MAYOR AND CITY CLERK TO EXECUTE A CONTRACT WITH B. D. SIMON
CONSTRUCTION COMPANY FOR THE TEMPORARY USE OF A PORTION OF CITY
STREETS DURING A STATE CONSTRUCTION PROJECT.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF JEFFERSON,
MISSOURI, AS FOLLOWS:
Section 1. The Mayor and Clerk are hereby authorized and
directed to execute a contract with B. D. Simon Construction Co.
for the temporary use of a portion of city streets during a state
construction project.
Section 2. The contract shall be substantially the same in
form and content as that contract attached hereto as Exhibit A.
Section 3. This Ordinance shall be in full force and effect
from and after the date of its passage and approval.
Passed --f 7 Approved 4- & — ,
Pre ding Officer yor
ATTEST:
City Clerk
HERCULES CONSTRUCTION CO.
® Y AT THE
HARRY S. TRUMAN STATE OFFICE BUILDING
CONSTRUCTION MANAGERS g r GENERAL CONTRACTORS
P.O. BOX 567 JEFFERSON CITY, MO 314-751-4819
400 S. BROADWAY 65102
February 22, 1984
To: Captain Dick Duncan,J.C. Police Department
Mr. Ray Bledsoe, J.C. Police Department
Chief Robert Rennick, J.C. Fire Department
Mr. Joe Duncan, J.C. Fire Department
Mr. Mike Bates, J.C. Public Works Department
Mr. Larry Bates, J.C. Public Works Department
Mr. Richard Harrison, Transportation Department
Mr. Tom Benton, J. C. Planning and Code Enforcement Department
Mr. Martin Brose, Transportation Department
Mr. Lynn Porterfield, City Counselor -<-
Mr. A.F. Bonderer, B.D. Simon Construction Company
® Re: Construction Fence/Barricades
Jefferson State Office Building
State of Missouri Project No. 01-307-02-0006
HCC Project No. 20024
Gentlemen:
This is to confirm our meeting of February 21 , 1984 at City Hall and of February 22,
1984, at the Jefferson Building, concerning the erection and location of the con-
struction fence in conjunction with the above project.
Per our conversations, we are agreed to the following:
A. The Contractor is to provide -
1 . Jefferson Street Side - Starting at the alley and proceeding continuously
north to Capitol Avenue, provide a four ft. high wire fence, four feet
back of the curb (allowing parking and access to the parking meters) .
A gated panel is to be provided opposite the front entrance for emergency
access to the building entrance.
2. Capitol Avenue Side - Starting at Jefferson Street and proceeding
approximately 58 ft. east, provide a four feet high fence, similar to
and as a continuation of that along Jefferson Street. Then, for the
next approximately 87 ft. east, provide a four feet wide covered walk-
way, of 2x4 and 40 wood construction with a plywood floor, roof, and
Sside adjacent to the construction site and a four feet high wire fence
on the street side (requested by the Police Department for visibility) .
The outside of this walkway will be provided approximately 20 feet out
in the street, allowing for a 14 feet construction staging area at the
Construction Fence/Barricades
® February 22, 1984
Page 2
curb. Then, for the remaining approximately 80 feet to the east
corner of the building, provide a four feet high wire fence, similar
to that along Jefferson Street. Note - the Contractor will keep clear
a path to the Fire Department pumper connections on the north side of
the building.
3. In Alley (South of Building) - For the limited period of time when the
Contractor is removing and replacing the exterior skin, he will provide
no more than a light duty chain or rope partition, so as not to limit
through-traffic in the event of an emergency.
4. Also, B.D. Simon Construction is to name the City of Jefferson, Missouri
as additional insured on the construction coverage.
B. The City of Jefferson is to provide -
l . Elimination of parking along both sides of Capitol Avenue in the
vicinity of the Jefferson Building, and
2. Provide re-striping of Capitol Avenue for two, 15 feet lanes of
traffic (one east bound and one west bound) . This work is to be done as
® soon as possible, so as to allow the contractor to construct his
walkway.
We have included sketches which we believe are in accordance with the above. If
anyone has any questions or comments, please respond immediately to this writer.
Very truly yours, ��----�
Stephen Kienstra
Project Manager
Hercules Construction Company
Jefferson State Office Building
Enclosure: Two Sketches
cc: Mr. Charles Brzuchalski
Mr. Earl Campbell
Paul Abbott
File
1��M1.IfA'��iwlr s� � �•
ems.
�'� 5�. �• OIti,� a�� No .
I .
o ,{
7EFFERS0N BLDG.
CiSTORY �
3
s�
s
i
v
i
F.D.
