HomeMy Public PortalAboutORD10370 BILL NO. 14
�a
,SPONSORED BY COUNCILMAN
ORDINANCE NO. /03 -7 O
AN ORDINANCE OF THE CITY OF JEFFERSON, MISSOURI, AUTHORIZING THE
MAYOR AND CITY CLERK TO EXECUTE A CONTRACT WITH TWEHOUS
EXCAVATING CO. , INC. , FOR SITE DEVELOPMENT OF THE RAILTON
INDUSTRIAL PARK - HOOVER UNIVERSAL SITE.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF JEFFERSON,
MISSOURI, AS FOLLOWS:
SECTION 1. The Mayor and Clerk are hereby authorized and
directed to execute a contract with Twehous Excavating Co. , Inc. ,
for site development of the Railton Industrial Park - Hoover
Universal Site for the sum of $774, 562 .50.
SECTION 2. The contract shall be substantially the same in
form and content as that contract attached hereto as Exhibit A.
SECTION 3. This Ordinance shall be in full force and effect
from and after the date of its passage and approval.
Passed: Approved:
si.d' g Of'fic r y r
ATTEST:
.Lcy9 �is�c��
ity perk
CONTRACT FOR PUBLIC WORK
This Contract is made �.ind entered into this 1 S day of
1985, by and between the City of Jefferson,
Missouri (City) , and Twehous Excavating Co. , Inc. (Contractor) .
WHEREAS, the Council of the City of Jefferson,
Missouri, did on the day of 1985, award
to the Contractor the bid of the sate developm t of the Railton
Industrial Park - Hoover Universal Site.
NOW, THEREFORE, for and in consideration of the awarding of
this Contract and the work thereunder by City to the Contractor,
the Contractor does hereby contract and agree to do and perform
said work, above specified and referred to, for the following
prices:
Seven Hundred Seventy-four Thousand, Five Hundred Sixty-two
Dollars and Fifty Cents ( $774 , 562 .50 )
The approximate quantities, unit prices and total amounts
are as shown in the Itemized Proposal attached hereto as Exhibit
"A" . Upon completion of the work, readjustments in the Contract
price shall be made according to actual measurements and at the
price per unit specified in the Contract.
It is agreed and understood by the parties hereto, that this
Contract is entered into subject to all existing ordinances of
the City pertaining to the work awarded and subject to the plans
and specifications and estimates of the costs for work on file in
the office of the City Clerk, and which shall be considered a
part of this Contract; that all questions arising as to the
proper performance of this Contract of such work in accordance
with the plans and specifications therefor, and estimates
thereof, shall be decided by the Director of Public Works of the
City of Jefferson, Missouri, or by such competent person
appointed by the Mayor and the City Council of the City of
Jefferson to supervise and superintend said work in the place of
and instead of such Director of Public Works; that in the case of
improper construction, the City reserves the right at any time to
suspend, relet or order an entire reconstruction of the work;
that Contractor agrees to commence work on or before a date to be
specified in a written "Notice to Proceed" and to fully complete
the project as per project specifications . The City reserves the
right at any time to suspend, relet or order an entire
reconstruction of the work awarded and to declare the contract
forfeited, but Such suspension, reletting or reconstruction or
forfeiture shall not affect the right of the City to recover all
damages and penalties accruing or due it by reason of the
Contractor's noncompliance with this Contract. Liquidated
damages of Five Hundred Dollars ( $500 ) per calendar day will be
assessed against the Contractor for each day the work remains
incomplete following the completion date or extension thereof.
-2-
The Contractor agrees to pay all classes and crafts of labor
used in the performance of this Contract the prevailing hourly
rate of wages as determined by the Department of Labor and
Industrial Relations and Contractor acknowledges that he knows
the prevailing hourly rate of wages for all the classes and
crafts of labor to be used in the performance of this Contract
because he has obtained the prevailing hourly rate of wages from
the contents of Special Wage Determination No. 5-026-077 and
Decision No. MO84-4061, in which the rate of wages are set forth.
The Contractor further agrees that he will keep an accurate
record showing the names and occupation of all workmen employed
by them in connection with the work to be performed under the
terms of this Contract. Record shall show the actual wages paid
to said workmen in connection with the work to be performed under
the terms of this Contract. Contractor further agrees that the
aforementioned accurate record shall be available and open at all
reasonable hours for the inspection by the Director of Public
Works or any other authorized employee of the City. In
compliance with the Prevailing Wage Law, as amended in Sections
290. 210 to 290. 340 inclusive, RSMo 1969, effective October 13,
1.969, not less than the prevailing hourly rate of wages in the
vp Jefferson City area shall be paid to all workmen performing work
under this Contract, Section 290.250. The Contractor shall
forfeit to the City, Ten Dollars ($10) for each workman employed,
for, each calendar day, or portion thereof, such workman is paid
Less the stipulated rates for any work done under said Contract,
by him or any subcontractor under him, Section 290 .250.
