HomeMy Public PortalAboutAB 21-064 Brown Park and E. Lake Street Shorleline Project Update
McCALL CITY COUNCIL 216 East Park Street
AGENDA BILL McCall, Idaho 83638
Number AB 21-064
Meeting Date February 26, 2021
AGENDA ITEM INFORMATION
SUBJECT:
Project Update – Brown Park and E. Lake Street Shoreline Repairs and Improvements.
Department Approvals
Initials
Originator
or
Supporter
Mayor / Council
City Manager
Clerk
Treasurer
Community Development
Police Department
Public Works
Golf Course
COST IMPACT:
Estimated Total Project Cost: 1.7 Million
Parks and Recreation
/
Originator
FUNDING SOURCE:
McCall Redevelopment Agency, Local Option Tax, Land & Water Conservation Funds
Airport
Library
TIMELINE:
FY21
Information Systems
Grant Coordinator
SUMMARY STATEMENT:
The goal of this work session is to give City Council an update and discuss the status of the construction and design work within Brown Park and along the shoreline adjacnet to E. Lake
Street North of the Marina. City staff has continued to work with the McCall Redevelopment Agency (MRA) to address overdue repairs and make needed improvements to the public shoreline
and facilities, while MRA funds are still available.
In conjunction with current contract awards, engineering and design task orders, and the public art proposal, it is estimated that MRA will have approximatly $800,000 to allocate towards
projects during the upcomming construction season. In addition to that amount, the Parks Department has approximatly $230,000 budgeted for playground replacement and renovations through
LWCF and LOT funds. Staff is working with both the design team and MRA to identify and prioritize bid items based on available budget and logical construciton sequencing to best address
facility maintenance and improvement priorities. Contstruction documents and the project bid manual are at 85% complete. Project(s) are scheduled to go out to bid on April 01.
Attachments: Brown Park and Lake Street Site Plans
RECOMMENDED ACTION:
Review and discuss project priorities, sequencing, scopes of work, funding sources, and long-term goals and objectives.
RECORD OF COUNCIL ACTION
MEETING DATE
ACTION
February 23, 2018
AB 18-050 A Proposed Waterfront Plan North of the Marina
April 23, 2020
AB 20-122 Request for Approval of the Planning, Design, and Engineering Agreement for the Lake Front Improvement Project