I
w
1
J la
'0
V
V
O I
W
C C
K®
K
co
® 4'-0 uyv, Wtn,Mc%6 F -
W r GmAinurs SwAW-6 Altus ---P
' - EK1ti in, Curb
JE i'F,E iPSOA/ STiPEf- T
ZoOZ
• + �, � �k t��-tip..
gl!O 10%� IJ=d
r
•
1. Z
� T
This Agreement is made this day of by
and between the City of Jefferson, Missouri (City) and B. 7D. •Simon
Construction Company (Company)
The Company is hereby authorized to use a portion of the streets
and sidewalks - on Capitol Avenue and Jefferson Street in
connection with its construction work on the state office
building referred to as the Jefferson Building. The portion
authorized to be used is specified in Exhibit 1 attached hereto.
Company will comply with all of the requirements contained in
Exhibit 1, including those shown on the map which is a part of
Exhibit 1. Company will further comply with the following
requirements :
1. Company will provide flagmen to control the movement of
equipment and vehicles in and out of the protected area.
2 . Company will properly place and maintain the necessary
signs and devices warning about the obstructions in the
street and on the sidewalks .
3 . The portion of Capitol Avenue authorized for temporary
use by Company shall be used solely for construction
access , and shall not be used for the storage of equip-
ment or materials .
4 . Damaged curbs, sidewalks and street pavement within the
authorized area shall be repaired to City standards
within 30 days of substantial completion of the project .
Any damage to curbs , sidewalks and street pavement
outside the authorized area shall be repaired to City
standards within 30 days after the damage occurs .
5. Due to the large number of pedestrians in the area for
4th of July celebrations, Company will take extra
precautions to assure that the obstructions are well-
marked and that the construction site is secure during
the period from midnight July 3d to midnight July 4th.
*
6 . Company will pay to the City a $ SG& $ELdly removal
cost for each parking meter required to be removed as a
result of the construction project, and will pay $ *
per week for each meter required to be removed and for
each meter whose use is eliminated because of the
rearrangement of the traffic lanes or any other cause
connected with the project .
7. Contractor shall clear all obstructions and defects from
the streets and sidewalks within 30 days of substantial
completion of the project . Contractor shall notify City
* Per conversation with Mike Bates April 14, 1984 cost to be :
I. Remove and reinstall meter heads $1.00 each.
a 2. Charge to be $. 50 per day per meter with Saturday, Sunday and holidays
excluded.
at least 7 days prior to removal of street obstructions
in order to allow the City to arrange the restriping of
the streets .
8. Contractor will not dispose of waste materials ,
® including but not limited to, plaster, cement, hardware,
and paint into the City's Sanitary or Surface Water
Sewer Systems.
City shall comply with the applicable provisions of Exhibit 1.
Upon Company's failure to comply with the requirements of this
agreement, City may terminate this agreement, remove any
obstructions from the streets and sidewalks , and if necessary,
make such repairs as are needed at Company's cost.
'City Clerk Mayor
ATTEST:
Secretary
•
CERTIFICATE OF INSURANCE
.r
Wausau Insurance Companies
This is to certify that the insurance policies (described below by o policy number)written on forms in use by the company have been issued.
Q is certificate is not a policy or a binder of insurance and does not in any way alter, amend or extend the coverage afforded by any policy
ferred to herein.
THIS CERTIFICATE REPLACES ONE ISSUED ON 2-22-84
Name and address of Insured
No.: 214 3
B .D . Simon Construction Co . Producer
Columbia , MO
P .O . Box 915
Columbia, MO 65201 Date Issued: 3-8-84
Region: CUM—SL(020) —KC
L�
Kind of Coverage t Expiration Date Policy Number Unless otherwise Indicated, this policy affords full coverage under the Workers'
Compensation laws of all states(except states where coverage can be provided only by
Workers' State Funds,and Canada)and as designated in the policy and endorsements for Coverage
Compensation* 3 7-1-84 0 714 00 044925 B--Employers'Liability.
Limits of Liability
Comprehensive 7-1-84 0724 0 2 044925 Bodily In(ury Property Damago
General Liability
$ 800 ,000 .
Each Occurrence $10 0 , 0 0 0 . Each Occurrence
Special Multi-Peril S coo 11 ❑ $ 800 ,000 , Aggregate $800 ,000 Aggregate
Trademark(Section II only)
Products-Completed Operations: ® Included ❑ Excluded Single Limit $ Each Occurrence
Contractual-All Written Contracts: lid Included ❑ Not Covered $ Aggregate
Owners', Landlords' $ Each Occurrence $ Each Occurrence
and Tenants'Liability $ Aggregate
Contractual Liability-- $ Each Occurrence $ Each Occurrence
noted Contracts
$ Aggregate
Single Limit $ Each Occurrence
$ Aggregate
Automobile Liability 111 7-1-84 0 7 2 4 09 044925 $10 0 ,0 0 0 . Per Person
AAAII Owned Autos XM Hired and Nonowned Autos $800 ,000 . Per Accident $ 10 0 , 0 0 0 Per Accident
❑ Specified Autos Only Single Limit $ Per Accident
$ Each Occurrence
Umbrella
Liability $ Aggregate Products-Completed Operations
$ Retention
Special Provisions/Locations/Specified Autos:
City of Jefferson, Jefferson City, MO is Additional Insured under policy
#0724 02 044925 with respect to the following job :
Renovation of the Jefferson State Office Building , Jefferson St . and
Capitol Dr . , Jefferson City , Missouri .
