Re: LHTAC Quarterly Progress Report
City of McCall
Robert Giles
216 E. Park St.
McCall , ID 83638
Dear Mayor Giles ,
RECEIVED
JUL 1 J 2022
The Local Highway Technical Assistance Council (LHTAC) provides an important
linkage between Local Highway Jurisdictions (LHJs) and the Idaho Transportation
Department in the utilization of Federal-aid highway funds available to the LHJs in
Idaho . This letter includes the status listing of current and upcoming LHTAC projects
for District 3.
LHTAC is committed to helping sponsors through the Federal-aid process and
developing a successful project. We hope you find this information informative. If you
have any questions or need any additional information, please contact our staff at 208-
344-0565 .
Sincerely ,
Laila Kral , P.E.
Administrator
Local Highway Technical Assistance Council
Association of Id aho Cities
Mayor Mac Pooler
City of Kellogg
Mayor Robert (BJ) Berlin
Oty of Roberts
Councilwoman Kari Peterson
City of Fruitland
Idaho Associatio n of Highway Districts
Commissioner Neal Gier
Buhl Highway District
Commissioner Kevin Renfrow
South Latah Highway Dis trict
Commissioner Gilbert Hofmeister
Power County Highway District
Idaho Association of Counties
Commissioner Phil Lampert
Benewah County
Commissioner Marlc Rekow
Gem County
Commissioner Todd Smith
Madison County
Ex·Officio Members
Kelley Pac ker, Execu t ive Director
Association of fdaho Cities
Nick Veldhouse, Executive Director
fdaho Association of Highway Districts
Seth Grigg. Executive Director
Idaho Association of Counties
..
V
District 3 Projects in Construction Phase
Quarterly Update April through June 2022
Bike/Ped Br Over Boise River, Sponsor: City of Eagle, Key#: 20841
Description: This project consists of design and construction of a bicycle and pedestrian bridge over
the north channel of the Boise River adjacent to the SH-55 (Eagle Rd .) Bridge . The bicycle and
pedestrian bridge will provide a critical link between the Boise River Greenbelt, planned pathways , and a
rapidly growing residential and commercial core area in the City of Eagle .
Status: The project was awarded and construction is anticipated to start October 2022
Project Manager: Amanda LaMott
Construction Year: 2023
Stoddard Path Ext PH 1, Sponsor: City of Nampa, Key #: 22050
Description: The Stoddard City Pathway (Iowa to Amity) project is an extension of the existing
Stoddard Pathway located in Nampa , Canyon County . The current Stoddard Pathway is approximately 2-
miles and connects neighborhoods to parks and schools in southeast Nampa . This extension would add
approximately %-mile to the paved trail starting at Iowa Avenue and ending at Amity Avenue.
Status: This project is currently in construction and approximately 99 % complete . The anticipated
completion date is Summer 2022 .
Project Manager: Amanda LaMott
Construction Year: 2020
Stoddard Path Ext, PH 2, Sponsor: City of Nampa, Key #: 22070
Description: The purpose of this project is to extend the Stoddard Pathway from Amity Avenue to
Sherman Avenue . The Stoddard City Pathway (Amity to Sherman) extension will provide a safe route to
Sherman Elementary . Students and pathway users will be able to utilize an existing crosswalk with a
Rapid Flashing Beacon at the Amity Avenue crossing . The project will also tie into the proposed
Stoddard City Pathway (Iowa to Amity), creating approximately 2 and % miles of continuous trail.
Status: This project is currently in construction and approximately 99 % complete . The anticipated
completion date is Spring 2022 . We are wating for the seed to finish the three months for warranty and
still need to finalize charging liquidated damage to the Contractor . The final payment has not been
made .
