HomeMy Public PortalAbout20140910 TE Grant - Byers_N Campbell Streetscape Estimate.pdfItem Description Qty Unit Unit Price Total Price
1 Traffic Control 1 LS 40,000.00$ 40,000.00$
2 Grading Complete 1 LS 150,000.00$ 150,000.00$
3 Driveway Concrete 1088 SY 60.00$ 65,280.00$
4 Concrete Valley Gutter 192 SY 70.00$ 13,440.00$
5 Concrete Curb & Gutter 6556 LF 20.00$ 131,120.00$
6 Remove & Replace Signs 24 EA 60.00$ 1,440.00$
7 Brick Pavers 19668 SF 10.00$ 196,680.00$
8 Signal Upgrades 1 LS 15,000.00$ 15,000.00$
Subtotal 612,960.00$
Contingency (20%)122,592.00$
Preliminary Concept Construction Estimate Total 735,552.00$
PRELIMINARY CONCEPT COST ESTIMATE
BYERS AVE. TO NORTH CAMPBELL ST. STREETSCAPE