HomeMy Public PortalAboutORD10374 1
BILL NO.
SPONSORED BY COUNCILMAN ,
ORDINANCE NO.
AN ORDINANCE OF THE CITY OF JEFFERSON, MISSOURI, AUTHORIZING THE
MAYOR AND CITY CLERK TO EXECUTE AN AGREEMENT WITH DULLE OVERHEAD
DOOR COMPANY, FOR GARAGE DOOR REPLACEMENTS AT THE STORAGE BUILDING,
831 EAST MILLER STREET.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF JEFFERSON,
MISSOURI, 'AS FOLLOWS:
Section 1. The Mayor and Clerk are hereby authorized and
directed Co execute a contract with Dulle Overhead Door Company, for
garage door replacements at the storage building, 831 East Miller
Street forza sum of $6,930.00.
Section 2. The Contract shall be substantially the same in
form and content as that contract attached hereto as Exhibit A.
Section`! 3. This Ordinance shall.be in full force and effect
from and after the date of its passage and approval.
PASSED APPROVED
'RRESIDING..0 I 'ICER MAYOR
ATTEST:
CITY CLERK
i
r •
Alh CONTRACT FOR REPLACEMENT
GARAGE DOORS, 831 E. MILLER
CITY OF JEFFERSON, MISSOURI
This contract is entered into this !� day of
19 , by and between the City of Jefferson, Missouri, hereinafter
called the City, and DULLE OVERHEAD DOOR COMPANY ,
hereinafter called the Contractor.
WHEREAS the City Council f the City of Jefferson, Missouri,
did on the I day of 19EE, award to the Contractor
the contract for replacement of garage doors, 831 E. Miller Street.
NOV; THEREFORE, for and in consideration of the awarding of
this contract and the work thereunder by the City to the contractor,
the said work, _above._specif ied.and referred to and to accept payment
therefore in the following manner:
Six Thousand Nine Hundred Thirty Dollarsv()
LUMP SUM and No Cents ( )
NOW, BY THESE PRESENTS, it is agreed and understood by the
parties hereto, and this contract is entered into subject to all
existing ordinances, plans and specifications for such work on file
in the office of the City Clerk, and which shall be considered a
part and parcel of this contract; that all questions arising as
to the proper performance of this contract of such work in accord-
ance with the plans and specif ications therefore, and estimates
thereof, shall be decided by the Director of Planning. and Code
Enforcement, of the City of Jefferson, Missouri, or by such compe-
tent persons appointed by the Mayor and the City Council of the City
of Jefferson to supervise and superintend said work in the place
of and instead of such Director of Planning and Code Enforcement;
that in the case of improper workmanship, the City of Jefferson
reserves the right at any time to suspend, re-let, or order an
entire reconstruction of the work; that the Contractor agrees to
commence work on or before a date to be specified in a written -
"Notice to Proceed" and to fully complete the project work covered
by the Contract within ninety (90) consecutive calendar days after
the date extablished in the Notice to Proceed. The City reserves
the right at any time to suspend, re-let or order an entire recon-
struction of the work awarded and to declare the contract forfeited;
but that such suspension, re-letting or reconstruction or forfeiture
shall. not affect the right of theCity to recover all damages and
penalties occurring or due it by reason of the Contractor's non-
compliance with this contract. Liquidated damages of one hundred
($100.00) dollars per day will be assessed against the Contractor
for each day the work covered by the Contract remains incomplete
following the completion date or extension thereof.
The Contractor agrees to pay all classes and crafts of labor
used in the performance of this contract the prevailing hourly rate
of wages as determined by the Department of Labor and Industrial
Relations and Second Party acknowledges that he knows the prevailing
hourly rate of wages for all classes and crafts of labor to be used
in the performance of this contract because he has obtained the
prevailing hourly rate of wages from the contents of Special Wage
Determination No.- S-026-061 , in which the rate of wages are set
forth.
The Contractor further agrees that he will keep an accurate
record showing the names and occupation of all workmen employed by
them in connection with the work to be performed under the terms of
this contract, which record shall show the actual wages paid to each
of said workmen in-connection with the work to be performed under the
terms of this contract, and agrees further that the aforementioned
accurate record shall be available and open at all reasonable hours
for the•inspectiou by the Director of Planning and Code Enforcement
or any other authorized employee of the City of Jefferson, Missouri.
In compliance with the Prevailing Wage Law, as amended in Section
290.210 and 290.•340 inclusive, Revised Statutes of- Missouri, 1969; --•- ..
effective October 13, 1969, not less than the prevailing hourly rate
of wages in the Jefferson City area shall be paid to all workmen
under this contract, Section 290.250. The Contractor shall forfeit
to the City ten ($10.00) dollars for each workman, employee, for
each calendar day, or portion thereof, such workman is paid less
than the stipulated rates for any work done under this contract, by
him or by subcontractors under him, Section 290.250.
The Contractor agrees to completely indemnify and hold harmless
the City for any and all damages',' injuries, actions, costs, attorneys
fees and all other expenses whatsoever arising out of the performance
of said work whether the property or persons damaged are'tbe servants
and employees of the Contractor or third parties in no runner connected
with said work. All interlineations, corrections, deletions and
changes herein have been made prior to the execution of this contract.
IN WITNESS WHEREOF, the parties have hereunto set their hands
and seals. this day of / Cif. ... , 1985.
CITY OF JEFFERSON, MISSOURI
-ATTEST: BY
C ty Clerk MAyor
ATTEST: AW64 BY � CIA&
CONTRACTOR
This contract, executed in duplicate, one copy being deposited in the
office of the City Clerk of the City of Jefferson, and the other be-
ing retained by the Contractor.