Project Manager: Amanda LaMott
Construction Year: 2020
ll Page July 5 , 2022
District 3 Projects in Construction Phase
Quarterly Update April through June 2022
S. 4th Ave, Indian Creek Bridge, Sponsor: City of Caldwell, Key#: 22593
Description: This project will replace the S . 4th Avenue bridge (ITD Bridge Key 27590) over Indian
Creek in Caldwell. This bridge replacement is part of a Competitive Highway Bridge Program grant and is
bundled with seven bridges in southern Idaho . The new bridge will be single-span and constructed with
prestressed vo ided slabs .
Status: This project has been awarded and construction is anticipated to begin in October 2022 .
Project Manager: Matt Koster
Construction Year: 2021
North Fork Boulder Creek Bridge, Sponsor: Owyhee County, Key #: 22594
Description: This project will replace the bridge over the North Fork Boulder Creek on Flint Creek
Road (ITD Bridge Key 28270) in Owyhee County. This bridge replacement is part of a Competitive
Highway Bridge Program grant and is bundled with seven bridges in southern Idaho . The new bridge will
be a single-span prefabricated steel girder bridge with GRS-IBS abutments .
Status: This project has been awarded and construction is anticipated to begin in September 2022 .
Project Manager: Matt Koster
Construction Year: 2021
FY22 Stoddard Pathway, Sponsor: City of Nampa, Key #: 22944
Description: The Stoddard pathway (Sherman Avenue to 2nd Street South) project is an extension of
the pathway adding approximately 0 .3 miles to the paved tra il.
Status: This project was advertised and is in the process of being awarded. Construction anticipated to
start Spring 2023 .
Project Manager: Amanda LaMott
Construction Year: 2022
21 Page July 5 , 2022
District 3 Projects in Design Phase
Quarterly Update April through June 2022
Middleton & Ustick Roundabout, Sponsor: City of Caldwell, Key#: 13487
Description: This project will improve a four-way stop at the Middleton Road and Ustick Road
Intersection by building a roundabout to help traffic flow and congestion .
Status: The project is in Final Design . The Right-of-Way acquisition is in progress by the
Sponsor. The sponsor has requested that a supplemental agreement be negotiated to modify
the design of the west leg of the roundabout to accommodate the newly planned widening of
Ustick Avenue to four lanes to the west of this project. The supplemental agreement is in the
negotiation process.
Project Manager: Wayne Herbel
Construction Year: 2025
Old Hwy 30/Plymouth St Bridge Replacement, Sponsor: Canyon HD, Key #: 13494
Description: This project includes construction of a new bridge at a new location along with
additional canal crossings and 2200 feet of new approach roadway . The existing bridge will be
left in place to serve pedestrians and bicyclists and provide connectivity for the City of Caldwell's
Greenbelt pathway .
Status: Preliminary Design Plans are in development and the consultant is working on the
Environmental Document. Due to rising construction prices and funding concerns , this project
will be delayed while additional funding sources are explored . A supplemental agreement has
been executed for bridge design over the Riverside Canal.
Project Manager: Wayne Herbel
Construction Year: 2023
N 10th Ave ITS & Overlay, Sponsor: City of Caldwell, Key#: 13905
Description: This project will overlay a one-half mile section of 10th Avenue in Downtown
Caldwell from the Railroad Overpass to 1-84 to replace the roadway surface that is in poor
condition. The project also includes installing intelligent transportation system (ITS) components
to connect signals and bring pedestrian facilities to current standards .
Status: The consultant for this project has submitted the PS&E package . The project is waiting
for construction funding .
Project Manager: Wayne Herbel
Construction Year: 2026
Page 11 July 5, 2022
District 3 Projects in Design Phase
Quarterly Update April through June 2022
Rail with Trail Pathway, Sponsor: City of Meridian, Key #: 13918
Description: This project constructs a multi-use pathway either along or parallel to the railroad
tracks for one-half mile near Downtown Meridian . City of Meridian is completing design with
local funds .
Status: The project is in preliminary design . The Right-of-Way acquisition for this project is
being done by the City of Meridian .
