MEETING MINUTES of the
NAUSET HIGH SCHOOL BUILDING COMMITTEE
MEETING DATE and TIME:
Wednesday,March 8,2023 -5:30pm
Remote Meeting Via Nauset School District Zoom
This meeting took place remotely pursuant to the law signed by Governor Baker on June 16, 2021 —
An Act Extending Certain COVID-19 Measures Adopted During the State of Emergency,
which includes an extension,until March 31,2023,of the remote meeting provisions of his March 12,2020 Executive
Order Suspending Certain Provisions of the Open Meeting Law.
MEMBER ATTENDANCE: Greg Levasseur,Chris Easley, Bob Capurso, Patrick Clark,Jody Craven,Tom Fizgibbons,
Griffin Ryder, Brooke Clenchy,Ron Collins,James Nowack, Lisa Orlandella,Kathleen Tringale,Giovanna Venditti and
Tom Faris
NON-MEMBER ATTENDANCE: The NRHS SBC Professional Team: Alyssa Chatani,Amanda Sawyer,Jorge Cruz,
Joe Sullivan and Peter Gaudreau
Call to Order/Agenda Chances
Chair Levasseur called the meeting to order at 5:32 pm,declared a quorum present and read the meeting participation and
recording statements.
Citizens Sneak: None
PRIORITY BUSINESS
A. Project Update CHA/Daedalus Update
Ms. Sawyer explained that the groundbreaking of the new building project needs to be scheduled. The MSBA is
allowing the District to pick a date. The suggestion is in May and create a subcommittee to head that up.
Also Ms. Sawyer reported that in regard to the builders' risk insurance,they have received bids back but were
very high, so Brait Builders has been asked to give some numbers and she should have an update of that
information at the next meeting.
B. Fiansburgh_Update
Mr. Cruz reported that they have been processing shop drawings and getting ready for construction. Demolition
on E Building is scheduled to happen next Monday and then move on to G Building. Many of the trees have been
cut down to be ready for construction. Topsoil has been removed and work on geotechnical test pits is being
done,so that excavation for the foundations can begin.
C. Review of Chanee Orders
Chair Levasseur reported that the Change Order Group met yesterday and is still reviewing the extra work for the
modulars. The cost is less than$96K at this time and continues to be updated. There is a small problem with the
drainage underneath the modulars that will result in a change order that will be wrapped up into a larger change
order request. (That will be fixed during school vacation). The subcommittee meets as needed and so far,there
has been a significant need to meet frequently, which ultimately is good for the overall project budget.
Nauset High School Building Committee March 8,2023 11 Page
D. Campus Team Proiect Progress
Mr.Clark reported that this has been the smoothest shift he has ever witnessed! The classrooms have settled right
in and everything is running smoothly. Everybody has pitched in to make it work!
Ms. Tringale noted the CHA gave a huge amount of support to the move and oversight of the movers. The
Technology Department got all the smart boards up and running the first day and the kitchen staff worked the
entire vacation week to make sure they were set up and ready to go. Much of the staff also came in during
vacation to get their classrooms ready. It went very well.
Mr. Faris said the impact on the students was minimal. Everything was ready to go Monday morning!
Mr. Capurso shared pictures of the modulars being used with students back in session,the beginning of the
construction and also many areas that have been converted into new space such as the auditorium stage that is
now the wellness center and the library that is now the cafeteria.
Superintendent Clenchy praised all for an excellent job in the move that was relatively seamless. She is very
happy to hear that the students love the modulars!
APPROVAL OF MINUTES
MOTION: It was moved b% Mr. Levasseur and seconded by Mr.Easley to approve the minutes of February 3,
2023. Ms.Venditti abstained from the vote: all others voted in favor via roll call vote.
MOTION: It was moved by Mr. Levasseur seconded bN• Mr.Fitzgibbons and voted unanimously via roll call vote
to approve the minutes of February 8,2023.
MOTION: It was moved by Mr. Levasseur,seconded by Mr.Easle}' and voted unanimously via roll call vote to
aporove the minutes of February 15 2023.
PAYMENT OF BILLS
MOTION: It was moved by Mr. Nowack seconded by Mr.Fitzgibbons and voted unanimousl •via roll call vote to
approve for paF ment the following bills of Warrant A-2448 in the amount of$644,811.98.
Amazon $ 440.19
Cape& Islands Shredding Services $ 276.00
Cape Cod Trailer Storage $ 315.00
Coastal Equipment Rentals $ 932.70
Daedalus Projects, Inc. $ 60,000.00
Five College Movers LLC $ 43,690.00
Flansburgh Associates $158,735.78
J&J Contractors,Inc. $376,564.12
M.A. Frazier,Inc. $ 549.45
Mid-City Scrap Iron &Salvage Co. $ 104.55
Mid-Cape Home Centers $ 356.19
Murphy,Lamere&Murphy $ 1,533.00
Paul Richard $ 715.00
Visual Edge It $ 600.00
Total: $644,811.98
Nauset High School Building Committee March 8,2023 2 Page
�4
MOTION: It was moved by Mr.Nowack,seconded by Mr.Fitxeibbons and voted unanimously via roll call vote to
approve for navment of the followine bills of Warrant A-2449 in the amount of$1,244,567.70.
Brait Builders $1,244,567.70
Total: $1,244,567.70
Mr. Easley requested an accounting of what has been spent thus far on the project. Ms. Sawyer indicated she is working
with MSBA on the budget and will have an update soon.
Chair Levasseur noted the next meeting is April 12,2023.
ADJOURNMENT:
MOTION: It was moved b • Mr. Easley,seconded b` Ms.Clench and voted unanimously to ad'ourn at 5:57PM.
Respectfully Submitted,
Amanda Lapierre
Recording Secretary
Gregory Levasseur Building Committee Chair
PRINT NAMErFITLE
C71-eaOl'y Le vd 2-w- Jul 11,2023
Gregorq Levas eur{J,111 L 202315:49 EDT;
SIGNATUREIDATE
Nauset High School Building Committee March 8,2023 3 1 Page