HomeMy Public PortalAbout12227O R D I N A N C E NO. 12227 AN ORDINANCE, appropriating Four Hundred Thirty
Thousand Dollars ($430,000.00) from the Sanitary Replacement Fund to be
used for project costs for the construction of CSO - Interceptor Access and
Monitoring Improvements Phase II (Miller Pressure Sewer) (2003054B), in
the City of St. Louis, Missouri; and authorizing the Executive Director and
Secretary-Treasurer on behalf of The Metropolitan St. Louis Sewer District to
enter into a contract with Gershenson Const. Co., Inc. for the construction of
the aforesaid construction.
WHEREAS, the bid for said construction is Three Hundred
Eighty-nine Thousand Two Hundred Twenty Dollars ($389,220.00), and the
allowance for construction change orders is Forty Thousand Seven Hundred
Eighty Dollars ($40,780.00), and
WHEREAS, the Director of Finance has certified that there is
an unencumbered balance in the above-named fund sufficient to pay the
obligation authorized herein,
NOW, THEREFORE, BE IT ORDAINED BY THE BOARD OF
TRUSTEES OF THE METROPOLITAN ST. LOUIS SEWER DISTRICT:
Section One. The sum of Four Hundred Thirty Thousand
Dollars ($430,000.00) is hereby appropriated from the Sanitary Replacement
Fund to be used for project costs for the construction of CSO - Interceptor
Access and Monitoring Improvements Phase II (Miller Pressure Sewer)
(2003054B), in the City of St. Louis, Missouri.
Section Two. The Executive Director and Secretary-Treasurer
are hereby authorized on behalf of The Metropolitan St. Louis Sewer District
to enter into a contract with Gershenson Const. Co., Inc. as the lowest
responsible bidder for the construction of CSO - Interceptor Access and
Monitoring Improvements Phase II (Miller Pressure Sewer) (2003054B), in
the City of St. Louis, Missouri, pursuant to bids received and opened on the
6th day of April, 2006.
Section Three. This ordinance, being an appropriation
ordinance, shall take effect immediately upon its enactment.
The foregoing Ordinance was adopted 6/8/06.