Contractor agrees to completely indemnify and hold harmless
the City for any and all damages , injuries, actions, costs ,
attorney's fees and all other expenses whatsoever, arising out of
the performance of said work whether the property or persons
damaged are the servants and employees of the Contractor or third
parties, in no manner connected with said work. All
interlinea.tions, corrections, deletions and changes herein have
been prior to the execution of this Contract.
Contractor shall procure and maintain during the life of
this Contract:
a. Workman's Compensation Insurance for all of its
employees to be engaged in work under this Contract .
b. Contractor' s Public Liability Insurance in an amount
not less than Eight Hundred Thousand Dollars ( $800, 000 )
for all claims arising out of a single occurrence and
One Hundred Thousand Dollars ( $100, 000 ) for any one
person in a single accident or occurrence, except for
those claims governed by the provisions of the Missouri
-3-
Workman's Compensation Law, Chapter 287 , RSMo, and
Contractor's Property Damage Insurance in an amount not
less than Eight Hundred Thousand Dollars ( $800, 000 ) for
all claims arising out of a single occurrence and One
Hundred Thousand Dollars ( $100, 000) for any one person
in a single accident or occurrence.
C. Automobile Liability Insurance in an amount riot less
than Eight Hundred Thousand Dollars ($800, 000 ) for all
claims arising out of a single occurrence and One
Hundred Thousand Dollars ( $100, 000) for any one person
in a single accident or occurrence.
d. City Listed as Additional Insured: The City shall be
listed as an "Additional Insured" on the Contractor's
public liability insurance and automobile liability
insurance policies .
e. The Certifications of Insurance furnished to the City
showing proof of compliance with these insurance
requirements shall contain a provision that coverage
under such policies shall not be cancelled or
materially changed until at least ten ( 10 ) days prior
written notice has been given to the City.
IN WITNESS WHEREO� the parties have hereunto set their
viands and seals this �_ day of _�� 1985 .
CITY OF JEFFERSON, MISSOURI
Attest:
By:
14ayor
City Clerk
Attest,:
By:
.�� Contractor
mom
.a
N
17co
ITY OF IEFFEJIN,.R
MAYOR: George Hartsfield
February 28, 1985
TO: Mayor and Members o ty Council
FROM: Thomas H. Benton, irector, Planning & Code Enforcement
SUBJECT: Bill #84-218
This Bill authorizes the City to enter into contract with
Twehous Excavating Co. for a total amount of $774 , 562. 50 .
Fund sources are broken down as follows :
CDBG $440, 126.00
Hoover Universal 164 , 061.25
Railton Trust 47, 135.25
Union Pacific Railroad 5,422.50
Utility Companies 28, 080.00
City - General Revenue 89, 737.50
The City of Jefferson has already acquired the property
necessary to honor our committment at a cost of $91, 710.00.
Please refer to attached letters of committment from those
entities involved in this project.
Thank you for your consideration. Mike Bates, Larry
Brickey, Chairman of the Chamber- of Commerce, and myself will be
in attendance to answer any questions you may have regarding this
Bill and contract.
John G. Christy Municipal Building 320 L McCarty St. Jerson City,Mlssouri 65101
314 634-6300 direct Dial 634- 6 40 9
February 28, 1985
HOOVER UNIVERSAL, INC.
P.O. Box 113
135 East Bennett Street
Saline, Michigan 48176
Mayor George Hartsfield and
Members of the City Council
320 East McCarty Street
Jefferson City, Missouri 65101
Dear Sirs:
It is our understanding that a Community Development Block Grant in the
amount of $440,126.00 has been granted to the City for the development
of the Railton Industrial Site.
It is also our understanding that the total scope of this development
exceeds the total amount covered by the Grant and that participation
by the City, Railton Trust, Union Pacific Railroad, local utilities
and Hoover Universal will be required. Therefore, Hoover Universal
will participate in this project, and will provide funds as liability
is incurred by us.
Sincerely,
H 0 ER UNIVE AL, INC.
