HomeMy Public PortalAbout2022.06.09 Relocation Agreement-State StreetInternal Use Only
UTILITY RELOCATION COST AGREEMENT
State Street (from Forest to W. Lake Street) Overhead Relocation and Conversion to
Underground – Summer 2022
THIS AGREEMENT (“this Agreement”) made and entered into this 9th day of June
2022, by and between the City of McCall 216 E. Park Street, McCall, ID. hereinafter referred to
as the “the City”, and IDAHO POWER COMPANY, hereinafter referred to as the “Company”.
PURPOSE: It is requested for the Company to perform utility relocation of some, or all
of its facilities located in or about the construction area to accommodate the Project. This
Agreement sets out the terms by which the Utility Relocation will occur, and how costs incurred
by the Company shall be reimbursed to the Company by the City.
THE PARTIES, in consideration of the mutual promises contained herein, and other good
and valuable consideration, the receipt and sufficiency of which are acknowledged, agree as
follows:
DEFINITIONS:
1. Project – The work defined by the plans and specifications developed by Idaho Power
and the City of McCall for the project identified by the City as “State Street (from Forest
to W. Lake Street) Overhead Relocation and Conversion to Underground – Summer
2022” attached hereto as Exhibit A.
Utility Relocation – Modification in place, relocation or reconstruction of Company
facilities to accommodate the Project.
TERMS:
1. Property Rights
A) The City will reimburse the Company for the Cost of Utility Relocation.
B) Prior to the Utility Relocation, the City will; reimburse the Company for costs
incurred in securing new easements or property rights outside the Project right-of-way; or (2)
provide sufficient space within the current or expanded Project right-of-way, for the new location
of the Company’s facilities as shown on the Project Drawings.
2. Relocation or Modification of Company Facilities
DocuSign Envelope ID: F97EA359-DAFE-483C-A320-FBE02C11D831
Internal Use Only
A) The Company shall arrange for all labor, materials, and equipment, including
survey services, necessary for the completion of Utility Relocation as shown on the Project
Plans.
B) Utility Relocation may either be done with Company forces and equipment or by
a contract awarded by the Company.
(C) The Company shall furnish to the City detailed plans, specifications, and
estimates of cost. The City acknowledges that such plans, specifications, and estimates of cost
represent the Company’s current plans and estimates; however, they are subject to change
without penalty to the Company. The Company will communicate any material changes to the
plans, specifications and estimates of cost to the City on a timely basis.
(D) The Company shall furnish a work schedule, including dates for begin and end of
work, to the City prior to the start of Utility Relocation. This work schedule is to include any
activities or work required by the City necessary for the completion of Utility Relocation.
Revised work schedules are to be furnished to the City when requested. The parties understand
that the Work Schedule represents the Company’s current good faith estimate for its relocation
work for the Project, but the Work Schedule is subject to change, and the Company will have no
liability to the City for changes to the Work Schedule. The Company will communicate any
material changes to the Work Schedule to the City on a timely basis. The Company shall not
commence Utility Relocation prior to issuance of a Public Works Permit from the City.
(E) The Company shall notify the City 48 hours prior to start of Utility Relocation.
(F) The Company shall notify the City in writing of the date when Utility Relocation is
completed.
(G) The City must issue a Public Works Permit to the Company (or its designated contractor)
authorizing work to commence within the City ROW and/or property prior to any construction
activities.
3. Estimated Cost, Submission and Payment of Billings
A) The City will reimburse the Company for the actual cost of Utility Relocation.
The estimated Cost of Utility Relocation (“Estimated Cost”) is $512,189.00. The parties
recognize and agree that the Estimated Cost is provided solely for budgeting purposes, may be
greater or lesser than the actual Cost of Utility Relocation, and is not binding on either party.
Copies of the data and information upon which the Estimated Cost is based are attached hereto as
Exhibit B.
B) The Company shall submit a final bill to the City for reimbursement of the total
Cost of Utility Relocation within one hundred twenty (120) days after completion of the work.
All billings shall include supporting documentation substantiating the cost of Utility Relocation.
DocuSign Envelope ID: F97EA359-DAFE-483C-A320-FBE02C11D831
Internal Use Only
C) The City shall pay progress billings within forty-five (45) days and final billing
within ninety (90) days after receipt of the bills. All payments are subject to the findings of a
final audit by the City.
D) Reference to the Project Number(s) shall be indicated on all bills, correspondence,
and records pertaining to this Project.
4. Disposal of Materials
The City shall be afforded a reasonable opportunity to inspect materials recovered by the
Company prior to disposal by sale or scrap. Upon written request by the City, the Company
shall notify the Highway Authority of the time and place where the material will be available for
inspection.
5. City of McCall and Company Contact Persons
A) The Company is to submit billings, documents and coordinate all Utility
Relocation activities through the City’s contact person of:
Nathan T. Stewart, P.E.
McCall Public Works Director, City Engineer
216 E. Park Street,
McCall, ID 83638
The City may change its contact person by notifying the Company in writing.
B) The City is to coordinate all Utility Relocation activities through the Company’s
contact person of:
Ethan Morgan
Idaho Power Company
1221 W. Idaho St.
Boise, ID 83702
(208) 388-6510
The Company may change its contact person by notifying the City in writing.
6. Choice of Law and Severability
A) This Agreement is governed by the laws of the State of Idaho. If a term of this
Agreement is determined to be illegal by competent authority, it will not invalidate the remaining
terms of this Agreement.
DocuSign Envelope ID: F97EA359-DAFE-483C-A320-FBE02C11D831
DocuSign Envelope ID: F97EA359-DAFE-483C-A320-FBE02C11D831
Internal Use Only
Exhibit A – Project Plans
DocuSign Envelope ID: F97EA359-DAFE-483C-A320-FBE02C11D831
DocuSign Envelope ID: F97EA359-DAFE-483C-A320-FBE02C11D831
DocuSign Envelope ID: F97EA359-DAFE-483C-A320-FBE02C11D831
DocuSign Envelope ID: F97EA359-DAFE-483C-A320-FBE02C11D831
Internal Use Only
Exhibit B – Cost Estimate
2022 estimate for
ACA
Labor & Equipment estimate $ 290,348.00
Material $ 181,841.00
Engr/PM/Inspect. $ 25,000.00
Other $ 15,000.00
Total $ 512,189.00