Project Manager: Amanda LaMott
Construction Year: 2026
Peckham Road Rehabilitation, Sponsor: Golden Gate HD, Key #: 13964
Description: The project will improve 3 .75 miles of Peckham Road between US-95 and Notus
Rd . It includes curb , gutter and sidewalk in select locations within the city limits of Wilder and
Greenleaf.
Status: Draft PS&E Submittal was received on 7/16/2021. The project is experiencing delay
due to permitting requirements for the railroad crossing . This project will be delayed to FY2023 .
Project Manager: Wayne Herbel
Construction Year: 2022
Desert Canyon Trail BikePed, Sponsor: City of Mountain Home, Key#: 18827
Description: This project consists of construction of sidewalks , bicycle lockers , shelters ,
benches , drinking fountains , lighting , and information boards on the Desert Canyon Trail in
Mountain Home .
Status: The City of Mountain Home continues working on a revised Plan , Specifications , and
Est imate (PS&E) Submittal so that this project can be re-advertised .
Project Manager: Kevin Kuther
Construction Year: 2019
Cove Rd Bridge, Washington Co, Sponsor: Washington County, Key#: 19129
Description: This project is for work to replace the 3-span steel truss bridge on Cove Road
over the Weiser River with a 2-span steel girder bridge , and raise the approach grades.
Status: The project consultant is preparing right-of-way and Final Design plans .
Project Manager: Scott Wood
Construction Year: 2025
Page 12 July 5, 2022
District 3 Projects in Design Phase
Quarterly Update April through June 2022
Old Hwy 30; Goodson to Oasis, Sponsor: Canyon HD, Key#: 19951
Description: The project will rehabilitate approximately 3.4 miles of Old Highway 30 , a major rural
collector serving northern Canyon County , as well as southern Payette and Gem Counties . This is the
final phase of rehabilitating Old Highway 30 from the vicinity of Caldwell to Payette County.
Status: The consultant is working on final permits and Plan , Specification , and Estimate (PS&E)
submittal to obligate construction funds .
Project Manager: Dan Coonce
Construction Year: 2027
Sand Hollow Rd; Oasis to Bl Canyon, Sponsor: Payette County, Key #: 20019
Description: This is phase 2 of the improvements on Sand Hollow Road . This phase is 4 .7 miles (from
Black Canyon Road to Oasis Road). The project includes rehabilitating asphalt pavement (pavement
repair and overlay) and upgrading guardrail at existing structures .
Status: This project design is complete . Currently the project is programmed for 2024 construction year.
Project Manager: Muhammad Zubery
Construction Year: 2024
Ola Hwy; Powerline Rd to 2nd Fork Rd, Sponsor: Gem County, Key#: 20100
Description: The Ola Highway Improvement project is located near the unincorporated community of
Ola in Gem County and is anticipated to overlay two miles of existing pavement and pave three miles of
existing gravel road to keep paved roads good and also to pave a road that exceeds the Averge Daily
Traffic for a gravel type surface .
Status: The draft Plans , Specification and Estimate (PS&E) package is on file . Utility coordination with
Idaho Power continues .
Project Manager: Muhammad Zubery
Construction Year: 2027
Mission Street; Southern City Limits to Deinhard Lane, Sponsor: City of McCall, Key #:
20146
Description: The Mission Street Rehabilitation project is located in the City of McCall in Valley County
and is anticipated to include the removal of the existing asphalt surface , widening of the road section ,
verifying the structural integrity of the base and sub-base , new asphalt pavement, striping , utility
relocations and the installation of storm water conveyance and treatment systems to improve the
condition of the roadway . It is also anticipated to include the design of a multi-use pathway adjacent to
the roadway .
Status: Design Approval was granted on 4/1/2022 . The consultant is currently working on Final Design .
Project Manager: Wayne Herbel
Construction Year: 2027
AdYocate I Su"'°"
""" Page 13 July 5, 2022
District 3 Projects in Design Phase
Quarterly Update April through June 2022
Old Hwy 30: Old Oregon Trail Rd To E 54th S St, Sponsor: Mountain Home HD,
Key#: 20182
Description: The Old HWY 30 ; Old Oregon Trail Road to E 54th Street project will pulverize
the existing surface to construct a 1 foot Cement Recycle Asphalt Base (CRAB) layer and a new
asphalt overlay . Additionally , guardrail along the southbound lane , will be replaced to improve
safety for all roadway users near the intersection with Old HWY 30 .
