HomeMy Public PortalAbout20141113 Change Order1.pdfJ-24609/Change Order #1
TYBEE ISLAND W&S IMPROVEMENTS
DIV I – JONES AVENUE WATER MAIN IMPROVEMENTS
DIV II – FORCE MAIN REPLACEMENT
CITY OF TYBEE ISLAND, GA
CHANGE ORDER NO. 1
J-24609
PROJECT: Tybee Island W&S Improvements
PROJECT NO.: 24609 DATE: 11/13/14
OWNER: City of Tybee Island, GA
CONTRACTOR: BRW Construction Group, LLC
The Contractor is hereby requested to comply with the following changes from the contract plans and
specifications:
Item #
Description of Changes – Quantities, Unit
Prices, Units, Etc.
Decrease In
Contract Price
Increase In
Contract Prices
See attached $ 275,088.75
Total DECREASE
Total INCREASE
Difference Col. (1) and (2)
Net DECREASE/INCREASE Contract Price $ 275,088.75
The sum of $275,088.75 is hereby added to the total contract price of $1,198,221.50 and the total contract price
to date is $1,473,310.25.
The time provided for completion in the contract is unchanged/increased/decreased by 60 calendar days.
This document shall become an amendment to contract and all provisions of the contract will apply hereto.
ACCEPTED BY: DATE:
BRW Construction Group, LLC
RECOMMENDED BY: DATE:
Thomas & Hutton
REVIEWED BY: DATE:
APPROVED BY: DATE:
City of Tybee Island