HomeMy Public PortalAbout07) 7D Traf UpgdCity Council
March 20, 2012
Page 2
approval.
4. On July 29, 2009, staff received the environmental clearance approval from
Caltrans .
5 . On October 22, 2009, staff prepared and submitted the request for authorization
to proceed with construction along with the plans and specifications to Caltrans.
6. On February 10, 2010, Caltrans obligated the HSIP funds and granted the City
authorization to proceed with the construction .
7. On May 4, 2010, the City Council approved the plans and specifications for this
project and authorized staff to solicit bids.
8. On May 1 0, 2010, a Notice Inviting Bids was published in the Pasadena Star
News and the bid plans and specifications were made available to prospective
bidders.
9 . On May 26, 2010, a mandatory pre-bid meeting was held and six contractors
attended this meeting.
1 0. On June 1, 201 0, the City Clerk opened and recorded a total of four bids for the
project.
11 . On July 20, 2010, the City Council awarded a construction contract in the
amount of $119,849 .00 to Christopher A Morales, Inc. (Contractor) for the traffic
signal upgrades on Temple City Boulevard at Las Tunas Drive and Baldwin
Avenue and Olive Street.
12. Between January and April, 2011, the contractor ordered and procured the traffic
signal poles for both intersections of Temple City Boulevard and Las Tunas
Drive, and Baldwin Avenue and Olive Street.
13. In April 2011, the contractor discovered the existing traffic signal wires were
permanently attached within the existing conduits and could not be used . Upon
discovery of this situation, construction manager, Arjan ldnani, and the contractor
met in the field to assess the contractor's findings and determine the most cost
effective solution.
14. On August 16, 2011, the City Council approved Progress Payment No. 1 in the
amount of $33,514.39 for the purchase of the traffic signal poles and related
equipment.
15. On August 25, 2011, the construction manager and the contractor discussed and
agreed to the additional scope of work and price. Subsequently, a request for
authorization was submitted to Caltrans on that same day to allocate the
additional needed funds as part of the grant.
City Council
March 20, 2012
Page3
16. On September 13, 2011, Caltrans approved the scope change in the amount of
$81 ,803.00 to be included as part of the grant funded scope . This allowed the
City to be eligible for reimbursement of the additional project costs related to the
wiring issues.
17. October 18, 2011 , the City Council approved Change Order No. 1 in the amount
of $81,803.00 for the installation of six new conduits at the intersections of Las
Tunas Drive and Temple City Boulevard, and one new conduit at the intersection
of Baldwin Avenue and Olive Street. City Council also approved and amended
the budget by appropriating $73,622 of HSIP funds and $13,180 of Measure R
funds for the project.
18. On December 6, 2011, the City Council approved Progress Payment No.2 in the
of $29,999.98 for construction services performed on the upgrade of the traffic
signals at the two intersections, Temple City Boulevard at Las Tunas Drive and
Baldwin Avenue at Olive Street.
19. On December 12, 2011, the contractor provided the Construction Manager, Arjan
ldnani, with Progress Payment No.3 in the amount of $127,164.73. This invoice
encompasses the completion of the construction improvements for this project.
20. On January 17, 2012, City Council approved Progress Payment No.3 in the
amount of $127,164.73 for the completion of the improvements which included
the upgrade of the traffic signals at two intersections, Temple City Boulevard at
Las Tunas Drive and Baldwin Avenue at Olive Street.
ANALYSIS:
On July 20, 2010, the contractor, Christopher A. Morales, Inc. (CRMI), was awarded a
construction contract for the upgrade of the traffic signals at two critical intersections,
Temple City Boulevard at Las Tunas Drive and Baldwin Avenue at Olive Street in the
amount of $119,849.00.
In consultation with the city's traffic engineer and the Director of Community
Development, the Construction Manager, Arjan ldnani and the contractor Christopher
A. Morales, Inc. (CRMI) both agreed during the course of construction that two change
orders were necessary to properly complete construction of the project. Change Order
No. 1 was presented and approved by the City Council in the amount of $81,803.00 for
the installation of six new conduits. Upon completion of the work associated with change
order no.1, a cost adjustment was made in the amount of $7,437.16, which resulted in a
final change order amount of $74,365.84. A second change order was issued in the
amount $6,500 to cover the cost of relocating a pole. The change order was
administratively approved in accordance with the construction contract, which provided
a 10% contingency to be used at the discretion of the staff.
On December 9, 2011, the contractor Christopher A. Morales, Inc. (CRMI) completed
all construction activity for the Traffic Signal Upgrades on Temple City Boulevard at Las
City Council
March 20, 2012
Page4
Tunas Drive and Baldwin Avenue at Olive Street. The total construction cost of the
project is $200,714.84. To date the contractor has been paid $190,679.10.
