HomeMy Public PortalAboutNauset School Building Committee -- 2022-09-28 Minutes Tin- Nauset Regional High School Building Committee Meeting Minutes Wednesday, September 28, 2022 Virtual Meeting 5:30 PM I Call to Order/Agenda Changes/Recording Notification Chair Greg Levasseur called the meeting to order at 5:30 pm and read the recording notification. MEMBER ATTENDANCE: Chris Easley, Tom Faris, Harry Terkanian, Giovanna Venditti, Lisa Orlandella, Peter Wade, Kathleen Tringale, Griffin Ryder,Jody Craven, Patrick Clark,Jackie Beebe, Brooke Clenchy, Bob Capurso NON-MEMBER ATTENDANCE: Jorge Cruz, Alyssa Chatani.,Amanda Sawyer, Brian Hores,Joe Sullivan, Kent Kovacs 11 Introduce New SBC Member Chair Greg Levasseur welcomed new building committee member Bob Capurso. Bob.introduced himself to the committee, he is Nauset School District's new Facility Manager and brings years of experience with him. Bob is replacing committee member Tony Nannini. III Citizens Speak None III Priority Business A. Daedalus/CHA Review of Filed sub bids Alyssa Chatani reviewed the filed sub bids. The project was rebid and file sub bids were due on September 14th. Overall, filed sub bid was a total of$66million.The HVAC Bid was over budgeted and the Attorney General has been reached out to for advice as only one bid for HVAC was submitted. Review of GC bid timeline The overall General Contractor bids are due on October 19th. Low bidder GVW withdrew their bid, leaving only one bidder left with the metal windows. We will have a better understanding of the overall project budget after the submission deadline for general contractor bids on October 19, 2022. Committee member Chris Easley shared his concerns with the budget estimate numbers being close to $20 million dollars over budget and the frustration with the timeline of communication with our OPM. Amanda Sawyer mentioned a redesign or pausing the project and rebidding later as potential options available to us to address the 40% budget overages. Some issues cited for the over budget include the distance to the Cape, still a shortage of qualified workers without much competition, supply chain issues, and pricing from vendors on a three year project. B. Review Prolect Status Discussion between many committee members, Daedalus/CHA and Flansburgh ensued. Some other projects have seen a cost increase over 40%on certain subcontractors. We have sold a concept of what it is going to cost to build a school with the vision of what Nauset education is. The vision we sold is not one we can afford with the budget we have.The balance will be challenging. We need to determine how to be financially responsible to minimize the cost associated with our project without compromising the educational program. Nine out of twelve school projects that Daedalus/CHA is trending came in within budget. The location of our project is not in our favor. C. Report from on campus team Kathleen Trinp—ale and Tom Faris Kathleen shared that she and Tom Faris have had the opportunity for a walk through to tour and view the modulars.They are working on version 10 of populating the modulars based on classrooms,scheduling conflicts, and office spaces. We are continuing to inventory Buildings D & N and storage rooms in anticipation of a move. Work is being done with the architect to refine the locker room layout. Tom Faris shared a layout of the modulars and updated the committee with changes that allowed larger classrooms, installation of stairwells, and an additional second ramp location all with no change order. Chair Greg Levasseur is hoping the committee will have the availability to walk through the modulars soon. D. Items not reasonably anticipated by the Chair Time was allotted for discussion.Topics included building committee email invites for all town administrators, poor communication with the public about the project status, and the lack of maintenance and upkeep regarding the building committee website. Invitations for the public to tour the modulars could happen as soon as late October or early November. IV Payment of Bills Giovanna Venditti motioned to pay the following bills from warrant A-2289 for a total amount of $299,437.48- Cape Cod Trailer Storage Inc.for$1,650.00, Daedalus Projects, Inc. for$50,000.00, Flansburgh Associates, Inc. for$210,900.00, Gatehouse Media for$912.56,JP Fine Tuning for $1,250.00, M.A.Frazier, Inc.for$1,243.92, Murphy, Lamere & Murphy for$22,386.00, Robert B Our for$10,845.00, and Visual Edge It for$250.00. Chris Easley seconds the motion. By a roll call vote,the committee votes unanimously. V Approval of Minutes of September 15, 2022 Greg Levasseur makes a motion to approve the minutes of September 15, 2022. Peter Wade seconds the motion.The committee votes unanimously by roll call. VI ADJOURNMENT Greg Levasseur motions to adjourn the meeting. Griffin Ryder seconds the motion. By a show of hands, the committee votes unanimously. Meeting adjourned at 6:30pm. Minutes submitted by Wendy Spampinato L�afa)u Print name Title Signatu� Date