HomeMy Public PortalAboutResolution No. 081-97 09-23-1997 RESOLUTION NO. 81-97
• STATEMENT EXPRESSING
OFFICIAL INTENT TO REIMBURSE
COSTS OF THE SEWER SYSTEM PROJECT
WHEREAS, the City of Richland Hills, Texas (the "Issuer") is a municipal corporation
organized and existing under the laws of the State of Texas;
WHEREAS, the Issuer expects to pay expenditures in connection with the design, planning,
acquisition and construction of the project described on Exhibit "A" hereto (the "Project") prior to
the issuance of obligations to finance the Project;
WHEREAS, the Issuer finds, considers, and declares that the reimbursement of the Issuer
for the payment of such expenditures will be appropriate and consistent with the lawful objectives
of the Issuer and, as such, chooses to declare its intention, in accordance with the provisions of
Section 1.150-2 of the Treasury Regulations, to reimburse itself for such payments at such time as
it issues obligations to finance the Project;
THEREFORE, BE IT RESOLVED BY THEY CITY COUNCIL OF THE CITY OF
RICHLAND HILLS, TEXAS, THAT:
Section 1. The Issuer reasonably expects to incur debt, as one or more series of obligations,
with an aggregate maximum principal amount not to exceed, $4,000,000 for the purpose of paying
• the costs of the Project.
Section 2. All costs to be reimbursed pursuant hereto will be capital expenditures. No tax-
exempt obligations will be issued by the Issuer in furtherance of this Statement after a date which
is later than 18 months after the later of (1) the date the expenditures are paid or (2) the date on
which the property, with respect to which such expenditures were made, is placed in service.
Section 3. The foregoing notwithstanding, no tax-exempt obligation will be issued pursuant
to this Statement more than three years after the date any expenditure which is to be reimbursed is
paid.
Date: September 23, 1997
c~''
y. ~ rr+ . Authorized Representative
: ~ ~ C. F. Kelley, Mayor
~ a~
~
e
~
•
. Exhibit "A"
In February, 1996, the City of Richland Hills was placed under an administrative
order from the Environmental Protection Agency. The City's wastewater system
does not meet EPA requirements. Defects in the systems were identified in a
report from a consulting engineer study. This report was submitted to EPA.
The scope of work to be accomplished under this administrative order includes
the following:
1. New manholes must be added where the distance is too far
between existing manholes.
2. Existing manholes must be rehabilitated where storm water and
ground water infiltrates into the system.
3. Private service lines must be repaired to prevent infiltration.
4. Existing wastewater mains must be repaired where infiltration
occurs.
• 5. Additional sewer maintenance equipment and confined space entry
equipment must be purchased in order to comply with EPA
standards.
6. The City must purchase and monitor flow meters within the system
in order to detect infiltration.
7. Existing wastewater mains that are too small must be replaced with
larger lines.
•
Table 20. Total S stem Rehabilitation Method Cost Summar
Rehabilitation Cost Summary
Rehab No. Rehabilitation Method No. of Units Unit Cost Total Cost
1000 Locate and Expose MH 60 EA $100 $6,000
1001 Locate MH and Raise Casting to Grade 5 EA $400 $2,000
1002 Clean MH -Could Not Inspect 3 EA $100 $300
1010 Install MH Insert 5 EA $100 $500
1020 Realign and Grout Casting 25 EA $350 $8,750
1022 Replace Casting (Frame and Lid) 2 EA $450 $900
1024 Replace Casting (Lid Only) 1 EA $150 $150
1040 Clean MH, Repair as Needed & Coat 153 VF $70 $10,728
1042 Clean MH Bottom, Stop I/I, Repair as Needed & Coat to 1' 13 EA $200 $2,600
Above Pipe Crown
1050 Stop I/I, Clean, Repair as Needed & Coat Entire MH 542 VF $75 $40,635
1052 Clean MH Bottom, Stop I/I, Repair as Needed & Coat to 1' S8 EA $250 $14,500
Above Pipe Crown
1060 Remove roots, Clean MH, Repair as Needed & Coat Entire 101 VF $80 $8,069
MH
1062 Clean MH Bottom, Remove Roots, Repair as Needed & 5 EA $300 $1,500
Coat to 1' Above Pipe Crown
1110 Construct /Reconstruct MH Invert 8 EA $350 $2,800
1210 Structurally Repair and Coat Entire MH 55 EA $150 $8,250
1998 Install Manhole 33 EA $2,000 $66,000
1999 Install Clean Out 39 EA $300 $11,700
3330 Replace Missing Cleanout Cap on Private Service Line 66 EA $50 $3,300
3340 Repair Broken Cleanout on Service Line 18 EA $250 $4,500
3360 Point Repair on Service Line 26 EA $450 $11,700
3400 Replace Section of Service Line 6 EA $600 53,600
4330 Replace Missing Cleanout Cap on Main Line 2 EA $50 $100
4350 Disconnect Abandoned Service Line 1 EA $450 S450
4360 Point Repair on Mainline or Municipal Service Line 193 EA Varies 5202,500
4370 Point Repair under Pvmt. on Mainline or Municipal Service 133 EA Varies $165,900
Line
4392 TV Line, Dye Test and Disconnect Storm Line on Mainline 3 EA Varies $4,400
Under Pvmt.
4510 Clean Line & Install Cured-In-Place Liner 2,209 EA Varies $115,379
4515 Open Service Connections to CIP Liner 13 EA $250 $3,250
4530 Clean Line & Install Liner By Pipe Bursting 4,677 EA Varies $282,540
4535 Open Service Connections to PB Liner 41 EA Varies $33,850
4999 Recommended Capacity Increases 1 LS $1,856,416 $1,856,415
5000 Clean Line Segment 13,159 LF $1 $16,449
5001 Sewer Maintenance Equipment 1 EA $170,000 $170,000
5002 Confined Space Entry Equipment 1 LS $4,955 $4,955
5003 Flow Monitoring Meters 1 LS $211,993 $211,993
TOTAL COST $3,276,661
CONTINGENCY $327,666
ENGINEERING AND INSPECTION $540,649
TOTAL ESTIMATED RECOMMENDED REPAIR COST $4,144,977