Status: Contract completion date was 12/31/2019, project not schedule for construction
obligation until 2024 (October 2023). This project has been completed and is on the shelf
awaiting construction funding obligation.
Project Manager: Dan Coonce
Construction Year: 2024
Eastside Drive Bridge, Sponsor: Valley County. Key #: 20230
Description: This project includes reconstruction of the deteriorated bridge and extends the
length to push the abutments beyond the channel limits in order to minimize potential for future
scour. The bridge length would extend to approximately 120', meaning that the new abutments
would extend 16' beyond the exiting abutments .
Status: The project is out to bid . Bid opening is on July 19 , 2022
Project Manager: Scott Wood
Construction Year: 2025
E Lake Fk Rd; E Lake Fk Cr Br To Sh55 1 Sponsor: Valley County. Key#: 20242
Description: This is a rehabilitation project of 0 .55 mile long on East Lake Fork Road between
Lake Fork Creek Bridge and the intersection with SH 55 . This project is expected to widen the
roadway and lessen the vertical grade near the SH-55 intersection to bring it into compliance
with current standards . Additional improvements will include replacing deteriorated culverts at
an irrigation canal crossing , acquiring right-of-way , and mitigating impacts to wetlands adjacent
to the roadway .
Status: The consultant is currently developing Preliminary Design Plans and working on the
Environmental Document.
Project Manager: Dan Coonce
Construction Year: 2027
Simco Rd Rehabilitation, Sponsor: Mountain Home HD. Key #: 21981
Description: This project will rehabil itate a 5 mile stretch of Simco Road . This is a rural
asphalt surface and a major collector in Elmore County .
Status: The draft Plans , Specifications and Estimate (PS&E) package is on file .
Project Manager: Muhammad Zubery
Construction Year: 2027
• Aavoate JSupport
"''" Page 14 July 5 , 2022
District 3 Projects in Design Phase
Quarterly Update April through June 2022
Midway Rd; Karcher to Caldwell Blvd, Sponsor: Canyon HD, Key #: 22016
Description: This project will rehabilitate pavement and construct shared-use shoulders on
Midway Road between SH-55(Karcher Road ) and l-84B (Caldwell Boulevard) in Canyon County .
Status: The Final Design Submittal has been received and review is underway .
Project Manager: Dan Coonce
Construction Year: 2027
Cherry Ln; Franklin Blvd to 11th Ave N, Sponsor: City of Nampa, Key#: 22017
Description: This project will rebuild Cherry Lane from 11th Ave North to Franklin Boulevard .
Status: The consultant is currently developing Preliminary Design Plans and working on the
Environmental Document.
Project Manager: Dan Coonce
Construction Year: 2027
Montana Ave; Ped lmprv & Widening, Sponsor: City of Caldwell, Key#: 22018
Description: This project will construct sidewalk from Syringa Middle School to Spruce St reet
on the West Side of Montana Avenue in the City of Caldwell. The project includes pedestrian
crossing and rectangular rapid flashing beacon cross i ng at the Alder Street and Spruce Street
intersections across Montana Avenue.
Status: The consul t ant is currently develop ing Prelim inary Des ign Plans and working on the
Env ironmental Document.
Project Manager: Amanda LaMott
Construction Year: 2027
Peckham Rd Intersections, Sponsor: Golden Gate HD, Key #: 22101
Description: This project will reconstruct three intersection on Peckham Road at Travis Road ,
Allendale Road and Van Slyke Road . Each intersection is substanda rd for truck turning
movements . The reconstruction will provide large turning radii to eliminate truck off-tracking and
reduce edge breakup . The intersection improvements will also allow trucks to ma intain their own
travel lane while making turns.