A final inspection has been conducted and it is determined that the project was
completed satisfactorily and in conformance with the project plans and specifications.
Staff has also reviewed the project file and determined that Christopher R. Morales, Inc.
(CRMI) is in compliance with all federal requirements. In addition, on February 27,
2012 a file review was performed by Caltrans with project staff and there were no
findings .
CONCLUSION:
The contractor has completed the construction of all improvements in accordance with
the contract and has complied with all federal requirements . It is recommended that the
City Council accept the project as complete, authorize the City Clerk to file the Notice of
Completion and release the final retention payment in the amount of $10,035.74 at a
minimum of 35 days after filing the Notice of Completion.
FISCAL IMPACT
Funding for this project was included in the Fiscal Year (FY) 2011-12 City Budget. With
regard to design it should be noted that the project was originally designed into two
separate projects based on the two grant applications submitted . Upon award, the
projects were combined into one due to the projects location . As such, the design and a
portion of costs associated with funding administration and project coordination were paid
in FY 2009-2010 and 2010-2011 . The following are the funding sources utilized to pay for
costs associated with the project:
Highway Safety Improvement Funds (HSIP)
MeasureR
General Funds
Total
$181,296.75
$ 50,980.00
$ 35,768.84
$268,045.59
The following are the final costs incurred for this project for construction, design,
construction management, material testing, funding administration, labor compliance,
project coordination services and miscellaneous costs for publishing :
Christopher Morales
Crown City Engineers
Avant-Garde
MTG Geotechnical Engineers
Miscellaneous Costs
Total Costs
$200,714.84
$ 46,841.75
$ 19,000.00
$ 726.00
$ 763.00
$268,045.59
City Council
March 20, 2012
PageS
ATT ACHMENT(S)
a) Christopher R. Morales, Inc.-Final Retention Payment, invoice 10-61
b) Notice of Completion
License No. 858974 C10
Bill To :
AAE Incorporated
1815 E. Heim Ave., Suite 100
Orange . CA 92865
ITEM
NO.
01
02
03
C001
C002
DESCRIPTION
Modification Of TraffiC Signals And Safety Ligh~ng At Tlte Intersection
OfT em pie City Blvd. & Las Tunas Dr.
Modification Of Traffic Signals And Safely lighting AI The lnler.;ection
Of Baldwin Ave. & Olive St.
Construct Curb Ramp Including Excavation And Backfill
Change Order
Extra Work: New Plans-New Conduit And Pull Boxes.
Temple City & las Tunas· $53 ,251.27
Baldwin & OWve · $21.1 14.57
Extra Work: Pole 1 location Change
.
---··--~ --
Subtotal
Original Contract Amount
Change Order/Extra Amt Approved Prior Period
Change Order/Extra Amt Approved This Period
Revised Contract Amount
Inspector
Project Manager
CHRISTOPHER R. MORALES, INC.
P.O. Box 610, San Dimas , CA 91773
(909) 599-2201 -Fax (909) 599-2722
)
10 No. 52 -2448934
Christopher R. Morales Job No . I 0-61
Invoice No. 718-l06lr
Invoice Date: 01-26-12
Due Date: 02-05-12
Attn:
Subject:
Re · -·--
CONTRACT
QTY UIM UNIT PRICE
1 LS $ 55,649.00
1 LS $ 51,000.00
1 LS $ 13,200.00
1 LS $ 74,365 .84
1 LS s 6,500.00
Mr. Arjan ldnani
.. ----
Temple City Blvd ., Trclffic Signal Modifications
CIP P09-0l & P09-02-FP:-1; HSIPL-5365(006)
REMAINING 5% RETENTION BILLING
PREVIOUS PERIOD CURRENT PERIOD
AMOUNT QTY. AMOUNT .(.ITY. AMOUNT
s 55,549.00
$ 51,000 .00
$ 13,200.00
$ 7 4.~
$ 6,500 .00
$ 119,849.00
$
$ 80 ,865.84
$ 200,714.84
100%
100%
100%
100%
10 0%
.
$ 55,649.00 0% $ -,
......
$ 51';-QOO.OO 0% $
$ 13,2~ 0% $ -,
$ 74,365 84 ~ ~--
$ 6,500.00 0% s
~.
$ 200,714 .84 $
Gross Amount Earned To Date
Less: Retention (0%)
Net Amount Earned To Date
Less : Previous Payment
.
-
.
.
..........
.
Less : Previous Billing Not Yet Paid
TotCII Oue
TOTAL TO DATE
QTY.
100%
1000k
100%
100%
,_
100%
AMT
$ 55 ,649.00
$ 51 ,000 .00
$ 13,200.00
$ 74,365.84
$ 6,500.00
s 200.714.84
$
$ 200,714.84
$ (190,679.10 )
$
$ 10,035 .74