HomeMy Public PortalAbout11605O R D I N A N C E NO. 11605
AN ORDINANCE, appropriating Four Hundred Ninety-three
Thousand Dollars ($493,000.00) from the Sanitary Replacement Fund for
construction phase services for Fenton Wastewater Treatment Plant
Improvements Construction Phase Services (2001068A); and authorizing
the Executive Director and Secretary-Treasurer on behalf of The
Metropolitan St. Louis Sewer District to enter into Contract E-1065 with
Abna Engineering, Inc. for the aforesaid construction phase services.
WHEREAS, the Director of Finance has certified that there is
an unencumbered balance in the above-named fund sufficient to pay the
obligation authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF
TRUSTEES OF THE METROOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of Four Hundred Ninety-three
Thousand Dollars ($493,000.00) is hereby appropriated from the
Sanitary Replacement Fund for construction phase services for Fenton
Wastewater Treatment Plant Improvements Construction Phase Services
(2001068A).
Section Two. The Executive Director and Secretary-
Treasurer are hereby authorized on behalf of The Metropolitan St. Louis
Sewer District to enter into Contract E-1065 with Abna Engineering, Inc.
for construction phase services for Fenton Wastewater Treatment Plant
Improvements Construction Phase Services (2001068A); said contract
amendment to be comprised of such terms and conditions as are
approved by the office of the General Counsel of the District.
Section Three. This ordinance, being an appropriation
ordinance, shall take effect immediately upon its enactment.
The foregoing Ordinance was adopted October 9, 2003.