Status: Draft Plans , Specifications & Estimat e (PSS&E) Submittal was received on 7/16/2021 .
The project is expe riencing delays due to pe rm itting requ irements for the railroad crossing . Th is
project will likely be delayed to FY23 .
Project Manager: Wayne Herbel
Construction Year: 2022
ru6
AdYoc.lte l Suppott
''"" Page IS July 5 , 2022
District 3 Projects in Design Phase
Quarterly Update April through June 2022
Franklin Blvd & Karcher Rd Int, Sponsor: City of Nampa, Key #: 22102
Description: This project will construct a dual lane offset roundabout at Franklin Blvd . and
Karcher Rd . in the City of Nampa . The project includes right-of-way , curb and gutter, sidewalk ,
lighting , pedestrian ramps and lane widening.
Status: The Sponsor has request a project construction obligation delay. The project is
scheduled for 2022 but due to the right-of-way acquisition delays would like to move to FY23 .
Project Manager: Dan Coonce
Construction Year: 2022
Int 3rd Ave N & W Industrial Rd, Sponsor: City of Nampa, Key#: 22103
Description: This project will install a new signalized intersection approximately one quarter
mile south of the existing Franklin Blvd . and Industrial Rd . intersection in the City of Nampa.
Status: The Concept Report was approved on June 30 , 2021 . The next phase of work will
begin once funding becomes available after July 2022 when the Freight Program Plan is
approved .
Project Manager: Dan Coonce
Construction Year: 2023
Ditto Cr & Reservoir Rd. Sponsor: Mountain Home HD, Key#: 22405
Description: This project will be improving sections of the rural roadways by redesigning the
alignments horizontal and vertical curves to current geometric standards and will add a paved
surface to the roadway improving skid resistance .
Status: The consultant is preparing the project Plan , Specifications , and Estimate (PS&E)
package .
Project Manager: Brian Wright
Construction Year: 2022
Page 16 July 5, 2022
District 3 Projects in Design Phase
Quarterly Update April through June 2022
Recreational Roads Signing, Sponsor: Valley County, Key #: 22406
Description: The scope of the Recreational Roads Signing & Delineation Safety
Improvements project , located in Valley County , will be accomplished by providing extra
signage to help drivers safely navigate the roadways and increase driver awareness of corners
at various locations along recreational roads within Valley County.
Status: LHTAC is working on Project Development for this project.
Project Manager: Brian Wright
Construction Year: 2022
Pine-Featherville Rd Rehab, Mt Home HD, Sponsor: Mountain Home HD, Key#:
22606
Description: This project will rehabilitate the roadway surface with the use of CRABS (Cement
Recycled Asphalt Base Stabilization) process . The paved roadway currently varies between 22
feet and 26 feet wide with approximately 1 foot gravel shoulder on both sides of the road . The
new design would maintain 26 feet of pavement with 2 foot gravel shoulders. The project will
also include the replacement of one set of culverts at Dog Creek with a clear span bridge .
Status: The consultant is currently working on the Concept Report.
Project Manager: Dan Coonce
Construction Year: 2023
Simco Road Safety Improvements, Sponsor: Mountain Home HD, Key#: 22879
Description: This project will improve safety for all roadway users by redesigning the
alignment's horizontal and vertical curves , adding flashing LED curve warning signs , and
rehabilitation of the asphalt surface.
Status: This has been combined with KN 21981 . The draft Plans , Specifications and Estimate
package is in file .
Project Manager: Muhammad Zubery
Construction Year: 2024
Pine-Featherville Rd Rehab, Sponsor: Mountain Home HD, Key#: 22889
Description: This project will rehabilitate the Pine-Featherville Road by using a RABS
(Recycled Asphalt Base Stabilization) or CRAB (Cement Recycled Asphalt Base) process in
conjunction with a new layer of plant mix asphalt.
Status: The consultant is currently working on the Concept Report.
Project Manager: Dan Coonce
Construction Year: 2023