing
7 Village Appr of Agreement
8 Construction
9 !Utilities Phase 2
r 10 initiate Utility Design
11 - • Preliminary Utility Design
12 Village Review & Approval
13 i Final Utility Design & costing
14 , Village Appr of Agreement
15 1 Construction
16 1 Utilities Phase 3
-TY-7 Initiate Utility Design
18 Preliminary Utility Design
19 Village Review & Approval
20 Final Utility Design & costing
21 Village Appr of Agreement
22 Construction
23 Utilities Phase 4
— 24
24 Initiate Utility Design
25 Preliminary Utility Design
26 Village Review & Approval
27 Final Utility Design & costing
28 J Village Appr of Agreement
29 Construction
30 Restoration Package
— 31 initiate Design
32 Prepare Plans & Specs
!i 33 - Prepare Bid package
! 34 1 Bid Phase
35 1 Construction
.
Project Key Biscyane UG Utilities
Date: Mon 10/16106
Village of Key Biscayne
Utilities UG Relocation
C3TS
Q3'06 104 'D6 Q1'07 :Q2'07 !03'07 Q4 '07 IQ1'08 Q2'08 03'08 '04'08 Q1'09 €Q2'09 ;Q3'09 'Q4'09 (Q1'10 :Q2'10 tQ3'10 {
♦ 12/1
2/28
k 1
Task j Milestone
Split Summary
Progress 111111111111111111111111111111111111111111 Project Summary
. 12/29
• 7/28
•
Irmogiongol
Total Duration: 41.1 mons? Page 1
External Tasks
External Milestone
Deadline