HomeMy Public PortalAbout11406 O R D I N A N C E NO. 11406
AN ORDINANCE, appropriating Three Hundred Thousand Dollars
($300,000.00) from the Operation, Maintenance and Construction Improvement Fund
of the Seminary Branch of River des Peres to be used for project costs for the
construction of storm sewers in Innisfail Storm Channel Phase III (88041C), in the
City of Webster Groves, Missouri; and authorizing the Executive Director and
Secretary-Treasurer on behalf of The Metropolitan St. Louis Sewer District to enter
into a contract with Unnerstall Contracting Company, LTD. for the construction of the
aforesaid storm sewers.
WHEREAS, the bid for the construction of said storm sewers is Two
Hundred Seventy-four Thousand Three Hundred Sixty-four Dollars ($274,364.00), and
the allowance for construction change orders is Twenty-five Thousand Six Hundred
Thirty-six Dollars ($25,636.00), and
WHEREAS, the State of Missouri has agreed to contribute Seventy-five
Thousand Dollars ($75,000.00) toward the costs of said project; upon the receipt of such
funds from said source, said money will be returned to the Operation, Maintenance and
Construction Improvement Fund of the Seminary Branch of the River des Peres, and
WHEREAS, the Director of Finance has certified that there is an
unencumbered balance in the above-named fund sufficient to pay the obligation
authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF
TRUSTEES OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
2
Section One. The sum of Three Hundred Thousand Dollars ($300,000.00)
is hereby appropriated from the Operation, Maintenance and Construction
Improvement Fund of the Seminary Branch of River des Peres to be used for project
costs for the construction of storm sewers in Innisfail Storm Channel Phase III
(88041C), in the City of Webster Groves, Missouri.
Section Two. The Executive Director and Secretary-Treasurer are hereby
authorized on behalf of The Metropolitan St. Louis Sewer District to enter into a
contract with Unnerstall Contracting Company, LTD. as the lowest responsible bidder
for the construction of storm sewers in Innisfail Storm Channel Phase III (88041C), in
the City of Webster Groves, Missouri, pursuant to bids received and opened on the 18th
day of November, 2002.
Section Three. This ordinance, being an appropriation ordinance,
shall take effect immediately upon its enactment.
The foregoing Ordinance was adopted December 13, 2002 by the following vote –
Ayes – C.D. Seward, A. J. Soukenik, T.W. Purcell, M.C. Williams, J.W. Siscel, and
J.M. Swartz.
Nays – None.
Secretary-Treasurer