HomeMy Public PortalAbout20140931Burts try at schedule.docSchedule for Tybee Renourishment
Starting North from where the 01 Submerge line comes on shore
13-18 October Mob Dredge “ALASKA”
18 October start between 7th and 8th street
21 October 7th street
23 October 6th street
25 October Center Street
28 October 3rd street
4 November 1st street (big curve)
9 November gate access Fort Screven
14 November Officers Row
19 November Gullick Street
24 November middle of North Beach parking lot
30 November North Federal Groin
1 December Back River
2 December 16th street
3 December 17th street
4 December 19th street
5 December South Groin
6 December 15th street
7 December 14th street
8 December 13th street
9 December 12th street
13 December 11th street
16 December 10th street
17 December 9th street
18 December 8th street
19-27 Break down equipment and start demob
29-30 December Remove subline from beach
1 January Done