A a C. u
mb b ,.-
Project Manager
ACM/m j c
tape ��
C*
phr r�, 8 I
�xa
s,; �dt UOS:ia p
a
ap� aoa� 3a o
�tlo.5' �s�°a
N
OAr r
44 (Zoe uc'i
Lr
a
s��a
� 0
r 14
ae $4 o -H
.o rn w > 3 �v w
N ( "� 4) 1 u ug�i cGU H
1N1 � bM.1N U �
E H i-1 o 49 1-4 W W
0 y,C41 to U 41 u1 m U 1.4
4b � H Cd bbo HW N q aE1HW . .
"ziz.+ .,.1 wO CJH z P4
0 (U �y b0
ASH G4 -4 b -H O41 OUEfl1
Ww �"� w 41 a � aN W >4
W � "i C7 2 fx
� � aC � cow�9 A �0 14
E-1 o 0. Q y
C!
o C) o �� �" d -H V E-1 U E A
.0 41
U 01 N A A ri N Ml sr 1 %o r1- col 1 0 r-I H r-1
01111,111 F-4
o'
« s
r �
Aft
FE' 0
f=IEw Ff I
ITY 0 N
WYOR:George Hartsfleld
February 28, 1985
Tel: Mayor and Members WV
FROM: Council
FROM: Thomas H. Benton;°bfrector, Planning & Code Enforcement
SUBJECT: Bill #84-218
This Ball authorizes the City to enter into contract with
Twehous Excavating Co. for a total amount of $774 , 562 .50.
Fund sources are broken down as follows:
CDBG $440, 126.00
Hoover Universal 164 , 061.25
Railton Trust 47, 135. 25
Union Pacific Railroad 5422. 50
Utility Companies 28, 080.00
City - General Revenue 89, 737.50
The City of Jefferson has already acquired the property
necessary to honor our committment at a cost of $91, 110.00.
Please refer to attached letters of committ ent from those
entities involved in this project.
Thank you for your consideration. Mike Bates, harry
Brickey, Chairman of the Chamber of Commerce, and myself will be
in attendance to answer any questions you may have regarding this
Bill and contract.
John G. Christy Municipal Building 320 E McCarty St. Jefferson City,Missouri 65101 ;
314 634-6300 Direct Dial 634 6 40 9
.... ..._ . .. . _.. .. .._ .. ._ .._.._..�._..__...� .� - _..,.tee. ,.
� oy
M
tl
4
r
1 2 E F F E,
fl ;4iii�iis'isl4s�t. ;t,iss'�Y.>".:.U2:��bbb:,!{.,...,..".i::,n.iC.:... '��s.`:t..a8f�rc>7�.;.uw�.'..1.¢�.�1'S[1R1• ...l.v.....�a..:i13S'eu::bX�T�yw7.�..dSt`4....;la«4c';,«:cia+.-:bS.;:.+Atx 'ii�
MAYOR: George Hartsi3eld
February 28 , 1985
TO: Mayor, City Council and City Administrator
FROM: Robert M. Bates, P.E. ey
Director of Public Works
RE: West Main Street Construction
6
Bids have been received for the lowering of West Main Street as a
part of the Hoover project. The following summarizes the street
costs only.
$ 89, 737. 50 Base Bid
4,486.87 5% Contingencies
6, 500. 00 50% Water Line Lowering
$100, 724. 37 Total Project Cost
_27, 500. 00 MHTD Participation
$ 73, 224.37 Net Cost to City
cc: Toni Benton
Bob Cox
Jim Hartley
Marc Thornsberry
don
s
John G. Christy Municipal Building 320 L McCarty St. Jefferson City,Missouri 65101
314 634-6300 Direct Dial 634-
February 28, 1985
HOOVER UNIVERSAL, INC.
P.O. Box 113
135 East Bennett Street
Saline, Michigan 48176
Mayor George Hartsfield and
Members of the City Council
320 East McCarty Street
Jefferson City, Missouri 65101
Dear Sirs:
It is our understanding that a Community Development Block Grant in the
amount of $440,126.00 has been granted to the City for the development
of the Railton Industrial Site.
It to also our understanding that the total scope of this development
exceeds the total amount covered by the Grant and that participation
by the City, Railton Trust, Union Pacific Railroad, local utilities
and Hoover Universal will be required. Therefore, Hoover Universal
will participate in this project, and will provide funds as liability
io incurred by us.
Sincerely,
H OVER UNIVE AL, INC.
a C. umb
Project Manager
ACM/mjc