Old Business:
North Beach Restrooms – Update
City Hall Needs Assessment – Update
Proposed Upgrades to Jones Avenue Paving Project
Consideration of amending project cost (change order) for with R.B. Baker Construction ($156,153.35 for paving and three stamped pedestrian cross-walks and appropriate signage at 4th,
8th and 15th Street intersections) to upgrade the paving mix to a higher grade and to add a tack coat(s). Staff recommends Alternative B. Cost of either alternative is within budget
cost for project of $178,000
Alternate A: $7,500 additional cost - This alternative added scope will cover additional material cost of a bituminous tack coat application of approximately 680 gallons and additional
labor and equipment cost associated with two process – Total cost of project would go from $156, 153.35 to $163,653.35.
Alternative B: $19,500 additional cost – This alternative added scope to cover the additional material cost of the Open Graded Interlayer mixture, bituminous tack coat application of
approximately 1,200 gallons and the additional labor and equipment cost associated with the two processes.- Total cost of project would go from $156,153.53 to $175,653.53.