Not withstanding any requirement, term or condition of any contract or other document with respect to which this certificate may be issued or may pertain, the insurance afford-
ed by the policy(policies)described above is subject to all of the terms, exclusions and conditions of such policy(policies)during the terms)thereof.
tThe entry of a number in this column means that the coverage is afforded by the company designated by the same number.
Issued to: Issued by (1.) EMPLOYERS INSURANCE OF WAUSAU A Mutual Company
• (2.) ILLINOIS EMPLOYERS INSURANCE OF WAUSAU
® City of Jefferson (1) WAUSAU UNDERWRITERS INSURANCE COMPANY
320 E . McCarty (4.) WORLDWIDE UNDERWRITERS INSURANCE COMPANY
Jefferson City, MO 65101
• Signed �/ 1 • �1 - ��� ��I1.GL/12
Authorized Company Repr senlotive
8-87 (5)15.5796
tG+cP , 10119
CERTIFICATE OF INSURANCE
Wausau Insurance Companies
.r. O
This is to certify that the insurance policies (described below by a policy number)written on forms in use by the company have been issued.
This certificate is not a policy or a binder of insurance and does not in any way alter, amend or extend the coverage afforded by any policy
(erred to herein.
Name and address of Insured
B. D. Simon Construction Co.
Producer No.: 2143
P.O. Box 915 Place: Kansas City, MO 64141
Columbia, MO 65201 Date Issued: 5 21 84
Region: CUM,SL(020),KC
Kind of Coverage co* Expiration Date Policy Number *+ Unless otherwise indicated, this policy affords full coverage under the Workers
"o Compensation laws of all states(except slates where coverage can be provided�only vbVy
Workers Slate Funds,and Canada)and as designated in the policy and endorsements forKzYYYtA
Compensation*+ 3 7 1 85 0715 00 044925 Employers Liability.
Limits of Liability
Comprehensive 2 ] 1 85 0725 02 044925 Bodily Injury Property Damage
General Liability
$ 800,000 Each Occurrence $ 100,000 Each Occurrence
Special Multi-Peril or
Trademark(Section II only) E 800,000 Aggregate $ 800,000 Aggregate
Products-Completed Operations: L Included ❑ Excluded Single Limit $ Each Occurrence
Contractual-All Written Contracts: Included ❑ Not Covered $ Aggregate
Owners', Landlords' $ Each Occurrence $ Each Occurrence
and Tenants'Liability $ Aggregate
Contractual Liability -- $ Each Occurrence $ Each Occurrence
Designated Contracts
$ Aggregate
Single Limit $ Each Occurrence
16 $ Aggregate
Automobile Liability 1 21 7 1 85 1 0725 09 044925 s 100,000 Per Person
All Owned Autos ( Hired and Nonowned Autos $ 800,000 Per Accident $ 100,000 Per Accident
❑ Specified Autos Only Single Limit $ Per Accident
$ Each Occurrence
Umbrella $ Aggregate Products-Completed Operations
Liability
$ Retention
Special Provisions/Locations/Specified Autos:
City of Jefferson, Jefferson City, MO is Additional Insured under policy ;✓0725 02 044925
with respect to the following job:
Renovation of the Jefferson State Office Building, Jefferson St. and Capitol Dr.,
Jefferson City, Missouri
Not withstanding any requirement, term or condition of any contract or other document with respect to which this certificate may be Issued or may pertain, the insurance afford•
ed by the policy(policies)described above is subject to all of the forms,exclusions and conditions of such policy(policies)during the terms)thereof.
*The entry of a number In this column means that the coverage Is afforded by the company designated by the some number.
Issued to: *Issued by 2. EMPLOYERS INSURANCE OF WAUSAU A Mutual Company
3. WAUSAU UNDERWRITERS INSURANCE COMPANY
City of Jefferson 5. WORLDWIDE UNDERWRITERS INSURANCE COMPANY
e 320 E. McCarty 7. ILLINOIS EMPLOYERS INSURANCE OF WAUSAU
Jefferson City, MO 65101 1. WAUSAU LLOYDS _J2
t �"r�x
• Signed `
Authowed Company Repr ntalrre
4,8, IS)155736