Town of Gulf Stream| Core Area Neighborhood Improvements 2
Project Team
Project Owner
Construction Project Manager
Richard Chipman, CGC
Construction Inspector
Ron Sellers
Project Manager/Utilities
Sira “Jockey” Prinyavivatkul, PE
Project Engineer/Stormwater
Jeff Hiscock, PE
Construction ContractorConsulting Engineer
Town Commission
Scott Morgan, Mayor
Thomas Stanley, Vice Mayor
Robert Canfield, Commissioner
Michael Greene, Commissioner
Joan Orthwein, Commissioner
Town Manager
Greg Dunham
Managing Member
Silvio Rubi
Senior Project Manager
Thomas Weeks Jr, P.E.
Project Manager
Jorge Perez
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 3
Meeting Agenda
Project Objectives
Project Summary
Construction Management
Introduction of Construction Contractor
Construction Schedule & What Residents Can Expect
How to Stay Informed
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 4
■Roadway
─Replace damaged pavements.
─Improve surface drainage.
■Stormwater Management
─Reduce flooding/ponding.
─Improve water quality.
■Water Main
─Replace asbestos cement pipes.
─Upsize for improved fire flows.
─Relocate meters from alley.
Project Objectives
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 5
■Demolish and remove
existing pavement.
■Regrade roadway.
■Install new pavement.
■Install Type F Curb and
Gutter at strategic
locations.
■Install 2-foot Valley
Gutters throughout.
Project Summary: Roadway Improvements
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 6
Project : Roadway –Existing Conditions
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 7
Project Summary: Roadway –Existing Conditions
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 8
Project Summary: Roadway Improvements
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 9
Project Summary: Roadway Improvements
BEFORE AFTER
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 10
Project Summary: Stormwater Drainage Assessment
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 11
Stormwater Improvements
■Replacing 24” Pipe
with 48” Pipe
─Increase Discharge Rate
■Additional stormwater
inlet/culvert network
─Reduce nuisance
ponding
■Water Quality
Improvements
─Exfiltration Trench
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 12
Project Summary: Water Main Improvements
■Replacing aging asbestos
cement potable water mains.
■Increase pipe diameters in
strategic areas to improve fire
flow.
■Relocate water meters from
alleys to roadways.
■Replace and add fire hydrants
for improved fire protection
coverage.
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 13
Project Summary: Water Main Improvements
■Replacing aging
asbestos cement
potable water mains
■Increase pipe
diameters in strategic
areas to improve fire
flow.
■Relocate water
meters from alleys to
Roadways
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 14
Project Summary: Project Phasing
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 15
Construction Management
■Resident Concerns
■Coordination of Resident Needs with
Contractor & Town
■Daily Communication with Contractor
■Complaint Resolution
■Inspections
■Quality Assurance
■Project Updates
■Contract Administration
CONSTRUCTION
CONTRACTOR:
Roadway Construction LLC.
Miami, FL
Title
16Town of Gulf Stream| Core Area Neighborhood Improvements
Construction Schedule
APRIL 22 Initial mobilization: light activity, surveying, setting up Maintenance of Traffic devices, erosion control material delivery
APRIL 24 Phase 1 begins at Golfview Drive with Clearing & Grubbing operations
MAY 03 Removal of existing drainage begins on Polo Drive
JUNE 17 Watermain & Storm Water installation begins on Polo Drive
JULY 02 Phase 1 begins at Palm Way with Clearing & Grubbing operations
AUGUST 21 Phase 1 begins at Banyan Road with Clearing & Grubbing operations
NOVEMBER 06 Phase 1 begins at Wright Way with Clearing & Grubbing operations
DECEMBER 11 Phase 1 begins at Old School Road with Clearing & Grubbing operations
FEBRUARY 16 Phase 1 is substantially complete
FEBRUARY 17 Phase 2 begins with initial mobilization, light activity, setting up Maintenance of Traffic devices, erosion control
material delivery
FEBRUARY 20 Phase 2 begins at Gulfstream Road & Golfview Drive with Clearing & Grubbing operations
FEBRUARY 27 Watermain & Storm Water installation begins on Gulfstream
MARCH 20 Phase 2 begins at Middle Road with Clearing & Grubbing operations
2024
2025
Title
17Town of Gulf Stream| Core Area Neighborhood Improvements
Construction Schedule
APRIL 17 Phase 2 begins at Lakeview Drive with Clearing & Grubbing operations
JUNE 15 Phase 2 begins at Banyan Road with Clearing & Grubbing operations
JULY 16 Phase 2 begins at Oleander Way with Clearing & Grubbing operations
SEPTEMBER 02 Phase 2 begins at Bermuda Way with Clearing & Grubbing operations
OCTOBER 14 Phase 2 is substantially complete
OCTOBER 15 Final Asphalt placement begins on Phase 1 and Phase 2
DECEMBER 13 Final Completion of the Project
2025
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 18
What Residents Can Expect
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 19
What Residents Can Expect
We will be a Good Neighbor during construction!
Traffic Control
Contractor will be required to maintain access to driveways/individual properties.
Emergency vehicle access shall be maintained.
Impacts to Gulf Stream School drop off and pickup loop shall be minimized to the extent possible.
Access for residents with special needs shall be maintained.
Mail Delivery
Trash Pick-Up
Site Restoration
The contractor is responsible to prepare a pre-construction video and restore in-kind areas damaged during construction including driveways, and front-yard grass areas. Final restoration will be completed as one of the last stages of construction. A preconstruction video will be completed to document the existing conditions along the project area before the contractor begins work.
Title
Town of Gulf Stream| Core Area Neighborhood Improvements 20
How to Stay Informed
After construction begins, call the project hotline with any questions and let us know how we’re doing!
Toll -Free Project Hotline:
855-228-3436
■The construction of this project
will disrupt normal daily
transportation and other
activities in the neighborhood
■Your patience and cooperation
during these important
infrastructure improvements are
sincerely appreciated
■For updates visit the Project Web
site,
https://CoreAreaRoadwork.com
Town of Gulf Stream
Core Area Neighborhood Improvements
Pre-Construction Public Outreach Meeting
Thank You for Attending!
Please let us know if you have any questions